09 - Code Enforcement & Demolition ReportsItem No. 9
Code Enforcement Re ort: Ma 020.
Cases Worked: 547
Cases Completed: 172
Initial Inspections: 523
Re -inspections: 265
Total Inspections: 788
Lots Abated: 78
Other Work by Abatement Crew:
Worked Downtown (Banners & tree removal) — 1 day
Tree & Brush Removal — 3 days
Removed Tires — 6 day
Removed Illegal Dumps — 8 days
Repaired/Serviced Equipment — 3 days
Worked on Wise Field Shop —1 day
Building and Standards Report: May, 2020
There was no Building and Standards meeting in May due to Covid-19.
No structures were demolished in the month of May.