1995-047-RES WHEREAS, CITY COUNCIL DID HERETOFORE IN RESOLUTION NO 93-100
.
RESOLUTION NO.
95-047
WHEREAS, the City Council of the City of Paris did heretofore, in Resolution
No. 93-100, award the contract for BOOSTER PUMP STATION PROJECT NO.
92WSRBOl-93 to OSCAR RENDA CONTRACTING, INC.; and,
WHEREAS, the City Engineer, Earl Smith, acting as project engineer of said
project recommends the amendment of said contract by Change Order No. Two and
Final attached hereto as Exhibit" A", which provides for a net increase in contract price
of $1,163.69 for the purpose of installing sensors to pump motors for a total of
$2,090,494.69, and such form should be approved, and adding 64 days to contract time
for rain delays, and the Mayor should be authorized to execute the same; NOW,
THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PARIS, that
the BOOSTER PUMP STATION PROJECT NO. 92WSRBOl-93 contract is hereby
amended by Change Order No. Two and Final attached hereto as Exhibit" A", providing
for a net increase in contract price of $1,163.69 for the purpose of installing sensors to
pump motors for a total of $2,090,494.69, and adding 64 days to contract time for rain
delays, which is in all things approved; and,
BE IT FURTHER RESOLVED, that the Mayor of the City of Paris, Eric S.
Clifford, be, and he is hereby authorized and directed on behalf of the City of Paris to
execute said Change Order No. Two and Final.
PASSED AND ADOPTED this 8th day of May, 1995.
Eric . Clifford, Mayor
ATTEST:
~-tt\.~~'I.\.~~
Mattie Cunningham, City Cl k
CHANGE ORDER
,!W',';liil'I"11I
. \L~.J~,
Order No,
Two (Final)
Date: March 27, 1995
Agreement Date:
December 17, 1993
NAME OF PROJECT:
Booster Pump Station
92 WSRB 01-93
OWNER:
City of Paris, Texas
CONTRACTOR:
Oscar Renda Contracting, Inc.
The following changes are hereby m<lde to the CONTRACT DOCUMENTS:
Adding 64 days to contract time, and $1,163.69 to contract amount.
Justification:
Rain delays justify time extension, and installing sensors to
pump motors justifies increased contract amount.
Change to CONTRACT PRICE:
Original CONTRACT PRICE
$ 2,080,000.00
Current CONTRACT PRICE adjusted by previous CHANGE ORDER $ 2.089.331.00
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [dec:re:fl~ecll
by: $ 1,163.69
The new CONTRACT PRICE including this CHANGE ORDER will be $2,090,494.69
Change to CONTRACT TIME:
The CONTRACT TIME will be [increased] ~Ii:j:: by 64
calendar days.
The date for completion of all work will be March 20, 1995 (Date).
Approvals Required:
To be effective this Order must be approved by the Federal agency if it changes the
scope or objective of the PROJECT. or as may otherwise be required by the SUPPLE-
MENTAL GENERAL CONDITIONS.
Requested by:
Recommended bv'
- .
Hayter Engineering, Inc.
Ordered by:
Ci~y ot Paris, Par1s, Texas
Eric S. Cli:f;:6ord,M"yor
Accepted by:
Oscar Renda Contracting, Inc.
ATTEST: '
, Mat.t:.l'e Lunulngudm, L.l__c.y, L.lcnk
Approved as to Form:
CONTRACTOOCUMENTS FOR CONSTRUCTION OF T.K. Haynes, City Attorney
FEDERALLY ASSISTED WATER AND SEWER PROJECTS
Document No.1 0
Char'lge Order: Paoe 1 at 1
EXHIBIT A