Laserfiche WebLink
6. Modification of shaft-driven pumps to belt -iriven pumps at Master Lift Station - One <br />completed, two scheduled for completion by end of August. <br />7. Installation of a news VFD at the Flow Equalization Basin - VFD ordered <br />8. Replacement of two check valves at Master Lift Station <br />9. Upgrade SCADA system - Replacing RACO (telephone dialsers) throughout the system <br />with radio communication <br />*Pending <br />10. Develop water plant capital plan, including filter and piping rehab - Media has been <br />replaced in all ten filters; considering installation of air-scour filter backwash capability <br />11. Implement security enhancements for water plant - Ongoing; 2-person minimum shifts <br />implemented <br />12. Implement security enhancements for wastewater plant Ongoing; 2-person minimum <br />shifts implemented <br />13. Rehabilitate east elevated water tank - Included in Engineering's long-range capital plan <br />14. Install a grit & screenings facility at the flow equalization basin - Included in the FY <br />2009-2010 budget request <br />15. Upgrade electrical system Pat Mayse Lake intake - Engineering study required <br />16. Develop phased program to equip lift stations to accept portable power - Limited <br />inventory of trailer mounted portable pumps for lift stations in stock; Engineering study <br />needed <br />17. Rehabilitate Lake Crook dam - Foliage control in place; phased plan submitted by <br />engineering consultant <br />18. Rehabilitate drying beds at the wastewater treatment plant, including the under drain <br />system - Ongoing; Included in FY 2009-2010 budget request <br />19. Install two additional variable frequency drives at the Master Lift Station - One <br />completed and one ordered with scheduled completion in mid-August <br />20. Install three (3) additional variable frequency drives at Pat Mayse Intake - Depends upon <br />NextERA negotiations <br />21. Replace Smith Creek bridge at water treatment plant - Grant applied for and is also in FY <br />2009-2010 budget request <br />22. Replace drainage structure under Lake Crook Road at water treatment plant FY 2009- <br />2010 budget request <br />City of Paris Needs Assessment <br />Page 11 <br />1~ ~ <br />