20 - Data Center Hardware RefreshItem No. 20
TO: City Council
Grayson Path, City Manager
FROM: Kent Klinkerman, IT Director
SUBJECT: Data Center Hardware Refresh
DATE: September 14, 2020
BACKGROUND: The City of Paris has a primary data center (PDC) and a secondary data center
(SDC). These two data centers are in separate locations for survivability and recovery. Virtual
servers and data are continually updated (mirrored) between these two sites. This is referred to as
High Availability. Users can be seamlessly shifted to the SDC if the PDC has a performance issue
or when routine maintenance is performed on either data center. Additionally, our backup software
solution conducts a backup of data each day at the SDC on a separate appliance for Disaster
Recovery.
The Information Technology critical infrastructure components have a life expectancy. Hardware
and software needs of City departments are constantly evolving. These components need to be
replaced on a regularly scheduled basis to insure reliability, performance, security and planned
expenses.
STATUS OF ISSUE: Two issues: 1). The age of the PDC hardware is 5 years. The age of the
SDC hardware is 11 years. The Backup hardware storage appliance is 10 years old. 2).
Unfortunately, the Backup software solution currently utilized is being phased out due to a merger
of two software companies.
This project would replace the PDC and SDC hardware (labor and equipment). A new backup
appliance would be located at each data center for further redundancy and recovery. The current
PDC hardware would be re -purposed to the Disaster Recovery platform. This project addresses
the issues outlined.
BUDGET: Total cost is $130,000. This is a planned expense split between the 2019-20 and 2020-
21 budget years. There is $66,000 budgeted in each fiscal year in 01-1009-89-01. Sterling
Computer Services is being utilized under a professional services contract using Dell Technologies
components in consultation with Dell Storage engineers.
The equipment is being purchased based on Texas Department of Information Research pricing.
The City currently has an account with Dell Computers for our IT infrastructure, therefore they
are our existing vendor, consultant and professional service; it is critical to maintain consistency
for the entire system with a provider based on the current network, computers, software, hardware,
etc. Sterling Computer Services is a contracted professional entity that Dell uses for most of their
installations, therefore is most qualified to perform this project.
RECOMMENDATION: Approve attached Professional Services Agreement
STERLING
PR,OFESSIONA,.L
SERVICES
City of Paris, Texas
Remote Hyper -V and Storage
Migration Services
08/25/2020
Case 14290
STERLING
1. INTRODUCTION................................................................................................................. 3
2. ENGAGEMENT DETAILS...................................................................................................
3
3. SCOPE OF SERVICE.........................................................................................................
3
4. STERLING'S PRICING METHODOLOGY...........................................................................6
5. PROJECT AND PRICING ASSUMPTIONS.........................................................................
7
6. OUT OF SCOPE.................................................................................................................
8
7. DELIVERY OF RESOURCE(S) -CUSTOMER SCHEDULING .............................................
8
8. PROJECT COMPLETION...................................................................................................
8
9. CUSTOMER RESPONSIBILITIES......................................................................................
8
10.CHANGE MANAGEMENT PROCESS................................................................................9
11 ACCEPTANCE OF PROPOSAL.......................................................................................10
APPENDIX A - SUPPORTED SITES.....................................................................................11
APPENDIX B - CHANGE ORDER DOCUMENT ....................................................................12
APPENDIX C - CUSTOMER PROPOSED ENVIRONMENT ..................................................13
DOCUMENT HISTORY.........................................................................................................14
877.242.4074
info@sterlingcompiAers.com
www.sterlingcomptiers.com
STERLING
1 IIN I r10 I
This Statement of Work (SOW) describes the managed deployment services to be provided by
Sterling, ("Provider") for Paris, Texas, ("Customer"). The term of this SOW shall begin on the
date of the last signature ("Effective Date") as setforth in the Signature Section of this SOW. This
SOW shall expire if not executed within ninety (90) days of the date of creation.
E.iC VIIIIlllllll i..l.. II I..I..AIIIL.S
These Services will be limited to 200 contiguous business
Period of Performance
Hours conducted over a period of time not to exceed 9
business Weeks.
8:00 AM and 5:00 PM local Sterling Customer time, Monday
through Friday, excluding normally observed holidays based
Service Normal
on a forty (40) hour week.
Hours Business
4(")""'I""'llllllllllllm During Project Kickoff, Sterling and Customerwill
Hours
discuss cutover schedules that may take place after hours to
limit production impact at no additional charge for afterhours
work.
Paris, Texas
Place of Performance
Remote Services
Paris TX 75460
. c lulll6,llll111!ll. IIIIIIIIII' Illllllllll.11lllw�lll l
Sterling will provide supplemental expertise to serve as an extension of the Customer's internal
staff, as specifically described herein.
Remote Hyper -V and Storage M igration Services
2.1 lntrc I:iii i°
The following proposal was created after the discussions with the customer on the request to
provide new hardware and services to refresh their current Production and DR data center
environments.
The proposal includes the remote deployment and configuration of the following equipment:
• Six (6) Dell PowerEdge R640 Servers
• Two (2) Dell ME4024 DAS Storage Arrays
• Two (2) Dell DD3300 with Avamar Software
After deployment of the new equipment, Sterling will assist with the migration of the existing
Hyper -V infrastructure to include the new clusters. Next, Sterling will setup and configure the
Hyper -V replication between the Production and DR sites.
877.242.4074
Project Kick Off
Conference call with Customer to obtain site-specific information, set expectations, etc.
Customer will provide configuration information for any existing infrastructure as needed
to prepare for services, prior to engineer onsite arrival
Review scope of work, discuss project objectives and expectations
Customer to inventory all equipment and confirm receipt at least one week prior to
engineer remote start of services
,,,, info@sterlingcomputers.com
) www.Aerlingcomputers.com
STERLING
2.1.2 Configure Dell PowerEdge R640 Servers (Prod)
• Create Server and Switch connection diagram
■ Work with On -Site resource to rack and stack servers
■ Work with On -Site resource to connect servers to network switches
�onfigure
Work with On -Site resource to properly configure uplink ports
• DRAC interfaces on servers
• Configure R640 for Hypervisor role on servers
• Install Windows operating system (OS) and enable Hyper -V role
• Patch Windows operating system current on all servers
• Create Windows Hyper -V Cluster
• Join cluster to SCVMM
2.1.3 Configure Dell ME4024 DAS Devices (Prod)
• Create DAS and Server connection diagram
■ Work with On -Site resource to rack and stack DAS devices
■ Work with On -Site resource to connect DAS devices to servers
■ Work with On -Site resource to properly configure uplink ports
• Configure DAS devices to participate in Windows Cluster
2.1.4 Configure Dell DD3300 Backup Devices (Prod)
• Create DataDomain and Switch connection diagram
■ Work with On -Site resource to rack and stack DataDomain devices
■ Work with On -Site resource to connect DataDomain devices to switches
■ Work with On -Site resource to properly configure uplink ports
2.1.5 Configure Dell Avamar Backup Software (Prod)
• Verify version of AVE to be deployed, ensuring compatibility with DDOS version.
■ If necessary, upgrade DDOS to supported version for AVE.
• Download and deploy Avamar virtual appliance file in Hyper -V manager
• Install and configure Avamar software on VM
• Connect DataDomain storage to AVE
• Configure Avamar backup jobs
• Configure backup schedules and policies
• Perform full backup of Production environment
2.1.6 Configure Dell PowerEdge R640 Servers (DR)
• Create Server and Switch connection diagram
■ Work with On -Site resource to rack and stack servers
■ Work with On -Site resource to connect servers to network switches
■ Work with On -Site resource to properly configure uplink ports
• Configure DRAC interfaces on servers
• Configure R640 for Hypervisor role on servers
• Install Windows operating system and enable Hyper -V role
• Patch Windows operating system current on all servers
• Create Windows Hyper -V Cluster
• Join cluster to SCVMM
2.1.7 Configure Dell ME4024 DAS Devices (DR)
611
vwvw.sterlingcomputers.com
STERLING
• Create DAS and Server connection diagram
■ Work with On -Site resource to rack and stack DAS devices
■ Work with On -Site resource to connect DAS devices to servers
■ Work with On -Site resource to properly configure uplink ports
• Configure DAS devices to participate in Windows Cluster
2.1.8 Configure Dell DD3300 Backup Devices (DR)
• Create DataDomain and Switch connection diagram
■ Work with On -Site resource to rack and stack DataDomain devices
■ Work with On -Site resource to connect DataDomain devices to switches
■ Work with On -Site resource to properly configure uplink ports
2.1.9 Configure Dell Avamar Backup Software (DR)
• Verify version of AVE to be deployed, ensuring compatibility with DDOS version.
a If necessary, upgrade DDOS to supported version for AVE.
• Download and deploy Avamar virtual appliance file in Hyper -V manager
• Install and configure Avamar software on VM
• Connect DataDomain storage to AVE
• Configure Avamar backup jobs
• Configure backup schedules and policies
• Perform full backup of DR environment
2.1.10 Configure Hyper -V Replication
• Configure each Hyper -V virtual machine for replication to DR
• Fully replicate all Hyper-VVMs to the DR side
2.1.11 Test Hype r -V Failover(Prod -> DR)
• Shutdown Production Hyper-VVMs and turn on the replica partners in DR
• Validate that all applications and data is working in DR
• Complete Testing
2.1.12 Test Hyper -V Failback (DR -> Prod)
• Shutdown DR Hyper-VVMs and turn on the replica partners in Production
• Validate that all applications and data is working in Production
2.1.13 Project Deliverables
Visio wiring diagram
Working Hyper -V Production site
Working Hyper -V DR site
2.1.14 Project Close Outand Documentation
• Deliver project deliverables referred to in the deliverables section of this SOW.
• Project closeout call.
• Customer signs project Customer Acceptance Form (CAF)
2.2 Sterling will perform the following Project Management activities during the term of
this SOW:
• Single point of contact and accountability for successful delivery of the Services
%, www.sterlingcompikers.com
STERLING
• Maintain focus on time, cost and scope
• Coordinate and facilitate kick-off, status, deliverable review and closeout meetings
• Establish and manage the Services schedule, communications and status reporting
• Provide up to one status call and brief status report per week
• Identify, monitor and manage Services risk, issues and escalations
• Facilitate change management as needed
• Confirm the Services delivered are in accordance with the SOW
• Written notification (including email) to Sterling Customer of completion of delivery of
these Services
• Up to one (1) deliverable review or phase completion call per week
• Monitor the Services budget and invoices
• Manage the Sterling Customer relationship
• Track and status progress against Services objectives
• All Project Management activities will be conducted remotely.
2.3 Customer Project Management
• Assign Customer Primary Point of Contact ("CPOC") to provide requirements and
technical data needed forthe Services.
• Provide Sterling personnel with adequate work space, supplies, facilities and systems
within reasonable proximity to where services are to be performed.
• Coordinate the scheduling of all necessary Customer resources required for the
Services and ensure those resources are available throughoutthe engagement,
including technical contacts.
• Maintain communication with end users to prevent scheduling conflicts and ensure
continuous workflowfor onsite engineer(s).
• Notify Sterling PM immediately with any issue related to the completion of the services
described in this SOW, and participate in the escalation of such issues until resolution is
achieved.
i I wl it � I„"IF I° IIIC III it ii III IIIClllll:..l llh-'lll� 'i..��lll...'u` G
Fixed Fee Charge - Customer agrees to pay Sterling on a Fixed Fee, ("FF") basis for Services
performed under this SOW.
Following the performance of the Service, Customer agrees to pay Sterling an amount not to
exceed the following One -Time Charge. Such amountwill be paid in accordance with the Provider
Pricing Table in this section:
One Time Charge: Please see attached Quote, Q-00343713
Expenses Included in the One-time Charge
This proposal does not include Travel and Expense fees as all services will be completed
remotely. If such variables impact the project and travel or expenses are required, Sterling will
notify the Customer prior to incurring additional expenses, provide an estimate of the additional
cost and/or schedule impact, create a change order and implement the change upon Customer's
acceptance of a Change Order..
877.242.4074
r
0. www.sterlingcompiAers.com
STERLING
■ Customer to provide all licensing files and keys needed for activating Dell and
Microsoft appliances/software
• User Permissions
�nowledge
Vendor will have AD domain administrator and vCenter administrator access
• transfer is not a formal training — but users will be given documentation and
information to allow customer -management of the entire environment.
. OL.,L.L° OFCO
• Any Sterling training, services, tasks or activities other than those specifically described
in this SOW.
• Provider is not responsible for conflicts with e)asting software or network permissions
conflicts, as configured by customer network and active directory.
• Provider will work with vendors for installation of 3rd party software but is not responsible
for issues that arise with third party software.
• Networking configuration and equipment was not included with this proposal, Customer
will verify and configure network routing as needed.
• Advanced virtual networking (Switch Embedded Teaming, network QoS bandwidth
allocation, and bandwidth reservation).
• Creation of Virtual Templates
• De -installation or disposal of e)asting servers
• Re -arranging / moving e)asting devices within the rack will be customer's responsibilities
• Any post -delivery support to the Deliverables produced
• Any mitigation services related to these services
Upon request by End User, Sterling will provide a proposal for such out of scope services pursuant
to the Change Management Process described in Section 9.
III...IIf EIIC: i OfIIC ES()t..IlF:iCE
...0,.I""..L.QIMliiiiiiiall SCI°..IIIIIIII„.III°
Upon completion of a Sterling SOW (Statement of work) Sterling and Customer will agree on firm
and fixed dates for the work to begin, all work scheduled will require a minimum of two (2) week
lead time. Both parties will use best reasonable efforts to inform the other party at least two (2)
weeks before requesting changes to dates for onsite/remote work.
I II:' IIUIIII I IIIIIC:,ullh...IIC °".IIC IIIII
The following is a list of tangible material provided as part of the Service performed by Sterling
for the Customer under this SOW.
• Customer shall either accept or reject Sterling's Deliverables and completion of work
within ten (10) business days from delivery to Customer. A Deliverable will be deemed
acceptable if it conforms in all material respects with Services described within this
SOW.
US I°" II IIk[IIIIIC I III'° II IIIIIIIIIII' I` "',I III” Il 111 llll lkl 111 lll.... III °"'I°"' 111 llllllllll
• Sterling and Customer will share responsibility for success of this implementation. The
full cooperation of Customer management, staff and any necessary internal parties will
be required to achieve the desired results. This includes making sufficient time for
review of written materials, meetings, etc.
www.sterlingcomputers.com
STERLING
• In order to keep the costs of the project to a minimum, Customer staff may be utilized to
perform the basic data gathering tasks. It is assumed that any data gathered by
Customer personnel will be accurate. This data will be analyzed to determine the
e)asting hardware/software architecture.
• End -User will maintain a backup of all data and programs on affected systems prior to
Sterling performing the Services and during the term of the SOW. Sterling will have no
liability for loss or recovery of data, programs or loss of use of system(s) arising out of or
in connection with the Services provided under this SOW.
• Provider will provide documentation for racking and cabling of the equipment. Customer
is responsible for the physical installation and power/data cabling
• Customer staff may be utilized to perform basic data gathering tasks during the planning
and execution phases
• Upon request, Customer will provide timely and accurate data
• Provider recommends the network map be kept on file as a reference to assist provider
Support engineers during trouble resolution
This Topology map should include IP addresses, Gateways, VLAN's, and VPN's on
local area network
• Making appropriate service outage windows available for Sterling Services as needed
• Customer is responsible for ensuring all systems and software impacted by this service
are under current support agreement
• Customer is responsible for troubleshooting firewall rules as needed
• Customer to provide adequate accounts for access to e)asting infrastructure in order to
build new environment templates and conduct migrations
• Customer will advise on what the maintenance windows are, and the deployment
process will be tailored to these windows
• Customer will assist Provider PM with scheduling and coordinating customer resources
• Customer will coordinate and ensuretechnical requirement compliance
• Customer will ensure necessary network requirements
• Ensure any e)asting equipment repositioning is completed priorto start of services
• Ensure any modifications needed to ebsting racks to accept Dell equipment is
completed prior to arrival
• Ensure that the required power distribution units ("PDUs") and UPS(s) are installed and
functional unless purchased with the Supported Product
• Ensure that the required power outlets are installed and functional in the location of the
hardware installation
• The physical and network security of Customer environment
I I':I. ' Ilh 111 l llll
IMA14AGEMEN
Upon Sterling's or Customer determination that a change is necessary to refine a
process, procedure, or add a service that is not included within the original scope of
work, a change order will be created by the Sterling PM, outlining the change and, if
applicable, any costs associated with the change.
Customer will review the proposed Change Request and determine whether the change
is acceptable or requires modifications. Both parties will (a) sign the Change Request,
(b) agree to modifications to the Change Request, or (c) reject the Change Request.
Changes to the scope of work will be implemented only upon agreement and signature
of the Change request by both parties.
19
() www.sterlingcompiders.com
y
STERLING
1. ACMi�7ANCi : viii: I:
IN WITNESS WHEREOF, Customer and Sterling Computers have caused this SOW to be signed
and delivered by their duly authorized representatives as of the date of last signature below (the
"Effective Date").
By signing this document all parties are responsible for the terms and conditions within this
agreement.
City of Paris, TX Sterling Computers
By: By:
Printed Name: Printed Name: Rob Foster
Title: Title: Director of Services
Date: Date:
This data, furnished in connection with this quotation, shall not be disclosed outside the
Government and shall not be duplicated, used, or disclosed in whole or in part for any
purpose other than to evaluate the proposal; provided that, if a contract is awarded to this
Offeror as a result of or in connection with the submission of this data, the Government shall
have the right to duplicate, use, or disclose the data to the extent provided in the contract.
This restriction does not limit the Government's right to use the information contained in the
data if it is obtained from another source without restriction. The data subject to the restriction
is contained in sheets marked with the following legend: 'Use or disclosure of the data on
this sheet is subject to the restriction on the title page of this proposal'.
877.242.4074
info@sterlingcomputers.com
www.sterlingcompiters.com
NIs
IL-
STERLING
A� ... IW�����s l�������u���� 111 �IIIIIIIIIII'.III:: f'fl.I..� '
The Services will be provided for the following supported sites during the term of this SOW.
Additional supported sites may be included as mutually agreed using the Change Management
process as defined in Section 9.
0.
STERLING
(,Yl III ', III'.:.R DOO,, ME111 ....
09,
STERLING
C .. . ..... CUS OWEDth
IR
jjj�e
STERLING
'IOCk )MEN..i.°FflS`! Q�RY
. . ......................................
t,. ...................................
Sterling Customer
. ... ............................. .......... . . . . . . . . . . ...... . . . ....... . ..... .. ..... ......... ....... .. ...........................................................................
City of Paris, TX .......... ........... ........... . .
Date
08/25/2020
. . . ............... -------
Document Author
....... .. ..................
Name: Matt Determan
Title: Technic at Services Rep
Company: Sterling Computers
Phone: 605.242.1275
Email:
Reference #C14290
Document Revision History
a Document Creation Date - 08/25/20
Revised by.X_on <Date> - resulting V2
Revised by.X_on <Date> - resulting V3
Revised by_)L_on <Date> - resulting V4
.........................................
(ADD).................................... --- ...... - .... ..... ...
,