1986-031-RES WHEREAS, the City Council of the City of Paris did heretofore, in Resolution No. 86-001, award the
RESOLUTION NO. 86-031
WHEREAS, the City Council of the City of Paris did
heretofore, in Resolution No. 86-001, award the contract for
construction of Additions to Water Treatment Plant to
Heritage Constructor's, Inc.; and,
WHEREAS, the Director of Engineering, John Buss,
reconnnends the amendment of said contract by Change Order
No, 2 attached hereto as Exhibit "A", which provides for a
net increase in contract price of $48,345,00 to a total of
$3,045,357.00 and an increase in contract time of ten (0)
calendar days, for furnishing and installing the Alum Sludge
Pumping System, junction box, sluice gate and piping; and
for deleting the l8-inch RCP sludge line and three manholes:
as described in the Engineer's letter of March 7, 1986, and
in the contractor's letter of March 25, 1986, said changes
being necessary and desirable for use in conjunction with
the Water Treatment Plant Alum Sludge Disposal System; NOW,
THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PARIS, That the contract for Addition to the Water Treatment
Plant is hereby amended by Change Order No. 2 attached
hereto as Exhibit "A" and the Mayor of the City of Paris,
George Fisher, Jr., is hereby authorized and directed, on
behalf of the City of Paris, to execute said Change Order.
Passed and adopted this 14th day of April, 1986,
~i~rq~ Mayor
ATTEST:
~~\.,,~,,~~
Mattie unningbam, City ler
APPROVED AS TO FORM:
J~=r~;~
T, K, aynes, Clty Attorney
-----~------~
' II,
~~,,'\-:ft City of Paris
~ ~~-;;; ':;~'" P.O. BOX 1037 PARIS. TEXAS 75460
CHANGE ORDER 4/: 2
PROJECT TITLE Additions To Water Treatment Plant
PROJECT NO. 82.10 CONTRACT NO. 15-82-10-0340
CONTRACTOR Heritaqe Constructors. Inc.
CONTRACT OATE 1-13-86
The fOllowing changes are hereby made to the Contract Documents:
CHANGE TO CONTRACT PRICE For Furnishing and Install ing the Al um Sl udge Pumping System,
Junction Box, Sluice Gate and Piping; and for deleting the 18-inch RCP Sludge Line and
three Manholes: as described in the Engineer's Letter of March 7, 1986, and in the
Contractor's Letter of March 25, 1986,
Contract Price will be increased by
Contract Price due to Change Order #1
New Contract Price due to this Change Order will be
$ 48,345,00
2,997,012.00
3,045,357,00
CHANGE TO CONTRACT TIME
The Contract Time will be increased by
10 Calendar Days.
New Contract Completion Date due to this
Change Order will be February 23, 1987
Requested by
City of Paris
date
Recommended by
John Buss, Director of Englneerlng
Mayor George Fisher, Jr.
date
Ordered by
date
Accepted by
date
Joe LaRue