Work in accordance with Sections 13.5.2 and 13.5.3, whether or not such Work is fabricated, installed or completed.
<br />However, neither this authority of the Architect nor a decision made in good faith either to exercise or not to
<br />exercise such authority shall give rise to a duty or responsibility of the Architect to the Contractor, Subcontractors,
<br />material and equipment suppliers, their agents or employees, or other persons or entities performing portions of the
<br />Work.
<br />§ 4.2.7 The Architect will review and approve, or take other appropriate action upon, the Contractor's submittals
<br />such as Shop Drawings, Product Data and Samples, but only for the limited purpose of checking for conformance
<br />with information given and the design concept expressed in the Contract Documents. The Architect's action will be
<br />taken in accordance with the submittal schedule approved by the Architect or, in the absence of an approved
<br />submittal schedule, with reasonable promptness while allowing sufficient time in the Architect's professional
<br />judgment to permit adequate review. Review of such submittals is not conducted for the purpose of determining the
<br />accuracy and completeness of other details such as dimensions and quantities, or for substantiating instructions for
<br />installation or performance of equipment or systems, all of which remain the responsibility of the Contractor as
<br />required by the Contract Documents. The Architect's review of the Contractor's submittals shall not relieve the
<br />Contractor of the obligations under Sections 3.3, 3.5 and 3.12. The Architect's review shall not constitute approval
<br />of safety precautions or, unless otherwise specifically stated by the Architect, of any construction means, methods,
<br />techniques, sequences or procedures. The Architect's approval of a specific item shall not indicate approval of an
<br />assembly of which the item is a component.
<br />§ 4.2.8 The Architect will prepare Change Orders and Construction Change Directives, and may authorize minor
<br />changes in the Work as provided in Section 7.4. The Architect will investigate and make determinations and
<br />recommendations regarding concealed and unknown conditions as provided in Section 3.7.4.
<br />§ 4.2.9 The Architect will conduct inspections to determine the date or dates of Substantial Completion and the date
<br />of final completion; issue Certificates of Substantial Completion pursuant to Section 9.8; receive and forward to the
<br />Owner, for the Owner's review and records, written warranties and related documents required by the Contract and
<br />assembled by the Contractor pursuant to Section 9.10; and issue a final Certificate for Payment pursuant to
<br />Section 9.10.
<br />§ 4.2.10 If the Owner and Architect agree, the Architect will provide one or more project representatives to assist in
<br />carrying out the Architect's responsibilities at the site. The duties, responsibilities and limitations of authority of
<br />such project representatives shall be as set forth in an exhibit to be incorporated in the Contract Documents.
<br />§ 4.2.11 The Architect will interpret and decide matters concerning performance under, and requirements of, the
<br />Contract Documents on written request of either the Owner or Contractor. The Architect's response to such requests
<br />will be made in writing within any time limits agreed upon or otherwise with reasonable promptness.
<br />§ 4.2.12 Interpretations and decisions of the Architect will be consistent with the intent of, and reasonably inferable
<br />from, the Contract Documents and will be in writing or in the form of drawings. When making such interpretations
<br />and decisions, the Architect will endeavor to secure faithful performance by both Owner and Contractor, will not
<br />show partiality to either and will not be liable for results of interpretations or decisions rendered in good faith.
<br />§ 4.2.13 The Architect's decisions on matters relating to aesthetic effect will be final if consistent with the intent
<br />expressed in the Contract Documents.
<br />§ 4.2.14 The Architect will review and respond to requests for information about the Contract Documents. The
<br />Architect's response to such requests will be made in writing within any time limits agreed upon or otherwise with
<br />reasonable promptness. If appropriate, the Architect will prepare and issue supplemental Drawings and
<br />Specifications in response to the requests for information.
<br />ARTICLE SUBCONTRACTORS
<br />§ 5.1 DEFINITIONS
<br />§ 5.1.1 A Subcontractor is a person or entity who has a direct contract with the Contractor to perform a portion of the
<br />Work at the site. The term "Subcontractor„ is referred to throughout the Contract Documents as if singular in
<br />number and means a Subcontractor or an authorized representative of the Subcontractor. The term "Subcontractor„
<br />does not include a separate contractor or subcontractors of a separate contractor.
<br />AIA Document A2011-2007. Copyright @ 1911 1915, 1918, 1925 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976 1987, 1997 and 2007 by The American
<br />Init. Institute of Architects. All rights reserved. IIioArieiicari'AIA the AIAlolr:r,A201 �ndAIAt1cwti,�r.tl),.r,:ri,.u7m,iitr„�rziz,chi,Pr,izacih,�+,iz,i7i��rt���;w
<br />,ri ir:i ircry u�t I�+r���a i.r,rar i rrnRfir:rt it I�+cn me,�„rei r�i, This document was created on 02/08/2022 15:28:46 18
<br />under the terms of AIA Documents on Demand® Order