§ 31-112. Administration and interpretation.
<br />(a) The City Manager or designee shall administer this Section and may consult with the
<br />Building Official, City Planner, City Engineer, Fire Marshal, Public Works Director, utility
<br />providers, and other affected departments as necessary.
<br />(b) The City Manager or designee may issue written interpretations, forms, checklists,
<br />routing procedures, and administrative guidance necessary to implement this section
<br />and DSM -002.
<br />(c) The City Manager or designee may determine whether a proposed use is an
<br />accessory server room, Limited Data Center, General Data Center, High -Intensity Data
<br />Center, Data Center with BESS, or other Data Center classification based on this
<br />section and DSM -002.
<br />(d) Any interpretation under this section shall not authorize a use'prohibited 'by this
<br />section, waive a P* or SUP* requirement, or alter zoning district eligibility.
<br />§ 31-113. Revisions to DSM -002.
<br />(a) DSM -,002 may be revised in accordance with the revision procedures established in
<br />the adopting ordinance and DSM -002.
<br />(b) Minor administrative revisions,, formatting corrections,_ -typographical corrections,
<br />reference updates, application forms, checklists, routing procedures, and revisions
<br />required by state or federal law may be approved administratively by the City Manager
<br />or designee.
<br />(c) Major revisions affecting zoning district eligibility, Data Center:classifications, SUP*
<br />requirements, minimum land use standards, development requirements, public
<br />infrastructure obligations, decommissioning requirements, financial assurance
<br />requirements, or substantive design and use standards shall require,City Council
<br />approval.
<br />(d) The current adopted version of DSM -002 shall.be maintained by the City and made
<br />available to the public through the City's official website or other City -designated
<br />location.
<br />§ 31-114. Water, wastewater, and utility coordination.
<br />(a) A Data Center shall not be approved unless the City'determines'that water,
<br />wastewater, drainage, and public infrastructure impacts have been adequately
<br />evaluated and addressed.
<br />(b) A Data Center applicant shall provide water demand, wastewater demand, cooling
<br />system, discharge, backflow prevention, cross -connection control, fire flow, and
<br />Page 16 of 26