1989-101-RES WHEREAS,CITY COUNCIL IN RES NO 89-006 AWARDED
RESOLUTION NO. 89-101
WHEREAS, the City Council of the City of Paris did
heretofore, in Resolution No. 89-006, award the contract for the
Evergreen and South Church Street 12" Water Main Extension,
88WSRP-01-88 to William Heuberger Construction; and,
WHEREAS, the City Engineer, Earl Smith, acting as project
engineer of said project recommends the amendment of said
contract by Change Order No. One and Final attached hereto as
Exhibit "A", which provides for a net decrease in contract price
of $170.00 for a total of $12,878.00 for adjusting as-built
quantities from bid quantities, and such form should be approved,
and the Mayor should be author ized to execute the same; NOW,
THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PARIS, that the Evergreen and South Church Street 12" Water Main
Extension, 88WSRP-01-88 Project, contract is hereby amended by
Change Order No. One and Final attached hereto as Exhibit "A",
providing for a net decrease in contract price of $170.00 for a
total of $12.878.00 for adjusting as-built quantities from bid
quantities, which is in all things approved; and,
BE IT FURTHER RESOLVED, That the Mayor Pro Tern of the City
of Paris, Curtis Fendley, be, and he is hereby authorized and
directed on behalf of the City of Paris to execute said Change
Order No. One and Final.
Passed and adopted this 14th day of August, 1989.
/1
{~-
Curtis Fendley,
Tern
ATTEST:
~~~,~'-,~
Mattie Cunning am, Ci er
APPROVED AS
FORM:
CHANGE ORDER
.~ (Instructions on reverse side)
N 1 & Final
o.
PROJECT: Evergreen & South Church
12" Water Main Extension
DATE OF ISSUANCE: August 14, 1989
OWNER:
ON~e, City of Paris
Address) Paris, Texas 75460
CONTRACTOR:
William Heuberger Construction
Route I, Box 87H
Paris, Texas 75460
CONTRACT FOR:
Evergreen and South Church
12" Water Main Extension
OWNER's Project No,
88-WSRB-OI-88
ENGINEER: City Engineer
City of Paris
ENGINEER's Project No.
88.08
You are directed to make the following changes in the Contract Documents,
Description: Delete bid item No.7 from project.
Purpose of Change Order:
To adjust as-built quantities
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
Original Contract Price
13,048.00
Original Contract Time
$
45 days
days or date
Pl'evious Change Orders No.
to No,
Net change from previous Change Orders
$
daY'
Contract Price prior to this Change Order
13,048.00
Contract Time Prior to this Change Order
45 days
days or date
$
Net Nb...........(decreasc) of this Change Order
170.00
Net Increase (decrease) of this Change Order
o
day.
$
Contract Price with all approved Change Orders
12,878.00
Contract Time with all approved Change Orders
45 days
$
dayl or date
RECOMMENDED:
APPROVED:
CITY OF PARIS, PARIS, TX
APPROVED:
hy
EacincCr
by
Curtis
OWNER
by
Fe~ey, Mayor Pro Tem
CoatraCtor
ATTEST:
Mattie Cunningham, City Clerk
EXHIBIT A
ATTACHMENT TO CHANGE ORDER NO.
AND FINAL
PROJECT: Evergreen & South Church 12" Water Main Extension
OWNER:
City of Paris, Paris, Texas
CONTRACTOR: William Heuberger Construction
OWNER'S PROJECT NO.: 88-WSRB-01-88
ITEM
QUANIT ITY
7,
Replace existing 6"
sanitary sewer with
6" AWWA C-900 PVC pipe
( 20LF)
UNIT PRICE
$ 8.50
TOTAL DECREASE IN CONTRACT PRICE
TOTAL
($170.00)
170.00