Loading...
1987-1991REGULAR MEETING WATER TREATMENT PLANT AND WASTEWATER TREATMENT PLANT CHANGE ORDER AND FINAL CHANGE ORDER REVIEW COMMITTEE, CITY OF PARIS July 13, 1987 The Water Treatment Plant and Wastewater Treatment Plant Change Order and Final Change Order Review Committee met in Special session, Monday, July 13, 1987, 10:00 A.M. Council chamber, City Hall. Chairman Bone called the meeting to order with the following members present: Eric Clifford, and Curtis Fendley. Also present were City Manager, Michael E. Malone, City Attorney T. K. Haynes, and City Clerk, Mattie Cunningham. Chairman Bone called for discussion on Change Order No. 2 to contract with Four Thirteen, Inc., for the 1985 Wastewater Treatment Plant Improvements. John Buss, Consultant Engineer, appeared before the Committee giving background of the Contract with Four Thirteen, Inc. Mr. Buss stated that the contract will be complete upon accepting the pending 6 items as follows: 1. Install Seal Water System for Grit Pump 2. Modify Piping from grit concentrator to screen 3. Install safety railing and grating over pista grit 4. Install auto - restart on effluent pumps 5. Install air conditioner in MCC room Total Change Order No. 2 $2,800.00 $2,700.00 $3,150.00 $1,700.00 $3,100.00 $13,450.00 Mr. Buss stated that the City's share of the $13,450.00 would be $4,775.00 and Anheuser Busch portion would be $8,675.00. Discussion was had regarding the acceptance of the change order by Anheuser Busch with the Committee. Mr. Buss told the Council that Jim Martin who has been working with the City on site agrees that the change order is necessary. City Attorney advised that Committee that it may take approximately six week to get an answer from Anheuser Busch, and that we do not want to send them something that we have not approved. After further discussion, the Committee agreed to recommend to the Council that Change Order No. 2 to the Contract with Four Thirteen, Inc. be accepted. Chairman Bone announced that the next item on the Agenda was discussion of Change Order No. 10 to Additions to Water Treatment Plant. John Buss told the Committee that the original contract was in the amount of $3,039,940.00 with Heritage Constructor's Inc., Change Order No. 1 reduced the contract amount approximately $50,000.00, there have been eight additional Change Orders, and Mr. Buss review the additional change orders. Mr. Buss state that there were eleven undisputed item that some were increases and others were decreases which resulted in an increase of $1,243.00, and recommended approval of these items. Mr. Buss discussed the cost of the filter blocks used for the project. Mr. Buss told the Committee that we used about $1,000.00 worth of these and as the contract price was $3,300.00 for Filter Blocks the balance was deleted from the contract by a Change Order. Mr. Buss told the Committee that the Contractor has returned the balance of the filter blocks to the supplier who is charging the contractor a restocking fee in the amount of $2,015.16, and the Contractor is requesting payment of the restocking fee. After discussion, the Committee agreed to recommend to the Council that payment of the restocking fee be made. Mr. Buss told the Committee that an additional $2,355.00 was requested by the contractor for the lime and lime processing cost as it is a verable cost item in the bid process. After discussion, the Committee agreed to recommend to the Council payment of the additional $2,355.00.00. Mr. Buss discussed the design error of Shimek, Jacobs & Finklea in the head loss for the head mixer being designed to low and it has to be corrected. Shimek, Jacobs & Finklea has agreed to participate towards the cost of correcting this error in the amount of $9,800.00 of the total cost of $25,500.00. After discussion, the Committee instructed the City Attorney to negotiate with Shimek, Jacobs & Finklea and make the best deal possible, and try for a split of the $25,500.00. Discussion was had concerning the hydrogen sulfide gas problem in the screening building. There being no further business, the meeting adjourned. BILL BONE, CHAIRMAN ATTEST: MATTIE CUNNINGHAM, CITY CLERK CITY OF PARIS WATER AND WASTEWATER RATE DESIGN STUDY INITIAL PROJECT SCHEDULING 01 -11 -88 MONTH JAN ( FEB I MAR { APR { MAY WEEK 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 MEETINGS: A. PROJECT TEAM B. ADVISORY COMMITTEE C. COUNCIL MEETING TASKS: A. GOALS AND OBJECTIVES B. TEST YEAR (T /Y) C. T/Y REV. REQ. D. CURRENT REVENUE E. FUHCTIONALIZE REV. R£0. F. MISC. REV. G. DEPOSIT REQ. H. CONTRACT(s) REVIEW I. S. B. 336 REVIEW J. RATE DESIGN FINAL REPORT * � s w w • r w w • r w :w wm WAVAM wm WAVAM .ev.� !" f .12; sra�w.aa%oc�.rvavw.cvae a NAKOW .avadarmty r SPECIAL MEETING WATER AND SEWER RATE STUDY ADVISORY COMMITTEE January 28, 1988 The Water and Sewer Rate study Advisory Committee of the City of Paris met in special session, Thursday, January 28, 1988, 6:00 P. M. Council Room, City Hall, Paris, Texas. Chairman Marshall H. Kent, Jr. Call the meeting to order with the following members present: Councilman Travis Wortham, Director of Finance, W. E. Anderson, City Attorney, T. K. Haynes, Director of Utilities, Herb Campbell, Jim Farris, Citizen, and City Clerk, Mattie Cunningham. Chairman Kent announced that the special meeting was called for the purpose of receiving a briefing from Reed & Stowe, Consultants for the City's Water and Sewer Rate Study. Jack Stowe representing Reed & Stowe presented the Committee with an Initial Project Schedule, attached hereto as exhibit A, and made part of these minutes. Mr. Stowe told the Committee that they have met several times with Freese and Nichols, Inc. who will be conducting the engineering portion of the study, lining out their specific task, and getting information together and information request which has been presented to W. E. Anderson. Mr. Stowe said one of their concerns when they started on this project was the quality and format of the data; however, the City has produced very good data, and it should not hold them back. Mr. Stowe told the Committee that their timetable shows meeting with the project team once each week, and every two weeks with the Advisory Committee in order to keep the Committee advised on the progress of the study, and at the same time, the things that might come up which would require a policy decision, and they wanting to recognize those and blend them in because the final result of a study like this has to accomplish the goals and objectives that the City sets out. Mr. Stowe explained that is one of the reasons why they have given out the survey questionnaire, and said that basically the information from the surveys will be used to come up with a common goal for the City, which will be discussed in. the next meeting. Mr. Stowe asked that the surveys be return to them as soon as possible. Mr. Stowe said the third item for discussion was the test year selected, that they had selected the year 12 months ending September 30, 1987 which is the starting point for data and information. Mr. Stowe explained they will take the dollar amount that the City has grouped, Reed and Stowe will have to go in and separate out how much of those dollars are spent for water and how much went for sewer. Mr. Stowe gave an example of an investment account dealing with the water treatment plant, they will identify all assets dealing with raw water, raw water transmission, treatment, treatment facilities, treated water transmission mains, treated water distribution mains, as of now, the City is capturing the information as mains. They will have to go in and do a study to separate that out between Page 2 transmission mains and distribution mains, and the reason why they are doing this is the system was designed to meet a need, that need is being brought about by residential customers, commercial customers, and industrial customers, and what they will be doing is getting the assets and operating expenses all classified as what their function is doing, then the Engineers will look at the customers as to what demands they are putting on the system that requires the system to be built that way, and the expenses being incurred in that manner, and what they do is assign the expenses over to the customer classes. Mr. Stowe told the Committee that one of the first things to look at in a rate study is the water supply,which the City of Paris is very fortunate to have Pat Mayse Lake. The City has a 55 MGD reserve, out of that the City is only using 21 MGD or 40% of the 55 MGD which has a cost to it, and the City is paying through the Operating and Maintenance. The contract states that for the present use or the 21 MGD the City will be paying the debt service on 1.6 million dollars which is the allocated cost relating to the 21 MGD that built Pat Mayse Lake. The City is paying for the raw water used based on a 50 year payout, and based on stated interest rate, we look at this as a contractual debt obligation, and when it is paid, it is Operating and Maintenance. $77,000.00 has been budgeted for this year of which $49,000.00 is debt service. City Attorney Haynes explained that the City is meeting their minimum obligation only, which is the 21 MGD, and feels we should be paying or setting aside funds to pay for the full 55 MGD reserved, and allowing everyone's participation in the future rights to pay for it, if we do not, when we get down to the end when we have to take the maximum amount of water from Pat Mayse, we will have to pay a larger amount, that is why we need to plan ahead. Mr. Haynes explained that the Consultants will be studying each of our contracts for water, they will tell us where we stand and how to proceed, this will be part of what we will be receiving in future meetings. Mr. Keith Reed explained that the longer the City delays making payments on the future reserve capacity at Pat Mayse, the City runs the risk of someone going to the Water Commission requesting water rights to Pat Mayse because the City of Paris has not payed anything on it. If the City makes an effort to pay or set aside a dedicated reserve, the City would have that as an argument. Mr. Reed said that we are only paying or the first 21 MGD of water taken from Pat Mayse, but when the City exceeds the 21 MGD, the City will have to start paying for a debt service which interest is being accrued. City Attorney Haynes said there has been interest shown by some of the Councilmen for what to do to try and take care of the people who are on a small fixed income without them having large water bills. Mr. Stowe said one of the first thing they will present is a cost base rate, compare it with the cost block rate currently being charged. Mr. Stowe said the cost block rate structure loads the cost on low users. They will take cost base rate and compare, and if that Page 3 is not acceptable, then will have some of the expenses shaved off the low users in order to lower their cost. This is one of the thing they will be bring to your for consideration. There being no further business, the meeting adjourned. MARSHALL H. KENT, JR. CHAIRMAN ATTEST: MATTIE CUNNINGHAM, CITY CLERK CITY OF PARIS WATER AND WASTEWATER RATE DESIGN STUDY INITIAL PROJECT SCHEDULING 01 -11 -88 MONTH JAN ( FEB MAR 1 APR I MAY WEEK 1 2 3 4 1 2 3 4 1 2 3 41 1 2 3 41 1 2 3 4 MEETINGS: A. PROJECT TEAM B. ADVISORY COMMITTEE C. COUNCIL MEETING TASKS: A. GOALS AND OBJECTIVES B. TEST YEAR (T /Y) C. T/Y REV. REQ. D. CURRENT REVENUE E. FUNCTIONALIZE REV. REQ. F. MISC. REV. G. DEPOSIT REQ. H. CONTRACT(s) REVIEW I. S. B. 336 REVIEW J. RATE DESIGN FINAL REPORT w • s w � � s • w � r i►. `�w t I E CITY OF PARIS RATE STUDY SURVEY 1. What would you perceive providing water and wast, limits retail customers and 16 Provide the highest economical price as the City's responsibility in =water services to its inside city contract customers? quality of service at the most Provide service at the lowest possible cost realizing that some related service interruptions will occur 14- Provide a reasonable level of service which would allow the City to recover cost plus a profit i. In your opinion, should the City Departments be furnished water and wastewater service with no charge? � Yes !✓ No If yes, should the related cost be recovered through: Utility rates to other customers Taxes 3. Should the City be in the business of supplying utility services to customers outside of its city limits? Yes No t 4. In your opinion, should the City have a long -terra plan for providing adequate utility services? 1 Yes 10 No If yes, how long of a planning period would be appropriate? Less than 5 years 5 to 10 years 5 More than 10 years 5. In your opinion, should any specific customers be subsidized by other utility customers? ® I Yes / No 6. Do you feel that the use of water should be encouraged or ® should r- �water be priced to encourage conservation? { Encourage use 17 Encourage conservation j 7. Should the cost of public fire protection be recovered in water rates or in the property taxes? Rates Taxes A. In your opini`orn,L should nTIty construction capital casts associated with new customers (growth) be recovered from the new customers or should the costs be absorbed by all customers? Recovered from new customers Absorbed by all customers 9. What is the main complaint of utility services you receive from your constituents other than the cost? • 10. In your opinion, other than the cost of service, what is the most sensitive issue to be addressed when pricing utility services? (examples: -a i l ity to pay.) attracting growth, encourage industrial development, etc.) 11. Please provide any additional comments you feel would be beneficial in the conduct of this study. 40 MINUTES OF THE SPECIAL MEETING OF THE WATER & SEWER RATE STUDY ADVISORY COMMITTEE February 11, 1988 The Water & Sewer Rate Study Advisory Committee met in special session, Thursday, February 11, 1988, 6:00 P. M. Council Room, City Hall. Chairman Marshall H. Kent Jr. called the meeting to order with the following members present: Councilman Bill Bone, Councilman Travis Wortham, Herb Campbell, Director of Utilities, W. E. Anderson, Director of Finance, City Manager, Michael E. Malone, City Attorney, T. K. Haynes, and Mattie Cunningham, City Clerk. Chairman Kent stated the purpose of this meeting was to receive a briefing from our Consultants, Reed and Stowe and Freese & Nichols, regarding the Water & Sewer Rate Study. Jack Stowe Consultant for Reed & Stowe, appeared and advised that the first item he would like to cover is the surveys that were sent out, and stated that he has received ten of those back, and requested that those still out to please return as soon as possible. Mr. Stowe went over each question on the survey and gave the results of the thirteen questions asked as follows: 1. What would you perceive as the City's responsibility in providing water and wastewater services to its inside city limits retail customers and contract customers? 6 Provide the highest quality of service at the most economical price. 4 Provide a reasonable level of service which would allow the City to recover cost plus a profit. 2. In your opinion, should the City Departments be furnished water and wastewater service with no charges? 3 Yes 7 No Mr. Stowe pointed out that the City's 1983 Bond Ordinance specifically states that the City shall not receive any free service for it's usage, and by law the city should be paying for these services. 3. Should the City be in the business of supplying utility services to customers outside of its city limits? 8 Yes 2 No 4. In Your opinion, should the City have a long -term plan for providing adequate utility services? 10 Yes 0 No If yes, how long of a planning period would be appropriate? Page 2 1 Less than 5 years 5 5 to 10 years 4 More than 10 years 5. In your opinion, should any specific customers be subsidized by other utility customers? 1 Yes 9 No 6. Do you feel that the use of water should be encouraged or should water be priced to encourage conservation? 7 Encourage use 3 Encourage conservation 7. Should the cost of public fire protection be recovered in water rates or in the property taxes? 3 Rates 6 Taxes 1 neither 8. In your opinion, should utility construction capital costs associated with new customers (growth) be recovered from the new customers or should the costs be absorbed by all customers? 6 Recovered from new customers 4 absorbed by all customers 1 Yes 9 No Mr. Stowe told the Committee that the next three questions are: 9. What is the main complaint of utility services you receive from your constituents other than the cost? 10. In your opinion, other than the cost of service, what is the most sensitive issue to be addressed when pricing utility services? (examples: ability to pay, attractive growth, encourage industrial development, etc.) 11. Please provide any additional comments you feel would be beneficial in the conduct of this study. Mr. Stowe explained these questions are open questions which are important because what they will do is take those three questions and what you have responded, overlay them to the way you responded to the first eight questions, and gave an example - what level of service you should provide? Highest quality of service at the most economical price. Mr. Stowe said that the most additional comments were the major complaints were low pressure, and in case of heavy rains is the inflow problem. Mr. Stowe said they coupled that with the planning process, Page 3 and it said - Yes we need to plan, either 5 - 10 years, or something beyond 10 years, everyone recognized the need to plan, provide quality service, and recognized that we have problems, when they weigh those three things together, this means we have improvements that need to be made. Mr. Stowe stated that they have not discussed this with anyone, but what they see based on the complaints you are getting, based on the desires that have been expressed, and based on the planning situation that has been expressed, we see that there needs to be some type of capital improvement looked at whether this year or five years from now, we do not know at this point, but are developing a frame work to look at. Mr. Stowe discussed the subsidizing of customers even though the answer was 9 no's and 1 yes, everyone responded in one of the areas we need to be sensitive to, that is the ability to pay, and we have to recognize the older or retired,their rate can not be as high as others, while we are say no, we do not want to subsidize, we are also saying we have to be sensitive in designing the rate for the people who are in these lower usage blocks. Mr. Stowe said cost is cost, but there are several ways to get to that cost, and that dictates the type of goals and what type allocation factors we might use, what type patterns we might apply, how deep we might deal into this level of customer that is in the 2,000 gallon range. Mr. Stowe said based on the committee's additional comments, they will spend time looking at this lower level to make sure that those people truly are only reflecting their cost, that they do not pick up an inordinate amount of the demand component of the plant or the demand component of the operating expenses. Mr. Stowe said this survey is only giving them directions for the rate design they will be presenting to the Committee. Mr. Stowe discussed the aspect of promoting usage, Mr. Stowe said you want the new customers to pay the cost of growth; however, the majority of the answers were that one of the goal should be to attract new growth and industry which could be a contradiction from what was said in the additional comments because if we saddle the new customers in a rate structure or with an impact figure we stand the risk to discouraging growth because they have to pay their cost on the front end, so that coupled with let's promote usage means, let's price it down and not take as much profit as we might originally, lets keep our prices as low as we possibly can, and still cover our cost, by keeping the cost low, we will sell more water and get more customers. Mr. Stowe said this is something we need to talk about. Mr. Stowe told the Committee that he has reviewed the contracts the city has for sale of water, and is going through and developing what the rates would be under those contracts. Councilman Bone requested additional information regarding the percent Campbell Soup payment that goes toward capital improvements, and what percent of the residential customers payment that goes for capital improvements. Mr. Stowe explained that they will be able to show the capital cost for each customer class and each contract as to what they are paying. They Page 4 will be able to tell you whether the city has good contracts or bad contracts. Barry Sarma, Consulting Engineer with Freese & Nichols, Inc., appeared before the Committee, telling them he has gone through the city's three water rights permits, one at Pat Mayse which is a Federal Reservoir, that the city has total rights of 55 MGD, Lake Crook which is approximately 1200 acre feet a year making a total of 65 MGD. Currently the city is using 12 million gallons of water a day which means you are using about 20% of the water rights. Mr. Sarma said the city has 80% of their water in storage for future use, and someone has to pay for it. Mr. Sarma said under the city's contract with Lamar County Water Supply District they have a guarantee of 16.7 MGD of water, and they are not paying for that storage. Mr. Sarma discussed the fact that the city has Lake Crook right next to the water treatment plant which would cost less to pump and transmit, that this might something for the city to look at. Mr. Sarma said he has looked at the projected population for the City of Paris, and in the past few years Paris has not grown, but the consumption of water has increased and explained that population is not the only way to increase consumption. Mr. Sarma told the Committee that the planning process is very important to any city, they have to look beyond the current year or two, and the system the city of Paris currently has, and the raw water that is available the city would have 30 to 40 years of growth. Mr. Sarma stated the third problem the city has is with the violations as for as infiltration - inflow problems, and expressed the seriousness of these violations, the EPA which you have two administrative orders, and one letter from the Texas Water Commission regarding this matter. Mr. Sarma said the city has to look at the system and how to improve it in order to meet the requirements of the permits. Mr. Sarma expressed the need to start paying for the water rights at Pat Mayse before someone steps in and requested the water rights to Pay Mayse. The City of Paris needs to protect their water rights by starting to pay for that right, and as for as the rate goes, we need your input as to how financing may be achieved and future upgrading for the system. Mr. Stowe discussed the issuance of bonds - stating that in the City's bond covenant, if the City issues Revenue Bonds, you have to go to a 1.25 coverage, or your revenue minus your operating expenses will have to equal that operating income 1.25 times the total interest cost of your new and existing debt, if it does not reach that point prior to issuing bonds, you can not issue bonds. Mr. Stowe said this is what happened in 1984, the city had to issue Certificate of Obligation Bonds which is backed by Ad Valorem tax because in 1983 the city did not have 1.25 coverage. Mr. Stowe said they will be coming to you as to when we can look toward a bond issue, when do you have to have your coverage Page 5 positioned right, that's the rate study that what we are here to do for you. There being no further business, the meeting adjourned. MARSHALL H. KENT, JR., CHAIRMAN ATTEST: MATTIE CUNNINGHAM, CITY CLERK MINUTES OF THE WATER & SEWER RATE STUDY ADVISORY COMMITTEE February 25, 1988 The Water & Sewer Rate Study Advisory Committee met in special session, Thursday, February 25, 1988, 6:00 P. M. Council Room, City Hall, Paris, Texas. Chairman Kent called the meeting to order with the following members present: Councilman Bone, City Attorney, T. K. Haynes, City Manager, Michael E. Malone, Director of Finance, W. E. Anderson, Director of Utilities, Herb Campbell, James Farris, Citizen, and City Clerk Mattie Cunningham. Jack Stowe representing Reed & Stowe presented a draft of the segments completed by his firm regarding the water and sewer rate study, and cautioned the Committee of the fact that this being a draft, it would be subject to change, and attached hereto as part of these minutes as exhibit A. Mr. Stowe called attention to the first three pages of the draft, the first page showing raw water pumped daily - average to the peak day from 1983 through 1987 stating that it has been rather static until 1987 when we reached a large raw water peak which they can not account for other than there must have been an extremely hot day, or some of the raw water could have gone to storage. Mr. Stowe went to the next draft showing treated water pumped daily - average vs peak day, and again stated that it stayed static with the exception of 1986 with a slight increase. The average treated water pumped is approximately 11 MGD, and peak treated water pumped is approximately 16 -18 MGD. Mr. Stowe said this information was needed to get them familiar with how the city's system is operating so they will be able to make decisions when they get ready to allocate such as characteristic of the water treatment plant. On the next schedule, Mr. Stowe pointed out the raw water vs treated water pumped, stating you expect to see differences due to storage that takes place, lag in measuring, and they were not to concerned with what they saw. Mr. Stowe went to page one of the draft advising they had taken the assets or investments that the city has in the Water & Sewer Fund and for the most part, is broken down fairly well for them between water and sewer except for investments in billing and collecting, and that is one of the things they went back in and allocated 50% of the investment over to the sewer side of the investments. Mr. Stowe stressed the importances of remembering that they were only looking at one half of the picture tonight, that being water not sewer. Mr. Stowe said that when the committee meets in two weeks he will have the figures for the sewer investments completed, and will be presented them at that time along with the water, and will be able to show the committee what he will give the engineers, and what they will use to do the customer class allocation study. Page 2 Mr. Stowe said in looking at the investment which is net for developer's and net depreciation. In Billing & Collection we have $70,000. invested at this time; water storage, counting the future reserve capacity we have in Pat Mayse, we have $4,244,050. invested; Raw Water Transmission Lines which they had to go back into the asset base and identify what is raw water transmission and originated $752,099.; Raw Water Treatment Plant we have $5,244,910. invested; Water Distribution - one of the items they had to go back in and determine what part is transmission mains, and what part is distribution main, and explained that some of the city's contracts calls for eight inch or larger mains, it is called a transmission main; if below eight inches it is a distribution main for cost assignment, and they have applied the contractual language to come up with the investment; Transmission mains $1,569,000. invested; Distribution Mains $2,646,357.; Meters and Boxes $293,168.; Service Lines $186,903.; Hydrants & Valves $206,064.; Machinery Tools & Equipment $70,276.; Sub -Total for Water Distribution $4,998,367. Mr. Stowe pointed out that on page two, they are showing construction in process which is blank explaining they had a figure of $106,000. for construction in process, but they needed to find out what type of investment is being built so they will know how to functionalize it, and will have that figure at the next meeting. Mr. Stowe told the committee that they have gone in and regrouped the assets by moving them around, distinguishing between raw water transmission, treatment plant, distribution mains and transmission mains. The next step is based on the analysis they have made of the city's history, and the design of the plant, they have funcitionalized those costs which are made up of four components - base meaning volume; extra capacity because of the peak day and peak hour, we have to have the investments in place to meet that peak; and customer cost. Mr. Stowe advised that the next step is the revenue requirements, and what they used was the 1987 -88 budget which they listed as it is shown in the City's budget, but there were adjustments that they had to make, first reclass certain expenses, second to make adjustments that are known and measurable at this time, and pointed out that on Page one of the Water Revenue Requirements under Billing and Collecting, they have cut $141,615. from the budgeted amount, and explained that this is the amount that will be moved over to sewer. Under Raw Water Storage - Contractual 0 &M Pat Mayse, you will see $77,000. has been moved, and explained this has been reclassed - $27,174. represents 0 &M at the reservoir, the balance of $49,826. represents the debt service that we are paying; Raw Water Transmission - you will see that in the budget they did not have anything identified, but they have pulled $220,447. from Water Production Contractual and moved it to Raw Water Transmission. Under Water Distribution they have removed $234,468. from Personnel, Supplies, Contractual, Maintenance Building and Equipment, and picked up $233,718. under Transmission for treated water transmission. Mr. Stowe explained they looked at the total linear feet the city has in place and found that 43% of the physical assets are eight inch mains and above as far as the distribution system, 57% is Page 3 below, so they applied 43% to these expenses in order to break out what is transmission related. Mr. Stowe said that one of the things they recognized was the support service coming out of the General Fund, of those, identified City Council, City Manager, Finance, Legal, Engineer, Warehouse, Garage, Plumbing Inspector, and they established a means of deducting the amount of time being spent for water and sewer use by these departments which amounts to $308,000. for water use only. Mr. Stowe explained that under Capital Outlay, there has been no adjustment, but it will have to be finalized before they can complete the study. This will revert back to the planning process. Mr. Stowe also said in the Debt Service was $234,271.; 1984 $523,921., Pat Mayse $49,826., and future amount they are incurring is approximately $80,00. Basically they move from the city's budget $2,207,185., and $3,216,799. required revenue, and advised these numbers will be changing. There being no further business, the meeting adjourned. MARSHALL H. KENT, JR., CHAIRMAN ATTEST: MATTIE CUNNINGHAM, CITY CLERK ICI 9 ri 73 101, rn i 7-- ! -0 Eo -.b to to -4h. .-k to Ca Ln co cm co 4 MILLION GALLONS DRAFT -A 0 0 -4 M to 0 — 0 rrl ;u T > U) IS m T b m ICI to co W J CD -F+ cc v rn b� cfl v MILLION GALLONS 4 j N 44 41- 0 M '-4 to tD 4 � fA 45 -i M W --, C-) X rn m v 0 m TI X v --a c > w A fTt all C '[7 f*1 Q Li --i 4 -o c m v GALLONS m i_�n_ rte_', U1 rn V rn CD J Q n o C] m Ln N Co N, {,_ 4- Ln cm _„j +G co Z C!! O N 1 co N ca -r m m < 0 L6 X }*i Q fIj (J') m PAGE 1 24- Feb -88 DATE CITY OF PARIS WATER INVESTMENT FUNCTIONALIIATION 1988 EXTRA CAPACITY NET ASSET INVESTMENT BASE MAX DAY MAX HOUR CUSTOMER Billing /Collecting Land $6,439 $6,439 Buildings 18,577 18,577 Furn & Fixtures 622 522 Machinery Tools & Equip 40,676 40,676 Automobiles 3,202 3,M Sub -Total Billing /Collecting $69,516 $0 $0 $0 $69,516 Dater Storage Pat Mayse: Current $1,044,104 $1,044,104 Future 2,553,587 2, 553, 587 Lake Crook 494,624 494,624 Lake Gibbons 151,735 151,735 Sub -Total Water Storage $4,244,050 $4,244,050 $0 $0 $0 Ran Water Trans. $752,099 $376,050 $0 $376,050 $0 Water Treatment Land $2,068 1,356 483 229 Buildings 732,835 480,546 171,193 81,0% Filtration Plants 3,388,786 2,259,191 847,197 282,399 Stand Pipes & Reservoirs 237,859 118,929 118,929 Wells & Pumps 865 ,728 567,689 202,237 95 802 s Furn & Fixtures 265 174 62 29 Machinery Tools & Equip 3,025 1,983 707 335 Instruments 1,767 1,159 413 1% Motor Vehicles 10,305 6,757 2,407 1,140 Misc. Equipment 2,273 1,490 531 251 Sub -Total Water Treatment $5,244,910 $3,439,274 $1,225,229 $580,407 $0 Water Distribution PAGE 2 24- Feb -88 DATE CITY OF PARIS WATER INVESTMENT FUNCTIONALIZATION 1988 EXTRA CAPACITY NET ASSET INVESTMENT BASE MAX DAY MAX HOUR CUSTOMER Buildings $276 $133 $29 $86 $27 Bridges & Culverts Mains: Transmission 1,569,000 1,046,000 523,000 Distribution 2,646,357 1,323,178 1,323,178 Meters 6 Boxes: 293,168 293,168 .625 .750 1.00 1.50 2.00 3.00 4.00 20.00 Service Lines: 186,903 186,903 .75 1.00 1.25 1.50 2.00 4.00 6.00 8.00 Hydrants d Valves 206,064 206,064 Machinery Tools i Equip 70,276 33,%9 7,499 21,926 6,883 Motor Vehicles 26,323 12,723 2,809 8,213 2,578 Sub -Total Water Distribution $4 ,998,367 $2,416,004 $533,337 $1,559,467 $489,559 Construction in Process Grand Total $15,308,943 $10,475,378 $1,758,566 $2,515,924 $559,075 PERCENTAGES 100.00% 68.43% 11.49% 16.43% 3.65% PAGE 1 24- Feb-88 DATE CITY OF PARIS CONSULTANT RECOMIMEM(DED WATER REVENUE REQUIREMENTS CONSULTANT RECOMMENDED 87/88 REVEME BUDGET RECOMMIEMNED ADJUSTMENTS REQUIREMENTS BILLING 3 COLLECTING PERSONNEL $178,150 ($89,075) $89,075 SUPPLIES 30,480 ($15,240) 15,240 CONTRACTUAL 46,450 1$23,225) 23,225 MAINT. am. 3,000 ($1,500) 1,500 EQUIP. 5,150 ($2,575) 2,575 AUDIT 10,000 ($10,000) 0 $273,230 3141,615) $131,615 RAW WATER STORAGE $27,174 $27,174 RAW WATER TRANSMISSION $224,447 $220,447 WATER PRODUCTION PERSONNEL $229,205 $229,205 SUPPLIES DEMICALS 162,000 162,000 MISC. 11,220 11,220 CONTRACTUAL O&M PAT MAYSE 77,000 (77,000) 0 POWER 425,000 (220,447) 204,553 MISC. 41,885 41,885 MAINT. BLDGS. 14,800 14,800 EQUIP. 49,415 49,415 AUDIT 800 (800) 0 $1,011,325 ($77,800) (3220,447) $713,078 WATER DISTRIBUTION PERSONNEL $243,345 ($104,638) $138,707 SUPPLIES 15,625 (6,719) 8,906 CONTRACTUAL 37,360 (16,065) 21,295 MIAIMT. 0 BLDGS. 226,200 (97,266) 128,934 EQUIP. 21,000 (9,030) 11,970 AUDIT 750 (750) 0 TRANSMISSION 0.43 AUDIT FEES $544,280 ($234,468) $309,812 $233,718 $233,718 $6,550 $6,550 PAGE 2 CITY OF PARIS CONSULTANT RECObNN:7M HATER REVENUE REQUIREMENTS 24- Feb -88 DATE DIIA'AF"'I" CONSULTANT RECOMMENDED 87/88 REVENUE BUDGET RECOMMENDED ADJUSTMENTS REQUIREMENTS GENERAL FUND SUPPORT: CITY COUNCIL $18,626 $18,626 CITY MANAGER N 906 26,906 LEGAL 31,106 31,106 FINANCE 65,508 65,508 ENGINEERING 101,160 101,160 WAREMJSE 34,563 34,563 GARAGE 14,507 14,507 PLUMBING INSP. 15,555 15,555 $307,931 $307,931 CAPITAL OUTLAY BILLING & COLLECTING $7,450 $7,450 RAH HATER SUPPLY 10,300 10,300 TRANSMISSION 129,000 129,000 DISTRIBUTION 0 MAINS 171,000 171,000 EQUIP 17,600 17,600 METERS & SERVICES 28,000 28,000 HYDRANTS 15,000 15,000 $378,350 $378,350 DEBT SERVICE 1983 0.566 0.11 234,271 $234,271 1984 0.455 0.175 523,921 523,921 PAT MAYSE 0 CURRENT 49,826 49,826 FUTURE 0.03137 80,106 80,106 $0 $888,124 $0 $888,124 TOTAL $2,207,185 $1,009,614 $0 $3,216,799 PAGE 1 24- Feb -88 DATE CITY OF PARIS WATER EXPENSE FUNCTIONALIZATION 1988 u A P T AVERAGE DAY 1c PEAK DAY If PEAK HOUR 24 EXTRA CAPACITY TOTAL EXPENSE EXPENSE BASE MAX DAY MAX HOUR CUSTOMER RAW WATER STORAGE $27,174 $27,174 RAW WATER TRANSMISSION $220,447 $220,447 PURIFICATION PERSONNEL $229,205 $1!2,803 $76,402 SUPPLIES: CHEMICALS 162,000 162,000 MISC. 11,220 11,220 CONTRACTUAL OtX PAT MAYSE 0 POWER 204,553 204,553 MISC. 41,885 41,885 MAINTENANCE 64,215 42,108 15,001 7,106 0 SUB -TOTAL PURIFICATION $713,078 $614,569 $91,403 $7,106 $0 TRANSMISSION $171,724 $114,483 $57,241 $0 DISTRIBUTION PERSONNEL $101,914 $50,957 $50,957 SUPPLIES 6,544 3,272 3,272 CONTRACTUAL 15,647 7,823 7,823 MAINTENANCE 103,529 50,042 11,047 32,301 10,140 SUB -TOTAL DISTRIBUTION $227,634 $112,094 $11,047 $94,353 $10,140 HYDRANTS $38,446 $38,446 METERS 4 SERVICES $105,726 $105,726 BILLING 4 COLLECTING $131,615 $131,615 GENERA. FUND SUPPORT: CITY COUNCIL $18,626 18,626 CITY MANAGER 26,906 26,906 LEGAL 31,106 31,106 FINANCE 65,508 65,508 ENGINEERING 101,160 69,220 11,620 16,625 3,694 WAREHOUSE 34,563 4650 3,970 59680 1,262 GARAGE 14,507 9,927 1,666 2,384 530 PLUMBING IMSP. 15,555 15,555 SUB -TOTAL GEN. FUND SUPPORT $307,931 $179,435 $17,257 $24,689 $86,549 AUDIT FEES $6,550 $6,550 CAPITAL OUTLAY PAGE 2 24- Feb -88 DATE , Ri A F T CITY OF PARIS AVERAGE DRY WATER EXPENSE FUNCTIONALIZATION PEAK DAY 1988 PEAK HOUR DEBT SERVICE 1983 REFUNDING 1984 UTILITY BONDS PAT MAYSE CURRENT FUTURE SUB -TOTAL DEBT SERVICE $234,271 $147,683 $45,821 $40,767 $0 523,921 EXTRA CAPACITY 49,826 49,826 TOTAL 80,106 $888,124 $598,504 $134,214 $155,406 $0 EXPENSE EXPENSE BASE MAX DAY MAX HOUR CUSTOMER TRANSMISSION $129,000 $86,000 $43,000 DISTRIBUTION 188,600 94,300 94,300 METERS X SERVICES 4000 28,000 HYDRANTS 15,000 15,000 BILLING b COLLECTING 7,450 7,450 RAW WATER SUPPLY 10,300 10,300 SUB -TOTAL CAPITAL OUTLAY $378,350 $180,300 $43,000 $109,300 $45,750 DEBT SERVICE 1983 REFUNDING 1984 UTILITY BONDS PAT MAYSE CURRENT FUTURE SUB -TOTAL DEBT SERVICE $234,271 $147,683 $45,821 $40,767 $0 523,921 320,889 88,393 114,639 49,826 49,826 80,106 80,106 $888,124 $598,504 $134,214 $155,406 $0 GRAND TOTAL $3, 216 ,799 $2,047,006 $354,162 $429,301 $386,331 PERCENTAGES 100.00% 63.63% 11.01% 13.35% 12.01% /PAGE U vp" CITY OF PARIS CONSULTANT REcoveO)ED WATER REVENUE REQUIREMENTS _-, - ,T° BILLING A COLLECTING PERSONNEL SUPPLIES CONTRACTUAL MAINT. BLD65. EQUIP. AUDIT TOTAL BILLING i COLLECTING RAY WATER STORAGE RAY WATER TRANSMISSION WATER PRODUCTION PERSONNEL SUPPLIES CHEMICALS MISC. CONTRACTUAL O&M PAT MAYSE POWER MISC. MAINT. BLDG& EQUIP. AUDIT TOTAL WATER PRODUCTION WATER DISTRIBUTION PERSONNEL SUPPLIES CONTRACTUAL MAINT. BLDG& EQUIP. AUDIT SUB -TOTAL DISTRIBUTION TRANSMISSION 8' TO ( 30' TRANSMISSION 30' AND ABOVE HYDRANTS io�' 04- Mar-68 DATE CONSULTANT RECOMMENDED 87/88 REVENUE BUDGET RECOMMENDED ADJUSTMENTS REQUIREMENTS $178,150 ($89,075) $89,075 30,480 315,240) 13,240 46,450 ($23,225) (7,500) 15,725 3,000 41,5001 1,500 5,150 ($2,575) 2,575 10,000 ($10,000) 0 $273,230 tf 141, 615) `r ($7, 500) `;*�f $124,115 $27,174 $27,174 49,415 $220,447 $220,447 0.564 0.121 $229,205 sm+205 162,000 162,000 11,220 11,220 77,000 (77,000) 0 425,000 (220,447) 204,553 41,885 41,885 14,800 14,800 49,415 49,415 800 (800) 0 $1,011,325 ($77,800) ($220,447) $713,078 $243,345 ($187,024) 56,321 15,625 (12,009) 3,616 37,360 (28,713) 8,647 226,200 (173,847) 6,292 58,645 21,000 (169140) 41860 750 (750) 0 $544,280 ($418,482) f6, 292 $132,090 225,238 225, 238 48,322 45,708 94,030 38,446 38,446 l� MINUTES OF THE WATER AND SEWER RATE STUDY ADVISORY COMMITTEE March 10, 1988 The Water and Sewer Rate Study Advisory Committee met in special session, Thursday, March 10, 1988, 3:00 P. M., Council Room, City Hall, Paris, Texas. Chairman Kent called the meeting to order with the following members present: Councilman Bone and Councilman Wortham. Also present was City Manager, Michael E. Malone, City Attorney, T. K. Haynes, Director of Finance, W. E. Anderson, Director of Utilities, Herb Campbell, James Farris, Citizen, and City Clerk, Mattie Cunningham. Chairman Kent announced the purpose of the meeting was to received a briefing from our Consultants, Reed and Stowe, and Frees & Nichols, Inc. Jack Stowe of Reed and Stowe presented the Committee with a packet, attached hereto as Exhibit A, and made a part of these minutes, pertaining to the function of our water system stating the first two pages were the same as those presented at the last meeting with a few refinements which is basically taking the investment the City currently has, net of depreciation, and net of developers contributions and functionalizing that across as to base capacity, max day extra capacity, max hour extra capacity, and what investments dedicated to just having customers. You will see on page two that the grant total of $15,411,411. gets spread to base - $10,621,360., max day $1,757,741., max hour $22,663,832., and customer $368,478. Mr. Stowe pointed out that the next step was to develop from the operating data the allocation factors or percentages that each class has within these functions. Barry Sarma, Consulting Engineer with Freese & Nichols, Inc., appeared before the Committee explaining the percentage of customer class allocation factors on page three of the packet - Supply Reservoir - The City is using approximately 20% of the Reservoir the balance is in future storage, you will notice that Raw Water Transmission and Pumping, the base cost for example Campbell Soup pays 26.75% of that, but the extra capacity (max day) they pay only 6.69 %. Mr. Sarma said Campbell Soup takes a large amount of water through the system, but the variation is very little in their use, and usually the time of the usage is not during the peak time of other users. Mr. Sarma pointed out that under Treated Water Distribution there is a blank for transmission mains for Campbell Soup, explaining this is transmissions mains below 30 inches the reason for this is the 30 and 33 inch main that comes from the treatment plant from which Campbell Soup get it's water, and he has allocated that portion of the system to every customer class; therefore, these lines are used by residential and commercial only for distribution, storage and standpipes. Mr. Stowe said that now that we understand how the system is operating, they have functionalized the system based on how it is operating, they know how the classes of customers are using the system, they took the percentage and applied them to dollars as you can see on page four. Mr. Stowe said that the City has $15,411,411. invested and as of that amount they can identify there is $4,328,946. invested for the benefit Page 2 of the residential class, $4,504,280. for the Commercial class, $3,949,761. Campbell Soup, and $2,628,424. for Lamar County Water Supply District. Mr. Stowe explained that the only thing the investment use is since they are using a cash basis is to develop a method for allocation of debt service. The next step is to go in and look at the Revenue requirements using the 1987 -88 Budget as shown on page 5. The first item they looked at was Billing and Collecting, you will see adjustments made removing approximately 50% of the cost that will be assigned over to the sewer because the function of the Billing and Collecting is on an equal split between the Water and Sewer, also an adjustment of $7,500.00 was made due to the fact that $30,000. was budgeted for this study which would not be needed on an occurring basis, but you do need to be collecting something for future studies. Mr. Stowe said they had also picked up $27,174. for Raw Water Storage (Pat Mayse). On Raw Water Transmission $220,447. this is for power to pump water from Pat Mayse up to the treatment plant, Water Production you will see a decrease - the Operating and Maintenance Pat Mayse by $77,000., and just reallocated it, recognized for the $27,000. associated with operating and maintenance raw water, and $49,000. as debt service, and you can also see there is a whole series of expenses that we are reclassifying, and trying to get in alignment with grouping of plant, and the functional ization that we are trying to allocate to that being base, max hour, max day and customer charge. Mr. Stowe referred to page six pointing out Water Revenue requirements - the far right hand corner, after all adjustments have been made including the future storage cost of $80,106. for Pat Mayse, the total Revenue requirements of $3,309,533. for the test year, and said the next step is to test to see if the City will make those revenues under the existing rates. Going to page seven, you will see a summary for meter sizes A -I, we will collect $2,071,280., Campbell Soup's contract $825,032., Lamar County Water Supply District's contract $494,518. total of $3,390,830. Mr. Stowe reminded the Committee to remember the estimate on revenue requirement including the future capacity cost of $80,000. was $3,309,000., and what that shows is the current contracts and current rates are adequate to hit our revenue requirements for water. Mr. Stowe pointed out that the one thing missing out of this cost function is the Capital Outlay Budget, and asked the Committee to remember the planning process that needs to be considered. Mr. Stowe said the Engineering Department is analyzing the system and is going to come up with cost estimates of the Capital Improvements that are required to meet the low pressure complaints that the Committee has talked about, and maintenance items that need attention. Mr. Stowe also called the Committee's attention to the fact that this is based on a 24 month average, and what they are assuming when they project forward is that the average of the past 24 months are going to take place in the next 12 months. This may or may not be the case, you may have a real wet summer this year, it would be that the sales drop below the average, by the same token, if we have a very dry summer sales could increase. Mr. Stowe went to page 8 which shows 1987 -88 Contract Revenue for Campbell Soup, page 9, Lamar County Water Supply District's contract 1987 -88 contract revenues distribution service charge that gives you Page 3 the rate they should be paying for all water taken through the distribution system, page 10 is the City of Paris, Lamar County Water Supply District 1987 -88 contract revenue, capital recovery fee, this is the amount they pay for all water that comes from the water treatment plant, when you add those two figures together you will come up with the total from the summary sheet. Mr. Stowe said the next step is to establish where these cost should fall out, where should the revenue be coming from based on the cost of service study, the allocation factors that were developed, and what they have done on page 11 is to take all the expense items and functionalizing each one of the rate items into the base, max day, max hour. Page 12 will show the $3,309,533. and tells us that $2,103,657. is being spent for base, $388,756. for max day, $445,921. for max hour, and $371,198. for customer charge. Mr. Sarma gave the Committee a handout (attached hereto as Exhibit B) called Customer Water Use and Capacity Requirements, this shows how the four classes of customers use the system which are Residential, Commercial, Campbell Soup, and Lamar County Water Supply District, and that allocation has come on the basis of their average use of the system, extra capacity on peak day, and extra capacity on peak hour. Mr. Sarma said the overall peak was 160% of the average peak day, he estimated over 200% on peak hour. Mr. Sarma said of the 160% the system load has been broken up into the four classes - Residential 200 %, Commercial 170 %, Campbell Soup 125 %, and Lamar County Water Supply District 195% of the average, the peak hour Residential 300 %, Commercial 250 %, Campbell Soup 140 %, and Lamar County Water Supply District 200% on the basis of this you will see there are extra capacities of 30.53% Residential, 25.97% Commercial, 17.77% Campbell Soup, and 25.73% Lamar County Water Supply District. This is the allocation that has gone from the system to the classes. Mr. Sarma said the product from these numbers will give you the last two pages for cost allocations. These are the final figures that will be used to design the rate. After further discussion, the meeting adjourned. MARSHALL H. KENT, JR., CHAIRMAN ATTEST: MATTIE CUNNINGHAM, CITY CLERK 1 PAW 1 off- Mar -88 DATE CITY OF PARIS WATER INVESTMENT FJVIONALI2ATION 1988 EXTRA CAPACITY NET ASSET INVESTMENT BASE MAX DAY MAX HOUR CUSTOMER Billing /Collecting Land $6,439 $6,439 Buildings 18,577 18,577 Furn $ Fixtures 622 622 Machinery Tools i Equip 40,676 40,676 Automobiles 3,202 3,202 Sub -Total Billing /Collecting $69,516 $0 $0 $0 $69,516 Water Storage Pat Mayse: Current $1,044,104 $1,044,104 Future 2,553,587 2,553,587 Lake Crook 494,624 ✓ : 494,624 Lake Gibbons 151,735 ✓ 151,735 Sub -Total Water Storage $4,244,050 $4,244,050 $0 $0 $0 Ran Water Trans. $752,099 / $376,050 $0 $376,050 $0 Water Treatment Land Buildings $2,068 1,356 729,302-/ 4781229 483 170,367 229 80,705 . Filtration Plants 31388,786 ✓ 2,259,191 847,197 282,399 Stand Pipes i Reservoirs 237,859 118,929 118,929 Wells $ Pumps 865,728 567,689 202,237 95,802 Furn $ Fixtures 265 174 62 29 Machinery Tools i Equip 3,025 1,983 707 335 Instruments 1,767 11159 413 1% Motor Vehicles 10,305 61757 2,407 11140 Misc. Equipment 21273 1,490 531 251 Sub -Total Water Treatment $5,241,378 $3,436,958 $1,224,404 $580,016 $0 Water Distribution ' ME 2 04- Mar -88 DATE CITY OF PARIS WATER INNESTMENT FLKTIOMALI1ATIGN 1988 M Construction in Process $106,000 53,000 53,000 Grand Total $15,411,411 $10,6211360 $1,757,741 $2,663,832 $368,478 PERCENTAGES 100.00% 68.92% 11.41% 17.28% 139% f EXTRA CAPACITY NET ASSET INVESTMENT BASF MAX DAY MAX HOUR CUSTOMER Buildings $276 $139 $a $91 $16 Bridges i Culverts Mains: Transmission 1,569,000 1,046,000 523,000 Distribution 21833,260 1,416,630 11416,630 Meters i Boxes: 293,168 293,168 .625 .750 1.00 1.50 2.00 3.00 4.00 20.00 Service Lines: 0 .75 1.00 1.25 1.50 2.00 4.00 6.00 8.00 Hydrants t Valves 206,064 206,064 Machinery Tools i Equip 70,276 35,309 7,499 23,266 41203 Motor Vehicles 26,323 13,225 2,809 8,715 1,574 Sub -Total Water Distribution $4,998,368 $2,511,303 $533,337 $1,654,766 $298,962 Construction in Process $106,000 53,000 53,000 Grand Total $15,411,411 $10,6211360 $1,757,741 $2,663,832 $368,478 PERCENTAGES 100.00% 68.92% 11.41% 17.28% 139% f PAGE I CITY OF PARIS CUSN ITEM SUPPLY RESEVOIR BASE RAN WATER TRANS. 6 PIPPING BASE EXTRA CAPACITY (MAX. DAY) TREATMENT TREATMENT PLANT, TREATED WATER PUMPING AM TRAMS. BASE EXTRA CAPACITY (MAX. DAY) TREATED WATER DISTRIBUTION TRANS. MAINS 3 BASE EXTRA CAPACITY (MAX HOUR) DISTRIBUTION, STORAGE, AND STANDPIPES BASE EXTRA CAPACITY (MAX HOUR) HYDRANTS EXTRA CAPACITY (MAX HOUR) 09- Mar -88 DATE RESIDENTIAL COMMERCIAL CAMPBELLS LCWSD 16.40% 19.92% 38.15% 25.53% 7e r Tod° 1 y 11.49% 13.96% 26.75% 10.20% 11.49% 9.74% 6.69% 9.68% c 11.49% 13.%% 26.75% 10.20% 11.49% 9.74% 6.69% 9.68% 16.12% 19.58% 14.30% 19.88% 20.27% 9.85% 22.57% 27.43% 24.76% 25.24% 39.37% 40.13% 20.50% PAGE 1 09-Kr-88 DATE CITY OF PARIS r � S CLAS9 ALLOCATION �� � s o � s� SERV ITEM SUPPLY RESEVOIR STORAGE RAW WATER TRANS. AND PUMPING BASE EXTRA CAPACITY TOTAL TREATMENT AND PIMPING BASE EXTRA CAPACITY TOTAL DISTRIBUTION TRANS. 30" AND ABOVE BASE EXTRA CAPACITY TRANS. 80 AND t 301 BASE EXTRA CAPACITY DISTRIBUTION i 8' BASE EXTRA CAPACITY TOTAL GENERAL EQUIP RESIDENTIAL COMMERCIAL CAMPBELLS LCWSD $696,024 $845,415 $1,619,105 #1,083,506 $86,416 $104,993 $201,187 $76,714 86,416 73,254 50,315 72,803 $172,832 $178,248 $251,502 $149,517 $602,234 $73116% $1,402,069 $534,621 602,234 510,510 350,648 507,365 $1,204,469 $1,242,207 $1,752,717 $1,041,986 $94,488 $114,801 $219,980 03,880 94,488 80,097 55,015 79,604 120,359 146,193 0 106,770 148,433 1519345 0 739545 639,467 777,163 0 0 7019515 7159115 0 0 $1,798,752 $19984,714 $274,995 $343,799 $39,583 $43,675 $69051 $7,566 METERS $230,423 $57,606 $3,139 $2,000 HYDRANTS_ $81,128 $82,694 $42,243 $0 CUSTOMER ACCOUNTING $55,566 $13,892 $8 $50 CWIP $50,170 $55,830 $0 $A /S, Y //, y!/ $4,328,946 $4,504,280 $3,9499761 $2,628,424 PERCENTAGES 28.09% 29.23% - 25.63$ 17.06% PAGE 1 CITY OF PARIS CONSULTANT REcoN E3DED RATER 109K REOUIRE)ENTS BILLING i COLLECTING PERSONA SUPPLIES CONTRACTUAL MAINT. BLDG& EQUIP. AUDIT TOTAL BILLING 4 COLLECTING RAW WATER STORAGE RAW WATER TRANSMISSION WATER PRODUCTION PERSONNEL. SUPPLIES DENICALS NISC. CONTRACTUAL DAN PAT MAYSE POWER MISC. NAINT. BIDGS. EQUIP. AUDIT TOTAL WATER PRODUCTION WATER DISTRIBUTION PERSONNEL. SUPPLIES CONTRACTUAL NAINT. aim EQUIP. AUDIT SUB-TOTAL DISTRIBUTION TRANSMISSION 8' TO ( 30' TRANSMISSION 30' AND ABOVE •` HYDRANTS 04 -hw-88 DATE -• CONSULTANT RECON ENDED 87/88 REA E BUDGET RED ADJUSTMENTS REQUIREMENTS $178,150 ($89,075) $89,075 30,480 (115,240) 15,240 4(,450 ($23,225) (7,500) 15,725 39000 ($1,500) 1,500 5,150 ($2,575) 2,573 10,000 ($10,000) 0 $273,230 ($141,615) °`r 07,500) ';��1 $124,115 $27,174 $27,174 $19011,325 ($77,800) ($220,447) $713,078 $243,345 ($187,024) 15,625 $220,447 $2209447 319360 (28,713) $229,245 $229,205 162,000 162,000 11,220 11,220 779000 (77,000) 0 425,000 (220,447) 204,553 41,885 41,885 14, 800. 14,800 49,415 49,415 800 (800) 0 $19011,325 ($77,800) ($220,447) $713,078 $243,345 ($187,024) 15,625 (12,009) 319360 (28,713) 226,200 (173,847) 6,292 219000 (169140) 750 (750) $544,280 tf418,482) i6, 292 0.564 225,238 0.121 A322 4%708 38,446 Y ' PAGE 2 07-Nar -88 DATE CITY OF PARIS �ti�TANC CONSULTANT RECOMMENDED 87/88 REVENUE RES RECOMMENDED ADJU57MENTS REQUIREMENTS METERS AM SERVICE 105,726 105,726 TOTAL DISTRIBUTION $544,280 ($750) $52,000 $595,530 AMMDIT FEES $6,55D $6,550 � n� - (, CITY COLKIL $18,626 $18,626 Cm MANABEA 26,906 26,906 LEGAL 31,106 31,106 FINANCE 65,508 65,508 ENGINEERING 101,160 101,160 WAREHOUSE 34,563 34,563 GARAGE 14,507 14,507 PLUMBING INSP. 159555 15,555 HYDRANTS $307,931 $307,931 CAPITAL OUTLAY BILLING 6 COLLECTING $79450 $71450 RAW WATER SUPPLY 10,300 10,300 TRANSMISSION 36,300 36,300 DISTRIBUTION MAINS 263,700 263,700 EQUIP 17,600 17,600 METERS A SERVICES 4000 28,000 HYDRANTS 15,000 15,000 $378,350 $378,350 PROJECTED 1987/88 FISCAL YEAR CURRENT RATES AND CONTRACT INTERPERTATIONS A $1,374,457 B 7,815 C 73,145 D 76,%3 E 300,300 F 48,020 6 67,980 H 3,602 I 118,999 $2,071,280 CANBELL SOUP 825,032 Los elk 494,518 Q s oX f app TOTAL �aOT oJ�C ►830, J",v- v9. ' a g3 3 � 3R s3 q 87/88 BUDGET $3,251,395 EST. SURPLUS $139,435 PAGE i CITY OF PARIS CAlPBEUS SOUP ASSUMPTIONS SALES TD CAMPBELLS > 1 MILLION CUBIC FEET 224,304,647 TOTAL WATER SALES 480,567,406 PERCENT TO TOTAL 46.67% BUDGETED PRODUCTION O:M $1,021,625 BUDGETED PRODUCTION PERSONNEL $2299205 83 REFUNDING $346,408 CONTRACTUAL PERCENTAGE 84 UTILITY BONDS $830,737 CONTRACTUAL PERCENTAGE AGENT FEES $1,489 ADMINISTRATIVE CHARGE 6.50% RATE TO BE . pER 100 £ SIN EXCES5OF�ICIMC� TOTAL ANNUAL REVENUES: FIRST i MILLION CU. FT. PER MOM $60,059 BASE CUSTOMER CHARGE 15,600 VOLUME RATE 749„373 TOTAL CAMPBELLS REVENUES $ 0, 032 56.60% 62.30% F PAGE I CITY OF PARIS LAMAR COUNTY WqliP1.Y DISTRICT 4987!88 CONTRACT DISTRIBUTIa1.5ERViCE q:�116E BUDGETED O&N $544,280 LESS: PROFIT 10.00% METERS 4 METER BOXES (309000) SERVICE LINES (14,000) NYDRllNTS 3 VALVES (16,000) ADJUSTED OIN $484,280 83 BONG DIST. P3I 3,555,124,768 $346,556 11.00% $38,121 84 BOND P$I $831,638 17.30% $143,873 BUDGETED CAPITAL OUTLAY ASSOC. WITH WATER STORAGE, PUMP STATIONS, AND MAINS $371,600 ADMIN. CHARGE 5.50% $67,462 PROFIT 10.00% $110,534 TOTAL $1,215,870 LCWSD SALES THRU DIST. 184,387,640 TOTAL WATER SALES 3,555,124,768 CAMPBELL SALES (19767,694,230) LCWSD SALES BEFORE DIST. (405,583,410) SALES THRU DIST. 19381,847,128 COIiTRACT m PERCENTAGE 13.34% $162,240 1000,s1i. ,^..Y"'.i"':.s y„,.,,k..: t,y�•... -gin ^? y T` .� AATE PER l00 CUBIC FEET, ;�' •�'-; �,�°, .`$0:6582 PAGE I CITY OF PARIS LANAR COUNTY WATER SUPPLY DISTRICT �yRRf'TI REVENUES 6 T CAPITAL RECOVERY FEE FACILITIES IN PLACE AT 10/1/89 M418 DEPRECIATION ON WiTP ADDITIaG SINCE 10/1/84 (4810102- 701617- 50000)/35 YEARS 115,957 83 BOND PROD. INT. $256,407 0.566 145,126 AGENT FEES 149 84 BIND PROD. INT. $565,638 iW 291,3D4 AGENT FEES 1,000 DEPRECIATION ON CAPITAL OUTLAY SINCE 10/1/84 4,172 SUB? -TOTAL $650,126 CONTRACTUAL PERCENTAGE 0.21 $136,526 BUDGETED OIN PRODUCTION $1,011,325 LCHSD SALES 589,971,050 TOTAL SALES 4,055,878,000 CONTRACTUAL PERCENTAGE A.55% $147,108 ADMINISTRATIVE DUARGE 0.065 $18,436 PROFIT 0.1 $30,207 TOTAL REVENUE REQUIREMENT $332,278 FSY -f'." �_ � x.�a•.AA y - K��T ft4213 .,� 07- Mar -88 DATE AVERAGE DAY PEW( DAY PEAK HOUR EXTRA CAPACITY TOTAL EXPENSE EXPENSE BASE MAX DAY MAX HOUR CUSTOMER RAW WATER STORAK $27,174 $27,174 RAW WATER TRANSMISSION $220,447 $220,447 PURIFICATION $124,115 9 $124,115 GENERAL FUND SUPPORT: PER50 M $229,205 $152,803 $76,402 18,626 SUPPLIES: 269906 26,906 LEGAL 31,106 CHEMAICALS 162,000 162,000 65,508 65,508 NISC. 11,220 11,220 11,538 17,485 2,419 WAREHOUSE 34,563 CONTRACTUAL 31942 5,974 826 GARAGE 14,507 91998 19655 21508 347 DAN PAT MWYSE 0 15,555 POWER 204,553 204,553 NISC. 41,885 41,885 MAINTENANCE 64,215 42,108 15,001 7,106 0 TOTAL PURIFICATION $713,078 $614,569 $91,403 $7,106 $0 DISTRIBUTION PERSOM a $56,321 $28,161 $28,161 SUPPLIES 3,616 1,808 1,808 CONTRACTUAL 8,647 41323 41323 MAINTENANCE 73,593 36,975 7,853 24,364 4,402 SUB -TOTAL DISTRIBUTION $142,178 $71,267 $7,853 $58,656 $4,402 TRAIMISSION- V TO 1 30" 29,566 160,376 94,189 TAANSNISSION 30• AND ABOVE 54,614 34,407 20,207 HYDRANTS 38,446 $38,446 METERS 4 SERVICES 105,726 $105,726 TOTAL DISTRIBUTION $595,530 $266,051 $122,249 $97,102 $110,128 ill BILLING i COLLECTING $124,115 9 $124,115 GENERAL FUND SUPPORT: CITY COUNCIL $18,626 18,626 CITY MANAGER 269906 26,906 LEGAL 31,106 31,106 FINANCE 65,508 65,508 ENGINEERING 101,160 69,718 11,538 17,485 2,419 WAREHOUSE 34,563 23,820 31942 5,974 826 GARAGE 14,507 91998 19655 21508 347 PLUMBING INSP. 15,555 15,555 wA07- Mar-88 2 DATE CITY OF PARIS AVERAGE DAY WATER EXPENSE FUNCTIONALIIATION PEAK DAY 1988 PEAK HOUR EXTRA CAPACITY R TOTAL EXPENSE EXPENSE BASE MAX DAY MAX HOUR CUSTOMER TOTAL GEM. FUND SUPPORT $307,931 $1809175 $17,134 $25,967 $84,655 AUDIT FEES f61550 gh 550 CAPITAL OUTLAY TRANSMISSION $36,300 $24,200 $12,100 DISTRIBUTION 281,300 140,650 140,650 METERS & SERVICES 28,000 28,000 HYDRANTS 15,000 15,000 BILLING & COLLECTING 7,45D 7,450 RAN WATER SUPPLY 10,300 109300 TOTAL CAPITAL OUTLAY $378,350 f $164,850 $12,100 $155,650 $45,750 DEBT SERVICE 1983 REFUNDING $234,271 $147,683 $45,821 $40,767 $0 1984 UTILITY BONDS 572,155 3529776 100,049 119,330 PAT MAYSE mom 49,826 49, 826 FUTURE 80,106 80,106 MTN. DEBT SERVICE $936,358 $630,392 $145,870 $160,096 $0 GRAND TOTAL $3, 309 ,533 $29103,657 $388,756 $4459921 $371,196 PERCENTAGES 100.00% 63.56% 11.75% 13.47% 11.22% R PAGE I 09- Mar -88 DATE CITY OF PARIS CUSTMR CLASS COST ALLOCATIONS i EXPENSE RESIDENTIAL COMMERCIAL CAMPBELLS LCWSD RAN WATER STORAGE $4,457 $5,413 $10,367 $6,938 RAW WATER TRANSMISSION $40,606 $49,314 $94,506 $36,021 PURIFICATION CITY COUNCIL $6,224 PERSONNEL 52,671 54,322 76,646 45,566 SUPPLIES: 6,045 3,836 LEGAL 10,402 CHEMICALS 29,840 36,239 69,449 26,471 MISC. 2,578 2,659 3,752 2,231 CONTRACTUAL 25,926 179253 HA10MUSE 9,708 OM PAT MAYSE 81858 518% SWAM 49075 POWER 37,679 45,758 87,692 33,424 NISC. 9,625 91927 14,006 8,327 MAINTENANCE 14,757 15,219 21,473 12,766 TOTAL PURIFICATION $147,150 $164,124 $273,019 $128,784 DISTRIBUTION PEAL 26,657 29,664 0 0 SUPPLIES 1,712 11905 0 0 CONTRACTUAL 49093 4,554 0 0 MAINTENANCE 34,832 38,762 0 0 SUB -TOTAL DISTRIBUTION $67,293 $74,885 $0 $0 TRANSMISSION 12,550 12,944 18,263 10,8357 (30" AND GREATER) TRANSMISSION M"TO ( 30" 1 91,644 101,444. 0 61,478 HYDRANTS 15,136 15,428 7,881 0 METERS i SERVICES 84,581 21,145 TOTAL DISTRIBUTION $271,204 $225,847 (26,144 $72,335 BILLING 9 COLLECTING $98,051 $24,513 $310 $1,241 GENML FUND SUPPORT: CITY COUNCIL $6,224 $5,201 $49482 $2,719 CITY MANAGER 81998 8,026 6,045 3,836 LEGAL 10,402 9,279 6,989 4,435 FINANCE 21,907 19,542 14,719 9,340 ENGINEERING 28,415, 29,566 25,926 179253 HA10MUSE 9,708 10,102. 81858 518% SWAM 49075 4,240 31718 29474 --PAGE 2 09-Mr-68 DATE CITY OF PARIS CUSTOMER CLASS COST ALLOCATIONS EXPENSE RESIDENTIAL. COMMERCIAL CAMBELLS LCWSD PlMINS INSP. 12,444 3,111 L TOTAL LIEN. FUND SUPPORT $102,174 $89,068 $70,737 $45,953 a. 30�,��3 AUDIT FEES $2,190 $1,954 $1,472 $934 CAPITAL OUTLAY TRANSMISSION $13,068 $14,466 $0 $8,766 DISTRIBUTION 133,139 148,161 0 0 METERS & SERVICES 22,400 5,600 HYDRANTS 5,906 6,020 3,075 0 BILLING 6 COLLECTING 5,960 1,490 RAW WATER SUPPLY 1,689 2,052 3,929 2,630 TOTAL CAPITAL OUTCRY $182,162 $177,788 $7,004 $11,396 DEBT SERVICE 1983 REFUNDING TREATMENT $45,075 $46,488 $65,593 $38,995 DISTRIBUTION 15,576 17,186 2,381 2,977 1984 UTILITY BONDS TREATMENT 98,420 101,503 143,218 85,143 DISTRIBUTION 58,785 64,862 8,987 11,236 s RESERVOIRS CURRENT 8,171 9,925 19,009 12,721 FUTURE 13,137 15,957 30,560 20,451 TOTAL DEBT SERVICE $239,165 $255,922 $M9,748 $17115M GRAND TOTAL. i, 087,160 $993, /$751,308, $475,1 PERCENTAGES 32.85% 30.03% 22.76% r 14.36% • /� /�,� n�0 Dap �� +� //G, M • i�' M Residential Ccmi*xcial Campbell LCWSD AVERAGE DAY (Z!(ID) 2.047 2.487 4.763 1.816 18.42 22.38 42.86 16.34 11.113 100.00 160 200 17.817 22.250 6.704 100.00 11.137 100.00 TABLE NO. 4.9 FY- -1987 CUMME R WATER USE AMID CAPACITY REQU REDTE M CAPACITY FACMIR IMM CAPACITY EXTRA CAPACITY PEAK DAY PEAK HR PEAK DAY PEAK TRt PEAK DAY PEAK BLUR % % (MM) (MCA) (1M) % (MM) % 200 280 4.094 5.732 2.047 30.53 3.685 33.09 170 250 4.228 6.218 1.741 25.97 3.731 33.50 125 140 5.954 6.668 1.191 17.77 1.905 17.10 195 200 3.541 3.632 1.725 25.73 1.816 16.31 160 200 17.817 22.250 6.704 100.00 11.137 100.00 MINUTES OF THE SPECIAL MEETING OF THE WATER & SEWER RATE STUDY ADVISORY COMMITTEE April 7, 1988 The Water & Sewer Rate Study Advisory Committee met in special session, Thursday, April 7, 1988, 5:45 P. M. Council Room, City Hall. Chairman Marshall H. Kent, Jr. called the meeting to order with the following members present: Councilman Wortham, James Farris, Herb Campbell, Director of Utilities, W. E. Anderson, Director of Finance, Michael E. Malone, City Manager, T. K. Haynes, City Attorney, and City Clerk, Mattie Cunningham. Barry Sarma, Consulting Engineer with the firm of Freese and Nichols, Inc., appeared before the Committee briefing them on the wastewater side of the City of Paris's rate study, and as of October 1987 there were 9,575 wastewater accounts of those, 8,191 were Residential, 1,355 Commercial, 16 Industrial, and 12 outside the city limits customers. We found in the last two years the water effluent averaged 4.05 million gallons a day, out of that reach averaged approximately 1.33 (I &I), the BOD per day averaged 190 milligrams per liter. Mr. Sarma said he felt the system worked good in dry weather, but during wet weather there were problems due to bypasses. Mr. Sarma stated that in order to do this study they had to subtract out Campbell Soup's water usage in order to make a connection between the water and wastewater relationship of what quantity of water that is used that gets in the wastewater facilities because as you know, Campbell Soup buys close to 50% of the clear water, and only discharges about 1% of the wastewater into the wastewater system. Lamar County Water Supply District has to be removed because they do not use the wastewater facility. Mr. Sarma stated that the test year data tells us that Residential Customers contribute 42% of the flow per day, 36.8% Commercial, 16.9 Industrial, and 3.3% Merico. In terms of BOD contributions, Residential contributed 33.7% per day, Commercial 28.8 %, Industrial 13.4, these are close to what their flow is, but Merico's BOD per day is 24.1% compared to their flow of 3.3% per day plus 9.7% per day for TSS. Mr. Sarma said on the basis of this, they have gone in and functionalized the cost into the components of plant collection, treatment, and customer cost. Jack Stowe of Reed and Stowe, explained that the process after receiving the allocation factors from Mr. Sarma is similar to those used for the water, that is, they functionalized the investments, then developed the revenue requirements, then they did the functional ization of the revenue requirements and allocated those to the customers classes. Mr. Stowe presented the Committee a handout , attached hereto as part of these minutes as exhibit A. Mr. Stowe said that based on records of the city, the city has a total of $9,848,178. invested in the wastewater system. Of that amount $4,380,805. is in the plant, $5,047,982. in collection, $69,516. Billing, and construction work in process is approximately $350,000. Mr. Stowe said in doing cost allocation the collection system is basically a volume related Page 2 function, so 100% is going in to the volume component, as you can see on page one; however, the treatment plant is a different situation because the plant is designed not only to meet the strength loading consisting of the BOD, TSS, and Ammonia loading, and what they have done is to utilized the design criteria of the plant. Mr. Stowe said they could go in and look at the specific assets that is within the treatment plant and identify out of those investments in total how much is related to each function, and as you can see, we have functionalized the actual treatment plant for $4,380,805. - volume $602,384., BOD strength $2,376,141., TSS strength $1,302,073., and NH3 strength $100,207. Mr. Stowe said that page two was a recap of those figures. Mr. Stowe said the next step, which is on page three, is the actual development of the wastewater revenue requirements. The first item is customer accounting, and in the budgeting process, this is captured under water in total. Mr. Stowe asked the Committee to remember that there was a reduction in Customer Accounting by $124,000. in the water section, they are now moving that amount over to the sewer component so that they can recognize it as a wastewater function. On the Wastewater Treatment Plant, we have budgeted $664,985., there are several items that needed adjusted, electricity $63,478., and building maintenance $63,278. with a total adjustment of $791,471. The Sanitary Sewer has been increased from $336,995. to $356,995. representing an increase of $20,000. contributing to building maintenance. There were no adjustments in the Lift Stations at this time. General Fund Support, they identified $294,383. relating to the General Fund services provided on behalf of the wastewater system and it's operation. Audit fees, they picked up $5,000. which is only a reclassification, Debt Service, you can see there was no adjustment. Mr. Stowe placed emphasis on the present budget, the Capital Outlay for Wastewater Treatment was $11,000. and Sanitary Sewer was $27,000. Mr. Stowe stated that they were aware of the current EPA Order for the Wastewater System, and they were waiting before finalizing this report, that City Staff is working on a capital improvement program, which will address some of the problems that are existing in the Wastewater Collection system, but as Mr. Sarma highlighted there was 1.3% MGD a day as far as inflow - infiltration, and based on our estimates of the cost at this time for treatment that adequates for approximately $2,000.00 a day due to the inflow - infiltration, so this is a number we have to be aware of, and recognize the need to develop a plan and spend money that is necessary to improve the system. Mr. Stowe said if the I & I could be cut in half, from the 33.3% to 16 %, that would be saving of $365,000. a year, this amount would finance approximately 3.5 million dollars in improvements, in other words, the savings would pay for the debt service. Mr. Stowe referred to page four where you can see that the grant total from what was budgeted 1.5 million dollars, it has been increased to 2.1 million dollars for revenue requirements for wastewater. The next step is to functionalize these expenses which is shown on page 5. For Customer Accounting, again this is a customer charge that flows straight across, Wastewater Treatment total was $791,741. of which $156,105. relates to volume, $355,251. BOD, $251,179. TSS, and $29,206. NH3, Sanitary Sewer is a volume related item which is $356,995., Lift Page 3 Station is the same volume related in the amount of $142,345. In the General Fund this has been allocated based on the expense items above - of the $294,383, volume relates $77,768., BOD $126,292., TSS $73,778., NH3 $6,477., and customers $10,068., Audit Fees are again spread across the board for a total of operating and maintenance of $1,715,579. The Debt Service 1983 and 1984 gives a grant total of $2,212,637. of the grant total $983,254. was functionalized for volume, $580,946. BOD, $379,655. TSS, $39,932. NH3, and $137,850. customer cost. Mr. Stowe said the final step after function into customer classes. This allocation is b, loading for BOD, TSS that is in your existii ammonia based on that and related flow voluu find that Residential is $911,021., Commer $299,249., and Merico as a separate item $2,121,637. The last schedule on page 7 is not made a contribution to the plant expan! the city had to fund that expansion at the 1984 bond issue, the cost of service as you $58,000. for residential, $50,000. Commercia Merico would have gone up $13,000. Merico I dollars to the plant expansion, and has b $143,000. a year to the over all customer c becomes imperative as we move forward into lookina at the contract price in relation lization is the allocation sed on the 250 MG strength g ordinance, and 30 MG for e that Barry addressed, we ial $701,965., Industrial $209,402. for a total of a comparison if Merico had ion that was made, and if ;ame time they put out the can see would have gone up , Industrial $21,000., and as contributed 1.1 million ?en a definite benefit of lass cost of service which the rate design issue, and to the benefits that the system is receiving, in other words, we will anticipate as we go through the contract pricing that Merico is going to be paying something less than the $209,000. because in our cost of service, or the $209,000. does not acknowledge the fact they contributed and bought 1.1 million dollars worth of capacity in the plant. What we will do is run through the contract pricing which does recognize that contribution and compare what we will collect under the contract to the $143,000. benefit to the system, and as long as that difference is not more than $143,000., the city will be ahead. Mr. Stowe advised the Committee that they were also developing a rate for the Industrial Surcharge, and at this point, we need to establish the Capital Outlay that is required, then they will be at a point of designing the rate. Mr. Stowe said the next report the Committee will get will be the final rate with all the documentations and findings. Mr. Stowe also stressed the importance of developing a 5 to 10 year plan as to where we are going with the system. There being no further business, the meeting adjourned. MARSHALL H. KENT, JR. CHAIRMAN ATTEST: MATTIE CUNNINGHAM, CITY CLERK Table 7.6 Wastewater Loading Characteristics (FY 1986 -87) Customer Average Day BOD /Day TSS /Day Flow (MGD ) lbs ( %) lbs X Residential 1.17 43.0 2,196 33:7 2,693 41.9 Commercial 1.00 36.8, 1,877 28.8 2,301 35.9 Industrial 0.46 16.9 874 13.4 801 12.5 Merico 0.09 3.3 1,572 24.1 623 9.7 Subtotal 2.72 100.0 .6,519 100.0 6,418 100.0 I/I Total 1.33 Total 4.05 r Ammonia lbs ( %) 305 43.6 261 37.3 132 18.9 2 0.3 700 100.0 7.12 CITY OF PARIS TABLE R-S 8.1 WASTEWATER PLANT FUNCTIONALIZATION ODD TSS NH3 ITEM TOTAL VOLUME STRENGTH STRENGTH STRENGTH CUSTOMER LAND $4,400 $605 $2,387 $1,308 $101 $0 BUILDINGS 1,342,832 51,236 822,661 432,538 36,397 0 TREATMENT PLANT 830,271 31,679 508,650 267,438 22,504 0 MASTER PUMP STA. 392,265 392,265 MACHINERY, TOOLS, EQUIP., AND VEHICLES SLUDGE DISPOSAL 219,364 TOTAL 109,682 109,682 W i S BILLING $69,516 LIFT STA. 8,353 8,353 4' PUMP 3,465 3,465 PLANT EXPANSION 1,472,450 56,181 902,069 474,289 39,911 PUMPS 50,820 50,820 MACHINERY, TOOLS, EQUIP., AND VEHICLES 56,585 7,781 30,692 16,818 1,294 0 $4,380,805 $602,384 $2,376,141 $1,3022,073 $100,207 $0 LAND $6,270 $6,270 LIFT STATIONS 57,794 57,794 SANITARY SEWER 3,455,691 3,455,691 FLOW EQUALIZATION 526,616 526,616 CENTRAL INTERCEPTOR 608,995 608,995 MANHOLES 143,466 143,466 PUMPS 14,404 14,404 SERVICE LINES 138,725 138,725 MACHINERY, TOOLS, EQUIP., AND VEHICLES 96,021 96,021 TOTAL $5,047,982 $5,047,982 $0 $0 $0 W i S BILLING $69,516 $69,516 CWIP $349,875 $349,875 TOTAL $9,848,178 $6,000,241 $2,376,141 $1,302,073 $100,207 $69,516 ITEM TREATMENT PLANT COLLECTION SYSTEM Y i S BILLING CYIP TOTAL 2�. s TABLE R-S 8.2 CITY OF PARIS PLANT SUMMARY $9,848,178 $6,000,241 $2,376,141 $1,302,073 $100,207 $69,516 1) BW TSS NH3 TOTAL VOLUME STRENGTH STRENGTH STRENGTH CUSTOMER $4,380,805 1602,384 $2,376,141 $1,302,073 $100,207 5,047,982 5,047, 982 0 0 0 69,516 69,516.00 349,875 349,875 $9,848,178 $6,000,241 $2,376,141 $1,302,073 $100,207 $69,516 1) CUSTOMER ACCOUNTING WASTEWATER TREATMENT: PERSONNEL SUPPLIES CONTRACTUAL: ELECTRICITY OTHER MAINTENANCE: BUILDINGS EQUIPMENT CAPITAL OUTLAY TOTAL SANITARY SEWER: PERSONNEL SUPPLIES CONTRACTUAL: ELECTRICITY OTHER MAINTENANCE: BUILDINGS EQUIPMENT CAPITAL OUTLAY TOTAL LIFT STATIONS: PERSONNEL SUPPLIES CONTRACTUAL: ELECTRICITY OTHER MAINTENANCE: BUILDINGS EQUIPMENT CAPITAL OUTLAY TOTAL CITY OF PARIS WASTEWATER ATER REVENUE REQUIREMENTS 1987/88 BUDGET ADJUSTMENTS $316,475 27,650 181,930 31,500 43, 800 52,520 11,110 $664s'985 $152,240 17,150 800 14,345 99,000 26,460 27,000 $336,995 $65,705 5,110 44,000 7,210 4,745 15,575 a $142,345 (124,415 63,478 63,278 $126,756 20,000 $20,000 $0 REVENUE REQUIREMENTS $124,415 $316,475 27,&% 245,408 31,500 107,078 52,520 11,110 $791,741 $152,240 17,150 804 14,345 119,000 26,460 $356,995 $65,705 5,110 44,000 7,210 4,745 15,575 0 $142,345 TABLE R -S 8.3 PAGE 1 OF 2 CITY OF PARIS WASTEWATER REVENUE REQUIREMENTS s zht�, y TABLE R—S 8.3 PAGE 2 OF 2 ADJUSTMENTS 1987/88 BUDGET GENERAL FUND SUPPORT: $9,5% CITY COUNCIL 13,861 CITY MANAGER 16,025 LEW 33,747 FINANCE 179,840 ENGINEERING WAREIMSE 14,814 GARAGE PLUMBING INSP. 10,944 TOTAL $0 AUDIT FEES $700 DEBT SERVICE: $5,700 1983 0.42 $146,593 1984 0.31 259,465 TOTAL. $406,058 GRAND TOTAL $1,551,083 s zht�, y TABLE R—S 8.3 PAGE 2 OF 2 ADJUSTMENTS REVEM E REQUIREMENTS .$915% $9,5% 13,861 13,861 16,025 16,025 -,33,747 33,747 179,840 179,840 14,814 14,814 10,%4 10,944 15,556 15,556 $294,383 $294,383 $5,000 $5,700 $146, 593 $0 $406,058 CUSTOMER ACCOUNTING WASTEWATER TREATMENT: PERSONNEL SUPPLIES CONTRACTUAL: ELECTRICITY OTHER MAINTENANCE: BUILDINGS EQUIPMENT CAPITAL OUTLAY TOTAL SANITARY SEWER: PERSONNEL SUPPLIES CONTRACTUAL: ELECTRICITY OTHER MAINTENANCE: BUILDINGS EQUIPMENT CAPITAL OUTLAY TOTAL LIFT STATIONS: PERSONNEL SUPPLIES CONTRACTUAL: ELECTRICITY OTHER MAINTENANCE: BUILDINGS EQUIPMENT CAPITAL OUTLAY TOTAL CITY OF PARIS WASTEWATER EXPENSE FUNCTIONALIZATION REVENUE REQUIREMENTS VOLUME DOD TSS NH3 CUSTOMER (124,415 $124,415 $316,475 $43,517 $171,655 $94,063 $7,239 $0 27,650 3,802 14,997 8,218 632 0 245,408 71,400 64,947 92,098 16,%3 31,500 4,331 17,086 9,363 721 0 107,078 14,724 58,079 31,826 21449 0 52,520 7,222 28,487 15,610 1,201 0 11,110 11,110 $791,741 $156,106 $355,251 $251,179 $29,206 $0 $152,240 $152,240 17,150 17,150 800 800 14,345 14,345 119,000 119,000 26,460 26,460 27,000 27,000 $356,995 $356,995 0 0 $65,705 $65,705 5,110 5,110 44,000 44,000 7,210 7,210 4,745 4,745 15,575 15,575 0 0 $142,345 $142,345 TABLE R-S 8.4 PAGE 1 OF 2 , �y GENERAL FUND SUPPORT: CITY COUNCIL CITY MANAGER LEGAL FINANCE ENGINEERING WAREt0USE GARAGE PLUMBING INSP. TOTAL AUDIT FEES TOTAL O 3 M DEBT SERVICE: CITY OF PARIS WASTEWATER EXPENSE FUNCTIONALIIATION REVENUE REgUIREMENTS VOLUME BOO TSS NH3 CUSTOMER TABLE R-S 8.4 PAGE 2 OF 2 $9,5% $4,443 $2,408 $1,703 $198 $843 13,861 6,418 3,479 2,460 286 1,218 16,025 7,420 4,022 2,844 331 1,409 33,747 15,627 8,470 5,988 6% 2,%6 179,840 24,729 97,545 53,452 4,114 0 14,814 6,860 3,718 2,629 306 1,302 10,944 5,068 2,747 1,942 226 %2 15,556 7,203 3,904 2,760 321 1,367 $294,383 $77,768 4126,292 $73,778 $6,477 $10,068 $5,700 $2,639 $1,431 $1,011 $118 $501 $1,715,579 $735,854 $482,973 $325,968 $35,800 $134,984 1983 $146,593 89, 315.20 35, 369.49 19, 381.71 1,491.61 1,034.76 SUB -TOTAL $1,862,172 $825,169 $518,343 $345,350 $37,292 $136,019 1984 $259,465 $158,086 $62,603 $34,305 $2,640 $1,832 GRAND TOTAL $2,121,637 $983,254 $580,946 $379,655 $39,932 $137,850 cm RESIDENTIAL COMMERCIAL INDUSTRIAL MERICO TOTAL RESIDENTIAL COMMERCIAL INDUSTRIAL MERICD TOTAL TABLE R-S 8.5 CITY OF PARIS CUSTOMER CLASS COST ALLOCATION WITH MERICO CONTRIBUTION % OF CUSTOMER VOLUME BOD TSS NH3 TOTAL TOTAL CHARGE CHARGE CHARGE CHARGE CHARGE $911,021 42.94% $115,997 $422,799 $1951779 $159,075 $17,370 701,965 33.09% 21,625 361,838 167,312 136,296 14,895 299,249 14.10% 228 166,170 77,847 47,457 7,547 209,402 9.87% 32,447 140,008 36,827 120 $2,121,637 100.00% $137,850 $983,254 $580,946 $379,655 $39,932 WITHOUT MERICO CONTRIBUTION % OF CUSTOMER VOLUME BOO TSS NH3 TOTAL TOTAL CHARGE CHARGE CHARGE CHARGE CHARGE $969,658 42.81% $116,849 $460,354 $207,434 $167,016 $18,005 751,572 33.18% 21,783 393,977 177,273 143,100 15,439 321,290 14.19% 230 180,930 82,481 49,826 7,823 222,462 9.82% 35,329 148,343 38,665 124 $2,264,981 100.00% $138,862 $1,070,590 $615,531 $398,607 $41,391 MINUTES OF THE WATER & SEWER COMMITTEE MEETING June 13, 1988 The Water & Sewer Committee met, Monday, June 13, 1988, 6:00 P. M., City Council Chambers, City Hall, Paris, Texas. Chairman, Eric Clifford called the meeting with Councilman Curtis Fendley present. Also present was City Manager, Michael E. Malone, City Attorney, T. K. Haynes, City Engineer, Earl Smith, and City Clerk, Mattie Cunningham. Chairman Clifford called for consideration of and action of a request from Ralph Taylor for City participation in water line extension for a new church building on Loop 286 South. Ralph Taylor, Minister of the Bethel Temple Church, appeared before the Committee and review his previous proposal of using a pool for drafting, underground water system, and reintroduced this to the Committee. Mr. Taylor also suggested that the city furnish pipe for the proposed water line, and the church would install the pipe, or the church would furnish the pipe, and the church would install it. Steve Burgin, Fire Chief, appeared before the Council stating the use of the pool was still out of the question, the deep well system would work, but would have to meet certain standards, and would be expensive. Chairman Clifford explained to Mr. Taylor that the City's policy did not include participate in water line extension, only upgrading of pipe from a six inch pipe, then the City would pay the difference in that, and the City Engineering Department would decide the size of pipe that was needed. Chairman Clifford suggested that Mr. Taylor get with the City Engineer and work out the procedures for the water line. City Attorney Haynes told Mr. Taylor that the City would secure right -of -way for the water line which was normally donated. City Manager Malone told Mr. Taylor the first step would be to get a licensed Engineer to draw up plan and present to the City Engineer, and would have to have a licensed plumber to make the tap. Leonard Owens, 1128 Cooper Street, appeared before the council requesting participation in water line extension to serve his residence at 1128 Cooper Street due to poor water pressure to his mobile home. Earl Smith, City Engineer, presented maps and a memorandum, attached hereto as exhibit A, of the happenings regarding Mr. Leonard's water service. After discussion, the Committee instructed City Staff to check into this matter and report back to the City Council. There being no further business, the meeting adjourned. ERIC S. CLIFFORD, CHAIRMAN ATTEST: MATTIE CUNNINGHAM, CITY CLERK MEMORANDUM TO: Leonard Owens Utility Service File FROM: Mike Tibbets, Staff Engineer DATE: February 11, 1988 SUBJECT: Mr. Leonard Owens On September 24, 1987, Mr. Leonard Owens contacted the City of Paris Engineering Department concerning obtaining water and sewer service for his lot at 1128 Cooper Street. (See Request for Service #170) He was informed by secretary Alice Pinalto that a cost estimate would be required if there was no water or sewer service available. Mr. Owens came back to the office on the Friday just before October 2, 1987. Alice and Steve Hodges (who makes the estimates) were both out of the office and I was very busy. I waited on him as soon as I could. He told me the situation and I began to try to see if I could find what the estimate was. I couldn't locate it so I told him I would call him back on Monday. On October 2, 1987, Steve worked up an estimate of $1,500 for 100 feet of 6" water main extension and $1,700 for 100 feet of 6" sewer extension. We found out that there was an existing sewer main in the street in front of his lot and that it would not require a sewer main exten- sion. I told him that we would dig it up to see if it was low enough to serve his lot. We located the sewer and determined that it was indeed low enough to serve his lot (3.87 feet of difference between sewer flow line and his sewer connection). On November 11, 1987, Mr. Owens paid $210 for a standard sewer tap in the dirt (receipt #4250). On that same day, the Engineering Department sent a work order to Public Works for construction of same. Allen Hicks completed the work on November 19, 1987. Sometime prior to November 11, 1987, (and I honestly can't remember when) we informed Mr. Owens that there was no water main in front of his property. We said that a main would have to be extended in the city right -of -way according to city standards (6" pipe mini- mum). This would cost a minimum of $1,500. This figure didn't seem to bother him much at the time. (He didn't complain.) I told him that an alternative to this high cost might be to get permission from the owner of the adjacent lot to the east (1106 Cooper) to run a line across that property to 1128 Cooper and that he wouldn't have to use as big and as expensive a line in that manner. Apparently he liked that idea because on November 11, 1987, (the day he paid for the sewer tap) he told the secretary that he was going to buy that lot. She even made a note of it. That made me glad because tensions had started by then. I then told him that if he owned that lot (1106 Cooper) all he would have to do to begin water service was to pay a $35 deposit at the water office which he promptly did. He told me that his wife had told him to buy the lot to start with, and that he should have "listened to her." I thought the problems were finally over until the following Friday (November 20, 1987). He came in to the office upset and said that the City had not set the meter or run a line from the meter across 1106 Cooper and up to his house at 1128 Cooper. I asked him if he had bought the lot at 1106 Cooper. He then informed me that he wasn't going to buy it and that he had never intended to buy it. I then told him that he couldn't run a line across property that did not belong to him without the owner's permission. I warned Mr. Owens that the owner of 1106 Cooper might decide that he didn't want Mr. Owens' line crossing 1106 and cut it off. He said he would take that chance himself. Mr. Owens then walked out mad. I immediately went to 1106 Cooper and located the existing tap, then called the water office to make sure a meter was installed. While I was out, Mr. Owens came back in with a letter from County Judge Bob Burns granting permission to lay water and sewer lines along the property line of 1106 Cooper. (The county now owned 1106 Cooper due to nonpayment of taxes). My interpretation of this letter was that the judge was allowing Mr. Owens to use the tap at 1106 Cooper for use at 1128 Cooper. However, when I contacted the judge to be sure of my interpreta- tion, he said that I was wrong. He wanted the water tap at 1106 Cooper to remain for its future owner. He only granted permission for lines to be laid along the edge of the property. Therefore, on November 20, 1987, I wrote Mr. Owens a letter informing him of what the judge had said. Since Mr. Owens did not want to run a City standard sized main due to the cost, I informed him that a water tap in the dirt was necessary and that it would cost him $135. Additionally, I told him that the City does not do private plumbing work on private property and that it would be necessary for him to run a line from the meter to his lot at 1128 Cooper. I at- tached a copy of "Water /Sewer Verification" to help him understand our water and sewer installation procedures. This attachment also warned of the low service possibly provided by using nonstandard sized service mains. I apologized for the delays and misunderstandings and asked him to call me if there were any questions. - 2 - oil December 17, 1987, Mr. Owens came in and paid $135 for the standard water tap in the dirt (Receipt #4437) as I had instructed. On December 18, 1987, the Engineering Department sent a work order to Public Works to construct the tap and to switch the meter in the existing meter box to the new meter box. On the same day, I contacted Pat Evans, Water Department Head, and asked her to not charge Mr. Owens for having an account at 1106 Cooper, and to switch the billing address to 1128 Cooper, which she did. Allen Hicks of Public Works completed the tap on December 21, 1987. Odis Bridgers contacted me about the tap saying that it was on a 3/4" line and that the flow rate would not be good. I told him that I was afraid of that but Mr. Owens didn't want to pay to do it cor- rectly and that he had already been warned. I thought that we had finally resolved our problems. However, in January, 1988, I got a call from Mr. Elbert Desmond (784 -4041) who was working for Mr. Owens. He said Mr. Owens wanted to know why the meter wasn't installed at 1128 Cooper instead of at 1106 Cooper. I told him that Mr. Owens hadn't paid to extend the main, so it wasn't extended to 1128 Cooper. After contacting Pat Evans again, I told Mr. Desmond that Mr. Owens could move the meter to his own property and run a line from the new tap to his meter all at his own cost. Next, on February 9, 1988, I got a call from Beverly at Public Works saying that Mr. Owens was complaining that his water meter was not at 1128 Cooper and that there was not adequate water pressure. I told her Mr. Owens had been warned verbally and by letter of the possibility of low service problems and that he would be allowed to move his meter in front of his property if he wished. =M o � LfN:: - 'M'N H to 0 .M •N NN . Ow c a J o � o A Hi 8 A W� MN 'H101 . `MN r\ � t a AN m� � �•� � -� H151 I- s Oi = pa co vt A 0 IA p :M N 'Hl 9f Hl LI WN N181 ° A 4L v M N ir I g I � m _ - -� a. Y O 01 S CO) D D .0 F _- r 3 �_ // O O OD S S in r r i � NW 0 ® r' 18 TH. 1 N.W. .A �o 17 TH, N.Vy. rn I 16 TH. W.W. co ? '� 15 TH 4 1 N N.W. y . N.W. + Li b i _N.W y 3 MX 10TH: N.W. l N:W. Ji D • .8 TH • r N.W. 4 N. W. 0 N. w. co N. W. El � O .n r � MINUTES OF THE SPECIAL MEETING OF THE WATER & SEWER RATE STUDY ADVISORY COMMITTEE January 7, 1991 The Water & Sewer Rate Study Advisory Committee met, Monday, January 7, 1991, 5:00 P. M., City Council Chambers, City Hall, Paris, Texas. Chairman, Billy Joe Burnett called the meeting to order with the following members present: Councilman E. W. (Bill) Booth, Councilman George Fisher, Jr., Director of Finance, W. E. Anderson, City Engineer, Earl Smith, Director of Utilities, Herb Campbell, Jim Farris, City Manager, Michael E. Malone, City Attorney, T. K. Haynes, and City Clerk, Mattie Cunningham. Chairman Burnett announced the purpose of the meeting was to receive briefing from Keith Reed, a partner in Reed -Stowe & Company that has been engaged to conduct a Water and Wastewater Rate Study for the City of Paris. Mr. Reed came forward and gave each member a questionnaire to fill out and return to them. Mr. Reed told the Committee the questionnaire would give them input on some of the thing that will take place in the rate calculation study. Mr. Reed told the Committee that the first thing they plan to do is an exact cost of service study based totally on actual cost where there is no substitution or cross substitution between classes of customers, that the residential, and commercial customers pay all their share, and the contract customers pay all their share according to their contracts with the City of Paris. Mr. Reed said there were several other thing they needed to get the committee's input on because they have agreed in their proposal to calculate the rate for the residential customers within the City of Paris, and the commercial customers that are not under a contract, that they will provide the City with three rate fall alternatives, and the Committee's input on the questionnaires will give Reed and Stowe the insight as to what the desires of the Committee are as far as the three rate fall alternatives. Mr. Reed announced the next thing they would like to do is set the time for the next committee meeting. After discussion, it was the consensus of the Committee to call the meeting for March 4, 1991 at 5:00 P. M. Mr. Reed advised that at the March meeting they would have a draft report for the Committee to look at and review, and have the Advisory Committee give them their thinking on the rates, and it would give them adequate time to incorporate the Committee's suggestions into the rate calculations. Mr. Reed said the final report would be complete by the first of April for the final presentation and adoption by the City of Paris. City Attorney Haynes reported that there was a change being made to the Tenaska contract regarding the audit period, but felt we could go forward on the rate study. Page 2 There being no further business, the meeting adjourned. BILLY JOE BURNETT, CHAIRMAN ATTEST: MATTIE CUNNINGHAM, CITY CLERK MINUTES OF THE SPECIAL MEETING OF THE WATER & SEWER RATE STUDY ADVISORY COMMITTEE March 12, 1991 The Water & Sewer Rate Study Advisory Committee met, Tuesday, March 12, 1991, 5:00 P.M., City Council Chambers, City Hall, Paris, Texas. Chairman Billy Joe Burnett called the meeting to order with the following members present: Councilman E. W. (Bill) Booth, Councilman George Fisher, Jr., Director of Utilities, Herb Campbell, City Engineer, Earl Smith, City Attorney, T. K. Haynes, and City Manager, Michael E. Malone. Also present was City Clerk, Mattie Cunningham. Chairman Burnett announced the purpose of the meeting was to receive briefing from Keith Reed, a partner in Reed -Stowe & Company that has been engaged to conduct a Water and Wastewater Rate Study for the City of Paris. Mr. Reed said this would be an informal meeting that he would not talk dollars and cents, but wanted to tell the Committee of some of thing that has developed since 1988. Mr. Reed told the Committee that they see new and continuing problems, one is the amount of infiltration /inflow that is getting back into the sewer lines that has to be treated, this amounts to approximately 40% volume from outside. The discharge is slightly less than before, and with the work that City Engineer, Earl Smith, has in process, should reduce the volume substantially. Councilman Burnett questioned Mr. Reed if we were getting most of the infiltration /Inflow from the older part of town, rain water, and on the loop. Mr. Reed told the Committee there was some infiltration /inflow from the older part of the City, rain water, and the loop, but this would only be a fraction of the problem. City Engineer, Earl Smith, said he feel that something that is going on is when we remodeled the lift station, we were not metering the lift station's bypasses, and now we are which would account for some of the increased volume. Mr. Reed pointed out the fact that some of the problems we are experiencing is in the outfall lines between the flow basin and the treatment plant, stating there is a 30% infiltration /inflow there. Mr. Reed said he was aware of the S. E. Lift station line replacement which will eliminate infiltration /inflow, and this is something that we have to work on. Mr. Reed discussed water metering problem telling the Committee that there is a 20% loss of water in the system, and is a problem that need attention. Mr. Reed pointed out that we have two customers that is on one 33 inch line, and when it leaks you know about it, and stated there is no leakage there. Mr. Reed pointed out there is 2.8 million gallons of water lost which would indicate a major metering problem at Page 2 W &S Rate Study Committee 3/12/91 the Water treatment Plant which would cause pricing problem. Mr. Reed questioned the calibration of the meters, stating it is the large meters that is possibly causing the major problems. Herb Campbell advised that the meters at the Water Treatment Plant is calibrated twice a year, that Campbell Soup calibrates their meter one time a year. Herb discussed the process of his departments reading meters and the meters that Public Works reads. Mr. Reed said one of the problem could be in the billing end of the process, and they plan to research the program, and see if there is a problem in the software, if it is permissible with the Committee. The Committee was in agreement to allow Mr. Reed to research the City's water billing software. Mr. Reed discussed commercial customers, and contracts for water service with the Committee, and told the Committee there is definitely going to be a rate increase. There being no further business, the meeting adjourned. BILLY JOE BURNETT, CHAIRMAN ATTEST: MATTIE CUNNINGHAM, CITY CLERK MINUTES OF THE SPECIAL MEETING OF THE WATER & SEWER RATE STUDY ADVISORY COMMITTEE August 22, 1991 The Water & Sewer Rate Study Advisory Committee met, Thursday, August 22, 1991, 3:30 P. M., City Council Chambers, City Hall, Paris, Texas. Chairman George Fisher called the meeting to order with the following members present: Councilman Billy Joe Burnett, Director of Utilities, Herb Campbell, City Engineer, Earl Smith, City Attorney, T. K. Haynes, City Manager, Michael E. Malone, and Jim Farris. Also present was City Clerk, Mattie Cunningham. Chairman Fisher announced the purpose of the special meeting was to received briefing From Keith Reed, a partner of Reed -Stowe & Company that has been engaged to conduct a Water and Wastewater Rate Study for the City of Paris. City Manager Malone introduced Mr. Keith Reed of Reed -Stowe & Company who conducted the water and wastewater rate study for the City of Paris. City Manager Malone said this study is performed every three years. Mr. Keith Reed, Partner in the Firm of Reed -Stowe & Company, 12770, Dallas, Texas, along with Peter Otterson, Senior Consultant with his firm, and Project Manager for the rate study was present. Mr. Reed presenting the Committee, and those in the audience with a handout that corresponded with the overhead transparencies that were presented. Mr. Reed told the Committee that in the industrial contracts with the City such as Tenaska and Campbell Soup there is a requirements in those contracts that an actual cost of service and rate a calculation be done every three years to redetermine their rates. The City also has their rates redetermined every three year, and this is the calculation for this particular year. Mr. Reed said his firm had performed the same service for the year 1987 -88, and the results of that study will be compared to that study. Mr. Reed stated that in calculating rates for all the customers within the city regardless whether they are residential, commercial, or contract customers, you go through the entire process to determine a total amount of money that will be needed to run the water and wastewater system, then that amount of money is allocated to the various and sundry customer classes. Mr. Reed told the Committee that at the start of their program this year, the City had received and adopted an engineering report from Bucher, Willis & Ratliff & Company that envision major changes an improvements to the water system. It involves installation of approximately fifteen million dollars in projects over a period of three or four years. Mr. Reed said this brought about their analysis of what kind of impact that would have on the debt service that the city has to pay on bonds that they sale to accomplish those projects. Mr. Reed said they looked upon that economic impact at two ways. The City has currently outstanding quite amount of debts in the water and Page 2 W &S Rate Study Committee Minutes 8/22/91 wastewater systems, and they looked at the possibility of doing an advance refunding of the existing debts at the same time as the sale of new bonds, and looked at the total cost at the same time. Mr. Reed said that what happens on the advance refunding is we will be able to save money, because those debts outstanding is at a higher interest rate than it is today, so they looked at the analysis two ways, one being doing an advance refunding and issued a new debt, or issued a new debt and left the old debt as is. Mr. Reed said the first sheet of the handout shows the impact of both of those items. The fourth column from the left is the total system debt with no advance refund. Mr. Reed pointed out that the figures for 1992 was for a part of a year. The last column on the right is the annual savings or loss between those two numbers, makes the end result a positive $278,000.00 benefit to the City to do the advance refunding. Mr. Reed stated this was the most favorable way was to go with the advance refunding. Mr. Reed said this is one of the components that makes up the City's total cost that has to be recovered from all customers for the debt service, and the customers pay according to the demand upon the system. Page two of the handout list out some of the major projects that are going to be accomplished with the bond sale that is going to take place in late 1991, and another one in early 1992. Mr. Reed said that the Engineering Firm along with the City Engineering Staff are recommending that the line between Pat Mayse Lake and the Water Treatment Plant be paralleled with another line at a cost of $5,050,000.00 to take care of the construction and engineering on this project. Mr. Reed told the Committee the actual size of the line has not been determined at this, it could be a 30 -inch, or as much as 42 -inch line. Mr. Reed said there was only one line coming from Pat Mayse Lake to the treatment plant, and it carries approximately 80 -85% of the water that the City uses. Mr. Reed stated that not only do we need additional supply for that particular facility, this would provide additional backup if something happened to that line, because if it blew out, the entire city and all industry would have to shut down, in order to provide water for the residential customers of the city. Herb Campbell, Director of Utilities, told the Committee that during the summer time approximately 6 -8 million gallons of water was pumped from Lake Crook, and eight million gallons would be the maximum that could be pumped from Lake Crook for a very short period of time, then we could supplement that by adding portable pumps. Mr. Campbell also said that the capacity from Pat Mayse Lake was 14 million gallons a day, and on peak days we are at capacity. The Water Treatment Plant modification of the next major project due to more stringent water treatment standards imposed by the EPA which will become effective June 1993. Total cost of this project is $3,976,000.00 for construction and engineering. Mr. Reed told the Committee if these improvements are not made, the City will not be able to meet the standards with the present plant, what it does is decreases the amount of water you treat because you have to be more critical in the treatment process, so the City will loose some volume if the expansion is not done. Page 3 W &S Rate Study Committee Minutes 8/22/91 The next large item is the Booster Pump Station Rehabilitation and Addition of a 4.0 million gallon ground storage tank at an estimated cost of $5,000,000.00. The total for all of the proposed project is $14,526,000.00. Page three of the handout, Mr. Reed pointed out was a budget comparison for actual operating expenses for the water and wastewater operation for the current year and the proposed 1991 -92 budget, which will be presented to the Council for approval. The total cost of service shows an increase of 15.24 %, with the debt service showing an increase of 40.20 %. City Attorney Haynes pointed out that the Water Production, Sewer Treatment, and Lift Stations Departments are intensive user of electrical power. Mr. Reed discussed lost and unaccountable water that is lost due to fire fighting, water leaks, water main breaks, inaccurate meter reading, meter stoppages, so what they had done was to see what type system loss there was. On the handout showing Water Production, Consumption and Losses in Gallons, Mr. Reed pointed out that just because the City produces water through the Water Production Plant it does not mean the City gets to sell all the water, and discussed the types of water losses the City has. Mr. Reed told the Committee the total system loss is 11.51 %. Mr. Reed said the customers classes are broken down by residential, commercial which is broken down further by small commercial and industrial customers that have contracts, then we have Campbell Soup, Tenaska, Merico, Lamar County Water Supply District which are contract customers. Mr. Reed pointed out on the handout these customers classes are broken down by total sales per month giving an annual total consumption and the percentage of total water sold, giving an average sale through out the year is 11.57 million gallons a day. Mr. Reed told the Committee that the percentage of consumption by each class, they should pay the same percentage ratio of all the treatment cost at the plant, and stated that there are some of the cost that are allocated by volume. Mr. Reed said now that they have identified the budget, who is using how much water, and based on the budget presented, operating & maintenance portion, and debt service of $2,335,640.00, and the test year assumption characteristics patterns for a twelve month period, they have developed the proposed rates. Mr. Reed pointed out from the handout the base amount for residential customers will be $5.64, and included in that is 200 CF of water, and if they use more than 200 CF of water they will pay $1.41 additional cost for each 100 CF. Mr. Reed said for a 1" - 2" water meter the base cost of $15.25 for the first 1,000 CF, they will pay an additional cost of $1.31 for each 100 CF, if they have a water meter greater than 2 ", and they are not qualified to sign up for the industrial rates, you have to have a 4" meter to qualify for the industrial rate, the base cost will be $39.45 for the first 3,000 CF, an additional cost of $1.31 per 100 CF above the 3,000 CF. Page 4 W &S Rate Study Committee Minutes 8/22/91 The next schedule is for those customers that qualify for an industrial water rates which requires a 4" meter. The 4" meter base cost of $1,000.00 entitles the customers to 100,000 CF, anything over that is an additional cost of $1.05 per 100 CF. A customer with a 6" meter, the base cost of $1,475.00 for the first 150,000 CF, anything over that is $1.05 per 100 CF. A customer with a 8" meter or over, the base cost is $1,950.00 plus 1.05 per 100 CF. Mr. Reed said those companies that takes the option to be on the industrial rate, they have to sign an agreement to stay on the rate for one year. Mr. Reed went over the rates for those who have contracts for water such as Campbell Soup, Tenaska, and Lamar County Water Supply, with general discussion from the audience. Mr. Reed stated that the next schedule of rates, Exhibit WW -9, Consultant Recommended Wastewater Rate Schedule, which is the wastewater rates that are to be charged. For a meter size of 5/7" - 3/4 ", the base cost will be $5.93 for 200 CF, anything over the 200 CF will be $2.03 per 100 CF. A meter 1" - 2", base cost will be $22.26 for the first 1,000 CF, anything over that will be $2.04 per 100 CF. A meter greater than 2 ", the base cost will be $42.94 for the first 2,000 CF, and $2.05 per 100 CF there after. Mr. Reed told the Council that each customer by his usage pattern establishes it own maximum, the City's accounts for the months of November, January, and February, you add up your consumption for these three months, and that is assumed that is the amount of water used each month through the year, or for domestic purpose that gets back into the system, anything above and beyond that amount that flows through your account, you do not have to pay sewer charge. Mr. Reed stated that each customer has its own individual calculated maximum amount of sewer they will have to pay, which is based on the average of November, January, and February. Mr. Reed pointed out that this cap only applies to single family residences. Mr. Reed advised that all of those charges are calculated and based on the assumption that those customers are not dischargers of real high toxic waste of any kind. Mr. Reed said that everyone who runs a system of that type, and discharges a high toxic of real high level of TSS or BOD are in what is called a monitored group. Mr. Reed explained that these rates applies to these customers, and in addition to those rates, there is a charge for each extra pound of BOD, TSS, and NH3. Mr. Reed said that Merico's contract calculation, which they have a settle up provisions in their contract. Their rate is based upon the estimated budget per year to perform certain functions, and based upon the volume flow that goes through and discharged by Merico, they also pay according to their contract an excess strength BOD and TSS. Mr. Reed show a comparison for the rate for residential customers of what they are paying right now compared to what is being recommended for 1991 both water and wastewater, reflected at various levels of consumptions. Also shown is a commercial customers water and sewer rates by consumption comparison. Page 5 W &S Rate Study Committee Minutes 8/22/91 Mr. Reed next showed a comparison for surrounding cities, stating that the City of Paris is not the highest or lowest, by comparison wise, but is in the middle for water and sewer rates. Mr. Reed stated that the last page is a contract rate comparison of the present rates to the proposed 1991 -92 rates showing the percentage of change. After a considerable amount of discussion with Mr. Reed and the audience, a motion was made by Councilman Burnett, seconded by Councilman Fisher to recommend to the City Council to approve the water and sewer rates as presented by Reed -Stowe Company. The motion carried unanimously, There being no further business, the meeting adjourned. GEORGE FISHER, CHAIRMAN ATTEST: MATTIE CUNNINGHAM, CITY CLERK