Code Enforcement Report: October & November 2021
Cases Worked: 453
Cases Completed: 690
Initial Inspections: 440
Re -inspections: 384
Total Inspections: 804
Lots Abated: 90
Other Work by Abatement Crew:
Tree & Brush Removal — 7 days
Removed Tires — 4 days
Removed Illegal Dumps — 7 days
Repaired/Serviced Equipment — 3 days
Blind Corners — 5 days
Worked Downtown — 7 days
Building and Standards Report: October & November 2021
There were 9 structures presented to the Building and Standards Commission:
343 Brown
1008 SW 3rd
513 E Sherman
835 NE 12th
1255 SE 14th
535 E Polk
830 NW 2811
250 NW 33rd
1113 M LK
There were 2 structures demolished in October & November, 2021.
1070 NE 13tH
1075 NE 13"