1986-048-RES WHEREAS, the City Council of the City of Paris did heretofore, in Resolution No. 86-001, award the
RESOLUTION NO. 86-048
WHEREAS, the City Council of the City of Paris did
heretofore, in Resolution No. 86-001, award the contract for
construction of Additions to Water Treatment Plant to
Heritage Constructor's, Inc,; and,
WHEREAS, the Director of Engineering, John Buss,
recommends the amendment of said contract by Change Order
No. 3 attached hereto as Exhibit "A", which provides for a
net increase in contract price of $26,913.00 to a total of
$3,072,270.00 and an increase in contract time of five (5)
calendar days, for relocation of the 2400 volt electrical
service, as described in the Engineer's letter of April 3,
1986, for furnishing and installation of fiberglass baffle
and diffuser walls as described in the Engineer's letters of
April 30, 1986 and May 22, 1986, and for piping changes at
the Maxey Plant alum sludge connection, as described in the
contractor's letter of May 14, 1986 and the Engineer's
letter of May 28, 1986; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PARIS, That the contract for Addition to the Water Treatment
Plant is hereby amended by Change Order No. 3 attached
hereto as Exhibit "A" and the Mayor of the City of Paris,
Billy Joe Burnett, is hereby authorized and directed, on
behalf of the City of Paris, to execute said Change Order.
Passed and adopted this 9th day of June, 1986.
Bi~~
ATTEST:
.
~rl~'~'~~~~
Mattie Cunning am, ity er'
, City Attorney
. ~ ~l-"
, '1 ~
City of Paris
,~;<- ,,'}'.:
,,\,.-\ -/ .,.1
-:~)"".
""..,\
P.O. 60X 1037
PARIS. TEXAS 75460
CHANGE ORDER
#3
PROJECT TITLE
Additions to Water Treatment
PROJECT NO.
82,10
CONTRACT NO.
Plant
15-82-10-0340
CONTRACT DATE _-1-1>_~.6_
CONTRACTOR
Heritage Constructors, Inc.
The following ch"ngcs are hereby made 10 the Contract Documents:
Changes to contract price:
1. For relocation of the 2400 volt electrical service, as described
in the Engineer's letter of April 3, 1986, and as a9reed during the meeting
of ~1ay 13, 1986.
Contract pri ce wi 11 be increased by $5,702,00,
2. For furnishing and installation of fibergalss baffle and diffuser
walls as described in the Engineer's letters of April 30, 1986 and
nay 22, 1986.
Contract price will be increased by $20,371,00.
3. For pIpIng changes at the Maxey Plant alum sludge connection, as
described in the Contractor's letter of May 14, 1986, and the Engineer's
letter of May 28, 1986,
Contract price will be increased by $840,00.
Total contract price increase due to this Change Order $26,913,00
Contract price prior to this Change Order $3,045,357,00
New contract price due to this Change Order will be $3,072,270.00,
Change to contract time:
The contract time wi 11 be increased by 5 ca 1 endar days.
New contract completion date due to this
Change Order will be February 28, 1987.
"
Requested by
r:ity of P~ri,
date
Recommended by
John Buss, Director of Engineering
date
Ordered by
date
Accepted by
Mayor
Joe LaRue
date
. I For.m 15.3