certification of the entire Application for Payment, and notify the Contractor and Owner of the Architect's reason for
<br />withholding certification in whole. If certification or notification is not made within such seven day period, the
<br />Contractor may, upon seven additional days' written notice to the Owner and Architect, stop the Work until payment of
<br />the amount owing has been received. The Contract Time and the Contract Sum shall be equitably adjusted due to the
<br />delay.
<br />§ 12.4 Progress Payments
<br />§ 12.4.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner provided
<br />in the Contract Documents.
<br />§ 12.4.2 The Contractor shall promptly pay each subcontractor and supplier, upon receipt of payment from the Owner,
<br />an amount determined in accordance with the terms of the applicable subcontracts and purchase orders.
<br />§ 12.4.3 Neither the Owner nor the Architect shall have responsibility for payments to a subcontractor or supplier.
<br />§ 12.4.4 A Certificate for Payment, a progress payment, or partial or entire use or occupancy of the Project by the Owner
<br />shall not constitute acceptance of Work not in accordance with the requirements of the Contract Documents.
<br />§ 12.5 Substantial Completion
<br />§ 12.5.1 Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is
<br />sufficiently complete in accordance with the Contract Documents so the Owner can occupy or utilize the Work for its
<br />intended use.
<br />§ 12.5.2 When the Contractor believes that the Work or designated portion thereof is substantially complete, it will
<br />notify the Architect and the Architect will make an inspection to determine whether the Work is substantially complete.
<br />When the Architect determines that the Work is substantially complete, the Architect shall prepare a Certificate of
<br />Substantial Completion that shall establish the date of Substantial Completion, establish the responsibilities of the
<br />Owner and Contractor, and fix the time within which the Contractor shall finish all items on the list accompanying the
<br />Certificate. Warranties required by the Contract Documents shall commence on the date of Substantial Completion of
<br />the Work or designated portion thereof unless otherwise provided in the Certificate of Substantial Completion.
<br />§ 12.6 Final Completion and Final Payment
<br />§ 12.6.1 Upon receipt of a final Application for Payment, the Architect will inspect the Work. When the Architect finds
<br />the Work acceptable and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment.
<br />§ 12.6.2 Final payment shall not become due until the Contractor submits to the Architect releases and waivers of liens,
<br />and data establishing payment or satisfaction of obligations, such as receipts, claims, security interests, or encumbrances
<br />arising out of the Contract.
<br />§ 12.6.3 Acceptance of final payment by the Contractor, a subcontractor or supplier shall constitute a waiver of claims
<br />by that payee except those previously made in writing and identified by that payee as unsettled at the time of final
<br />Application for Payment.
<br />ARTICLE 13 PROTECTION OF PERSONS AND PROPERTY
<br />The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs,
<br />including all those required by law in connection with performance of the Contract. The Contractor shall take
<br />reasonable precautions to prevent damage, injury, or loss to employees on the Work and other persons who may be
<br />affected thereby, the Work and materials and equipment to be incorporated therein, and other property at the site or
<br />adjacent thereto. The Contractor shall promptly remedy damage and loss to property caused in whole or in part by the
<br />Contractor, or by anyone for whose acts the Contractor may be liable.
<br />ARTICLE 14 CORRECTION OF WORK
<br />§ 14.1 The Contractor shall promptly correct Work rejected by the Architect as failing to conform to the requirements of
<br />the Contract Documents. The Contractor shall bear the cost of correcting such rejected Work, including the costs of
<br />uncovering, replacement, and additional testing.
<br />11
<br />Init. AIA Document A105T"' — 2017. Copyright ® 1993, 2007 and 2017 by The American Institute of Architects. All rights reserved. 'tVPJUa 4tt4'r Yf II¢is P,110"°
<br />I l;nrha;;iaor 7 uttt lis Ipiiotw,,1, d Iby V„l.ed aeo p�yi ui,,pl N' aw and hlilre o oo dlha ra, ll U [reu J)G8 Iwruu.ruiittroaio o a,aU a�pr:uw,tlwoa tli rdr¢ oii wtMirlll utija in cet'tlPAs /I�U,P ' 4)o u,irrfenMl, or atny
<br />x wVlc,o�, OW !it, m iiyi oe��si"M In S ew�ere ¢bowl and a ai inlin G p�ua i ue lltta ar<,, afm"i WIR Ilam pwoo ,ecu'a CO fihe rToaJXhriiU"'1 e t ii'd tDdw .,,ollddi�, ouriduo th6a, Ilawu. This do,'-"ument 10
<br />/ was created on 02/08/2022 15:28:45 under the terms of AIA Documents on Demand® Order No. 2114288131 , and is not for resale. This document
<br />is licensed by The American Institute of Architects for one-time use only, and may not be reproduced prior to its completion.
<br />
|