1991-083-RES WHEREAS, the City Council of the City of Paris did heretofore, in Resolution No. 91-030, award the
RESOLUTION NO. 91-083
WHEREAS, the City Council of the City of Paris did
heretofore, in Resolution No. 91-030, award the contract for
the "Pro Rata 12" Water Line Extension Hwy 271 North Project"
to Bill Hazelwood, Inc.; and,
WHEREAS, the City Engineer, Earl Smith, acting as
project engineer of said project recommends the amendment of
said contract by Change Order No. One and Final attached
hereto as Exhibit "A", which provides for a net increase in
contract price of $2,169.70 for a total of $76,682.95 for
adjustment of As-Bid quantities to reflect As-Built
quantities, and such form should be approved, and the Mayor
should be authorized to execute the same; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PARIS, that the "Pro Rata 12" Water Line Extension Hwy 271
North Project", contract is hereby amended by Change Order
No. One and Final attached hereto as Exhibit "A", providing
for a net increase in contract price of $2,169.70 for a total
of $76,682.95 for adjustment of As-Bid quantities to reflect
As-Built quantities, which is in all things approved; and,
BE IT FURTHER RESOLVED, that the Mayor of the City of
Paris, George Fisher, be, and he is hereby authorized and
directed on behalf of the City of Paris to execute said
Change Order No. One and Final.
Passed and adopted this 12th day of August, 1991.
~~~r
ATTEST:
Mattie
'<
APPROVED
CHANGE ORDER
(Instructions on reverse side)
No. One and Final
PROJEer: Pro Rata 12" Watermain
OWNER: Extension Highway 271 N
(Name. City of Paris
Address) P.O. Box 9037
Paris, TX 75461-9037
CONTRAerOR:
Bill Hazelwood, Inc.
P.O. Box 966
Sherman, TX 75091-0966
CONTRAer FOR:
DATE OF ISSUANCE: A t 12 1991
. ugus ,
OWNER's Project No.
83.65
ENGINEER:
Construction of approximately 3160 LF
of 12" Watermain with appurtenances
ENGINEER's Project No. 83.65
You are directed to make the following changes in the Contract Documents.
Description: See attached schedule of quantities
Purpose of Change Order: Adjustment of As-Bid quantities to reflect As-Built quantities
Attachments: (List documents 'supporting change) At tachmen t A
CHANGE IN CONTRAer PRICE:'
CHANGE IN CONTRAct: TIME:
Original Contract Priq:
Original Contract rune
$
$74,513.25
90 days
April 1, 1991
da)'Sordate
Previous Change Orders No
to No.
Net change from previous Change Orders
$
S74.~11.2~
da"
Contract Price prior to this Change Order
Contract Time Prior to this Change Order
$
$74,513.25
90
days <<date
Net Increase (.mcr-'Il of this Change Order
$2,169.70
Net Increase {dt1rt"l\"'J of this Change Order
20
da"
$
Contract Price with all approved Change Orders
Contract Time with all approved Change Orders
$
$76,682.95
110 days
July 20, 1991
dayJor4atc.
RECOMMENDED:
APPROVED:
CITY OF PARIS, PARIS, TX
AJ>PROVED,- ----
"-
Fisher, Mayor
by
"""""""
Bill Hazelwood
by
Earl
ATTEST:
--
E. Smith, P.E.
by
George
OWNER
Mattie Cunningham, City Clerk
EXHIBIT A
ATTACHMENT A CHANGE ORDER NO. ONE & FINAL
PROJECT:
PRO RATA 12" WATERMAIN REPLACEMENT HWY 271 NORTH
OWNER:
CITY OF PARIS
P.O. BOX 9037
PARIS, TEXAS 75461-9037
CONTRACTOR:
BILL HAZELWOOD, INCORPORATED
OWNER'S PROJECT NO.: 83.65
ITEM OUANITITY UNIT PRICE TOTAL
1. 12" AWWA C-900 DRl8
PVC Watermain,
Furnished & Installed
Tested & Cleaned-up 120 LF $ 15.66 $1,879.20
4. 12" Gate Valve With
Box, Complete in Place lEA $ 735.00 $ 735.00
5. Water Service Connection
To Watermain, Complete
In Place lEA $ 106.00 $ 106.00
8. Gravel Drive Repair 32 LF $ 3.35 $ 107.20
Extra Labor and
Equipment Required To
Locate and Expose
Existing Pipe $ 650.00
TOTAL INCREASE $3,477.40
9. Hot Mix Asphalt Concrete
Drive Repair 91 LF $ 8.70 $ 791. 70
10. Concrete Drive Repair 43 LF $ 12.00 $ 516.00
,
TOTAL DECREASE $1,307.70
TOTAL NET INCREASE TO CONTRACT PRICE $2,169.70
ADJUSTED CONTRACT PRICE $76,682.95