§ 12.1.2 If a portion of the Work has been covered that the Architect has not specifically requested to examine prior <br />to its being covered, the Architect may request to see such Work and it shall be uncovered by the Contractor. If such <br />Work is in accordance with the Contract Documents, costs of uncovering and replacement shall, by appropriate <br />Change Order, be at the Owner's expense. If such Work is not in accordance with the Contract Documents, such <br />costs and the cost of correction shall be at the Contractor's expense unless the condition was caused by the Owner or <br />a separate contractor in which event the Owner shall be responsible for payment of such costs. <br />§ 12.2 CORRECTION OF WORK <br />§ 12.2.1 BEFORE OR AFTER SUBSTANTIAL COMPLETION <br />The Contractor shall promptly correct Work rejected by the Architect or failing to conform to the requirements of <br />the Contract Documents, whether discovered before or after Substantial Completion and whether or not fabricated, <br />installed or completed. Costs of correcting such rejected Work, including additional testing and inspections, the cost <br />of uncovering and replacement, and compensation for the Architect's services and expenses made necessary <br />thereby, shall be at the Contractor's expense. <br />§ 12.2.2 AFTER SUBSTANTIAL COMPLETION <br />§ 12.2.2.1 In addition to the Contractor's obligations under Section 3.5, if, within one year after the date of <br />Substantial Completion of the Work or designated portion thereof or after the date for commencement of warranties <br />established under Section 9.9.1, or by terms of an applicable special warranty required by the Contract Documents, <br />any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor <br />shall correct it promptly after receipt of written notice from the Owner to do so unless the Owner has previously <br />given the Contractor a written acceptance of such condition. The Owner shall give such notice promptly after <br />discovery of the condition. During the one-year period for correction of Work, if the Owner fails to notify the <br />Contractor and give the Contractor an opportunity to make the correction, the Owner waives the rights to require <br />correction by the Contractor and to make a claim for breach of warranty. If the Contractor fails to correct <br />nonconforming Work within a reasonable time during that period after receipt of notice from the Owner or <br />Architect, the Owner may correct it in accordance with Section 2.4. <br />§ 12.2.2.2 The one-year period for correction of Work shall be extended with respect to portions of Work first <br />performed after Substantial Completion by the period of time between Substantial Completion and the actual <br />completion of that portion of the Work. <br />§ 12.2.2.3 The one-year period for correction of Work shall not be extended by corrective Work performed by the <br />Contractor pursuant to this Section 12.2. <br />§ 12.2.3 The Contractor shall remove from the site portions of the Work that are not in accordance with the <br />requirements of the Contract Documents and are neither corrected by the Contractor nor accepted by the Owner. <br />§ 12.2.4 The Contractor shall bear the cost of correcting destroyed or damaged construction, whether completed or <br />partially completed, of the Owner or separate contractors caused by the Contractor's correction or removal of Work <br />that is not in accordance with the requirements of the Contract Documents. <br />§ 12.2.5 Nothing contained in this Section 12.2 shall be construed to establish a period of limitation with respect to <br />other obligations the Contractor has under the Contract Documents. Establishment of the one-year period for <br />correction of Work as described in Section 12.2.2 relates only to the specific obligation of the Contractor to correct <br />the Work, and has no relationship to the time within which the obligation to comply with the Contract Documents <br />may be sought to be enforced, nor to the time within which proceedings may be commenced to establish the <br />Contractor's liability with respect to the Contractor's obligations other than specifically to correct the Work. <br />§ 12.3 ACCEPTANCE OF NONCONFORMING WORK <br />If the Owner prefers to accept Work that is not in accordance with the requirements of the Contract Documents, the <br />Owner may do so instead of requiring its removal and correction, in which case the Contract Sum will be reduced as <br />appropriate and equitable. Such adjustment shall be effected whether or not final payment has been made. <br />Init. AIA Document A2011-2007. Copyright @ 1911, 1915, 1918, 1925 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976 1987, 1997 and 2007 by The American <br />Institute of Architects. All rights reserved. 'AIA thoAlAlo1�:�, A201 �iiri AIACgifta(11),:��;:ro.u7i�,iitr„�rz iz,�i h�izaciti,�,iz,i7crt��;, 32 <br />al id 111 lay i not I�+o i.n,ed Witt out Ipoi mi ,slog ii, This document was created on 02/08/2022 15:28:46 under the terms of AIA Documents on Demand® Order <br />/ No. 2114288131 , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents' Documents -on - <br />Demand — End User License Agreement. To report copyright violations, e-mail copyright@aia.org. <br />