1987-049-RES WHEREAS, the City Council of the City of Paris did heretofore, in Resolution No. 86-001, award the
RESOLUTION NO, 87-049
WHEREAS, the City Council of the City of Paris did
heretofore, in Resolution No. 86-001, award the contract for
construction of Additions to Water Treatment Plant to
Heritage Constructor's, Inc.; and,
WHEREAS, the Assistant City Manager, John Buss, recom-
mends the amendment of said contract by Change Order No. 9
attached hereto as Exhibit "A", which authorizes contractor
to proceed with modifications to Lake Crook raw water piping
to install a check valve by force account methods as spec-
ified under Method C in Contract General Provisions, Part
6.03 with contract period being extended by one day for each
actual full day worked on this modification and for the
number of whole days summed from the number of fractional
days worked on this modification; and,
WHEREAS, in the event contractor is not agreeable to
Change Order No. 9 then said modification should be accom-
plished by force account or separate contract as well best
serve the interest of the City of Paris; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PARIS, That the contract for Additions to the Water Treat-
ment Plant is hereby amended by Change Order No. 9 attached
hereto as Exhibit "A" and the Mayor of the City of Paris,
Billy Joe Burnett, is hereby authorized and directed, on
behalf of the City of Paris, to execute said Change Order.
BE IT FURTHER RESOLVED, That in the event the contrac-
tor refuses to agree to Change Order No. 9 then it is hereby
authorized and directed that the modification on said Change
Order No.9 be accomplished by force account or by separate
contract as will best serve the interest of the City of
Paris.
Passed and adopted this 11th day of May, 1987.
Bil~~
ATTEST:
~~,,~ ~ ~""""'~~
Mattie Cunning am, City C er
APPROVED AS :YORM:
A. hI'
r~~'"~:,~. City.oip~~i~
1\ . I
L..:..::..;:..\ ~.O. BOX ~J7 ~ARIS. TEXAS 75460
CHANGE ORDER # 9
. .
PROJECT TITLE
Additions to Hater Treatment Plant
PROJECT NO. 82.10 CONTRACT NO. 15-82-10-0340
CONTRACTOR Heritaqe Constructors, Inc.
CONTRACT DATE 1-13-R6
The following changes are hereby made to the Contract Documents:
CHANGE TO CONTRACT PRICE
Contractor is authorized to oroceed \'1ith modifications to lake Crook raw water piping
to install a check valve. The orice for this ~rork shall be determined by Method C
as specified in the Contract General Provisions, Part 6.03
"
CHANGE TO CONTRACT TIME
The Contract Period shall be extended by one day for each actual full day worked
on this modification and for the number of whole days summed from the number of
fractional days worked on this modification.
Justification:
To prevent backf10w into lake Crook when under voltage transients cause lake Crook
Pump Station raw water ~umps to shut down.
Requested by
Owner
date
Recommended by
John Buss, Assistant City t~naDer
date
Ordered by
Billy Joe Burnett, ~4yor
date
Accepted by
Dennis Smith, Heritage Constructors, Inc.
date