09 - Demolition and Code Enforcement ReportsItem No. 9
Code Enforcement Report; March 2020
Cases Worked: 162
Cases Completed: 128
Initial Inspections: 162
Re -inspections: 221
Lots Abated: 27
Other Work by Abatement Crew:
Mowed 6 Right -of -Ways —1 days
Tree Removal — 2 days
Removed Tires — 9 day
Removed Illegal Dumps — 7 days
Repaired/Serviced Equipment — 2 days
Worked at Wise Field Shop — 2 day
Building,_and Stwawndardsw gport: March,,w2020
There were 9 structures presented to the commission:
2004 Cleveland 926 W Cherry
322 NE 17th 743 NW 4th
717 NW 4th 1758 NE 10th
142 Plum 387 NW 3rd
359 NW 12th
4 Structures were demolished:
716 E Washington
115 NW 131h
1214 W Kaufman
714 NW 4th