11/25/2019 MinutesPARIS ECONOMIC DEVELOPMENT CORPORATION
MONTHLY MEETING
Board Members Present:
Tim Hernandez, Chairman
Mihir Pankaj, Secretary/Treasurer
Marion Hamill
A.J. Hashmi
Ex -Officio Members Present:
Gene Anderson, Interim City Manager
Legal Counsel:
Stephanie Harris
Call to Order.
Paris City Council Chambers
107 East Kaufinan St.
Paris, Texas 75460
MondayNovember 25 2019
5:30 O'CLOCK P.M.
MINUTES
Staff Present:
Michael Paris, Executive Director
Chris Stout, Economic Development Associate
Paula Brownfield, Administrative Assistant
Guest(s) Present:
Mary Madewell, The Paris News
Richard Thompson, Citizen
City Council Liaison:
Paula Portugal
Mr. Hernandez called the monthly meeting of the Paris Economic Development Corporation to order at
5:31 p.m. on November 25, 2019.
Invocation
Mr. Anderson gave the invocation.
Citizens' Input
Mr. Hernandez invited those present to speak during Citizens' Input. No one came forward and the
Citizen's Input was closed.
Discuss andossiblr a rove Minutes of the October 15 2019 Monthl Meetin the November 7
2019.. S �ecial Meetin �� the November 12 2019 S ecial MeeHn �• and the November 14 2019 Joint
S �ecial Meetin x with C��r,-,,,,Council.
Mr. Hernandez asked if there were any changes to the minutes. Dr. Hashmi made a motion to approve the
minutes as presented. Mr. Hamill seconded the motion. Vote was 4 -ayes to 0 -nays.
Discuss and ossibl a grove October 2019 Financials.
Mr. Pankaj stated that Personnel was $11,635.19 for October and Marketing expenses totaled $887.22.
Going on to New Industry Projects, the total was $55,997.50 which included surveying and the last bit of
PEDC Board Meeting Minutes
November 25, 2019
Page 2 of 4
demolition. Our total expenses for October were $85,703.45 and our cash balance was $4,238,927.59. Dr.
Hashmi made a motion to approve the October 2019 financials. Mr. Hamill seconded the motion. Vote was
4 -ayes to 0 -nays.
Discuss and aossibly a grove revised incentives for J. Skinner.
Mr. Paris requested that the Board table J. Skinner since we have not received all the information from
them. J. Skinner is considering the prospect of expansion, so the PEDC may be enhancing the performance
agreement. Dr. Hashmi made a motion to table discussion of the incentives for J. Skinner. Mr. Hamill
seconded the motion. Vote was 4 -ayes to 0 -nays.
American S iralWeld Pie U date:
• Construction. Construction cannot go forward on the Brownfield until the VCP process is done.
The application for the VCP process should happen tomorrow and it will most likely be January
before we have clearance on that process. We must maintain our liability because the Master
Agreement states that it must be ready for construction before we convey everything to ASWP.
• Phase II Transfer of the Brownfield to ASWP. We should be transferring in the next couple of
weeks. The environmental aspect is lingering. The TCEQ volunteer cleanup process should be
wrapping up sometime in January or February of 2020. At that time construction can begin on the
Brownfield.
• Phase III Wetlands Progress. The Wetlands are completed. We have gone through the thirty -day
notice with the Tulsa Corp of Engineers and they have not responded. We are about four months
ahead of schedule on the Wetlands.
• Rail Development. The agreement has been red -lined and returned to Kiamichi Rail. We are
expecting a response back from them in a couple of weeks. Our part of the rail will go out for bids
once the agreement is signed. The rail will take approximately six to eight months to complete. Mr.
Hernandez asked if this meets the deadlines of the Master Agreement and Mr. Paris said that he will
go back a verify whether it does.
Questions. Dr. Hashmi asked who is responsible if there is a delay in the project. Mr. Paris stated
that our responsibility is to American SpiralWeld per the Master Agreement. At this point we have
met the conditions of the Master Agreement. The Brownfield was to be transferred in October, but
American was notified six months ago that the environmental was going to take longer. At the same
time we found out the Wetlands would be reconditioned and a new application would be submitted.
This sped up the Wetlands finalization. At that point American agreed to transfer everything at
once. This was a delay to the October deadline, but expedited the Wetlands. Mr. Paris stated that
we are in communication with American SpiralWeld throughout the process. Dr. Hashmi asked
why there was a delay in the Brownfield. Mr. Paris answered by saying that all the work to clean up
the Brownfield was more than we expected, but has only delayed us six to eight weeks. Dr. Hashmi
asked what part caused the delay. Mr. Paris explained that the separation between the Wetlands and
the Brownfield did not cause the delay. The environmental cleanup, removal of the test wells and
removal of two unexpected tanks at Superior Switch delayed us about two months. Dr. Hashmi said
that the person responsible for the delay was the one who was responsible for fixing the wells and
giving us a time estimate. Mr. Paris stated that the demolition was not delayed; the environmental
was delayed because of the conditions for removing bad soil and examining ground water under the
test wells. The unexpected items found during the demolition created more work and caused the
PEDC Board Meeting Minutes
November 25, 2019
Page 3 of 4
delay. Mr. Hernandez suggested that the deadlines in the Master Agreement be shown to the Board
in a timeline chart next month. He went on to say that the rail development has been delayed. It
doesn't matter who is responsible for the delays. It matters when we miss a deadline and the fact
that we inform does not subrogate our responsibility. Ms. Harris added that we will need to double-
check for a deadline. She did not recollect there being a deadline on rail. Mr. Stout stated the only
deadline he recalled in the Master Agreement beyond the Phase II was for the Phase III Wetlands
which was to be six months after Phase II. This should take place in April 2020. The rail does not
have a deadline attached to it, just the requirements that we assist them. Mr. Hernandez stated there
was a deadline on rail. Mr. Paris interjected that the rail would need to be done by the time the plant
goes into production. Mr. Paris went on to say, Mr. Hook with American SpiralWeld said that if rail
is delayed it is because rail is a different organization and we are working with rail's timelines. Mr.
Hernandez stated that when there is a verbal agreement agreeing to delays, a written document
showing what was agreed to should be completed.
Asset Mang ement:
• Preparation of Gene Stallings Business Park. There is an issue with the water pump station next
to the property which is mainly used by Kimberly Clark. We are evaluating the capacity of the
pump and may need to put in a larger pump. Mr. Pankaj asked if this would be a PEDC cost. Mr.
Paris said it would. If Walker Partners are prepared to present, we will do that next month. Walker
Partners purpose is to advise the PEDC on what infrastructure is needed at the property. Dr. Hashmi
questioned when did we decide on the engineering firm and how was it was decided. Mr. Paris
answered that he chose Walker Partners. Dr. Hashmi asked if the Board approved them. Mr. Paris
stated he wasn't sure, but didn't think they had. Mr. Hernandez asked about the scope of work and
what the costs of Walker's services were. He went on to say that we need to look at both the scope
and the dollar amount for Walker Partners. Also, we need to look at other companies.
Scope of work for land clearing. EST, Inc. will be contacted to make a presentation on the list of
properties and the scope of work needed for clean-up and development. The priorities on the land
clearing will be listed along with the properties. Mr. Hernandez asked if three bids would be ready
by the next Board Meeting. Mr. Paris stated that we would not have bids by the next meeting; we
would have the properties prioritized. EST, Inc. is in contact with the City and we will prepare to
move forward quickly.
• Prioritizing land preparation for development. At the next meeting we will have a list compiled
of the PEDC properties and their priority on cleanup. The first priority will be cleaning the southern
part of the NW Business Park in preparation for Rocket X. The SW Business Park property will be
second on the list.
Questions. Dr. Hashmi asked on what basis were the priorities decided on. Mr. Paris told the Board
that we are working out a schedule with EST, Inc. Dr. Hashmi asked whether the prioritization is a
part of engineering or a part of marketing. Mr. Paris answered that it was a part of engineering. Dr.
Hashmi stated that marketing would be better, since you want to know which properties are the
most marketable. Mr. Pankaj stated that the order the properties are listed in is also the fastest order
to develop the properties. Dr. Hashmi asked why an engineering company should be deciding what
land ought to be developed first. Mr. Paris responded that the infrastructure around the properties
needs to be included in the assessment, as well as, the ease of traffic flow into the site. Dr. Hashmi
added that only someone with marketing experience would know which is the best property to
market first.
PEDC Board Meeting Minutes
November 25, 2019
Page 4 of 4
Convene into Executive Session:
1) Pursuant to Section 551.087 of the Texas Government Code to (1) discuss or
deliberate regarding commercial or financial information that the governmental body
has received from a business prospect that the governmental body seeks to have
locate, stay, or expand in or near the territory of the governmental body and with
which the governmental body is conducting economic development negotiations; or
(2) to deliberate the offer of a financial or other incentive to a business prospect
described by Subdivision (1), to wit:
• Project Rocket X
• Project Rainwater Falls
2) Pursuant to Section 551.072 of the Texas Government Code to discuss and deliberate
the purchase, exchange, lease, or value of real property.
• Real Estate
Chairman Hernandez convened the Board into Executive Session at 6:05 p.m.
Reconvene into O yen Session ecutive Session.
Chairman Hernandez reconvened the Board into open session at 6:25 p.m. Dr. Hashmi made a motion to
accept as proposed on the Project Rocket X and take the proposed back to the company for their response.
Mr. Pankaj seconded the motion. Vote was 4 -ayes to 0 -nays.
Discuss Future Agenda Items.
No future agenda items were discussed.
A4iourn
Mr. Pankaj made a motion to adjourn. Dr. Hashmi seconded the motion. Vote was 4 -ayes to 0 -nays. The
meeting adjourned at 6:27 p.m.
Respectfully submitted,
Paula Brownfield
Administrative Assistant
Paris Economic Development Corporation