1995-120-RES WHEREAS, CITY COUNCIL DID HERETOFORE IN RESOLUTION NO 93-064 AWARD
RESOLUTION NO. 95-120
WHEREAS, the City Council of the City of Paris did heretofore, in Resolution
No. 93-064, award the contract for RAW WATER TRANSMISSION MAIN FROM
PAT MAYSE LAKE TO CITY OF PARIS WATER TREATMENT PLANT, EDA
Project No. 08-01-02814, 92 WSRB 02-92, to KENCO, INC.; and,
WHEREAS, the City Engineer, Earl Smith, acting as project engineer of said
project, recommends the amendment of said contract by Change Order No. Five and
Final attached hereto as Exhibit" A ", which provides for a net increase in contract price
of $13,571.00 for revised work scope which will fully rehabilitate the three raw water
pumps, for a total contract price of $3,714,651.00, and such form should be approved, and
the Mayor should be authorized to execute the same; NOW, TIlEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PARIS, that
the RAW WATER TRANSMISSION MAIN FROM PAT MAYSE LAKE TO CITY
OF PARIS WATER TREATMENT PLANT, EDA Project No. 08-01-02814,92 WSRB
02-92, contract is hereby amended by Change Order No. Five and Final, attached hereto
as Exhibit" A", providing for a net increase in contract price of $13,571.00 for revised
work scope which will fully rehabilitate the three raw water pumps, for a total contract
price of $3,714,651.00, which is, in all things, approved; and,
BE IT FURTHER RESOLVED, that the Mayor of the City of Paris, Eric S.
Clifford, be, and he is hereby authorized and directed on behalf of the City of Paris to
execute said Change Order No. Five and Final.
PASSED AND ADOPTED this 13th day of November, 1995.
~
Eric S. Clifford, Mayor
.~
ATTEST:
Mattie Cunningham, City Cl
ity Attorney
CHANGE ORDER
Order No. Five and Final
Date: October 23, 1995
NAME OF PROJECT:
Agreement Date: July 12, 1995
36" Raw Water Transmission Main
Job No. 92 WSRB 02-92
OWNER:
Citv of Paris
CONTRACTOR:
Kenko, Inc.
The following changes are hereby made to the CONTRACT DOCUMENTS:
Work scope revised on three raw water pumps to be rehabilitated based on findings
after dismantling of pumps by Johnston Pump Company.
Justification:
The revised work scope will fully rehabilitate the three raw water pumps.
Change to CONTRACT PRICE:
Original CONTRACT PRICE
S 3.657,005.80
Current CONTRACT PRICE adjusted by previous CHANGE ORDER $ 3.701,080.00
The CONTRACT PRICE due to this CHANGE ORDER will be (increased) (d8&uuedjx
by: $ 13,571. 00
The new CONTRACT PRICE including this CHANGE ORDER will be S 3,714,651.00
Change 'to CONTRACT TIME:
The CONTRACT TIME will be (increased) (deltltuud) by 270
calendar days.
The date for completion of all work will be October 11, 1995 (Date).
Approvals Required: .
To be effective this Order must be approved by the Federal agency if it changes the
scope or objective of the PROJECT. or as may otherwise be required by the SUPPLE-
MENTAL GENERAL CONDITIONS.
Requested by:
KenKo, Inc.
Recommended by:
Hayter Engineering, Inc.
Ordered by:
Accepted by:
Eric S. Clifford, Mayor City af Paris, Paris, Texas
Federal Agency Approval (where applicable)
ATTEST:
, Mattie Cunningham City Clerk
CONTRACT OOCUMENTS FOA CONSTRUCTION OF' JOCument No. 10
FEDEAALL V ASSISTED WA TEA AND seWER PROJECTS Change Order. Page 1 011
EXHIBIT A