1985-088-RES WHEREAS, the City Council of the City of Paris did heretofore, in Resolution No. 85-087, award the
85-088
RESOLUTION NO.
WHEREAS, the City Council of the City of Paris did
heretofore, in Resolution No. 85-087, award the contract for
construction of a Wastewater Pumping Station to Johansson
Construction Co., Inc.; and,
WHEREAS, the Director of Engineering, John Buss,
recommends the amendment of said contract by Change Order
No.1 attached hereto as Exhibit "A", which provides for the
reduction of the instrumentation and control cost, changing
the sluice gate requirements, pipe and pipe fitting changes,
changes in building construction, deletion of the north
meter vault and meter, allowing reuse of temporary bypass
piping, clarification in earthwork specification which
resul ts in a reduction in contract price to $546,341. 00;
NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PARIS, that the Wastewater Pumping Station contract is
hereby amended by Change Order No. 1 attached hereto as
Exhibit "A" and the Mayor of the City of Paris, George
Fisher, Jr., is hereby authorized and directed on behalf of
the City of Paris to execute said Change Order.
Passed and adopted this 14th day of October, 1985.
~~f~MaYOr
ATTEST:
~~'''~~'
Matt1e unn1ng am, 1t er
APPROVED AS TO FORM:
~:-_-~
T. K. Haynes, City Attorney
~
~
CHANGE ORDER 4+ 1
,_;i~'}; City of Paris
,;-:::.>. / P_O. GOX 1037 : PARIS, TEXAS 75450
PROJECT TIT LE
PROJECT NO.
CONTRACTOR
WASTEWATER PUMPING STATION
85.20
15-85-20-0341
CDrnRACT DATE __.__~
CONTRACT NO
,Johansson Construction COrTijJilJ1Y, Inc.
The follo\'/ing Ch31lGCS arc hereby rl1tlde 10 the Con;rJc; Documents:
CHANGE: TO COf,nr-\/\CT PRICE
$590,000.00
Original Total Contract Price
Reduction in the Contract Price Due to
This Change Order
43,659.00
New Total Contract Price Due to This Change
Ol-der fOl- Changes Desuibed in Attachlllent "A"
$545,341.00
CH/\NGE TO cor\'Tr:;;\CT :I~'"H:
JUST! FICAT!ON
None
The changes descl-ibed in detail in Attachment "A" involve clal-ifications in the
contract documents and changes in the work which will reduce the Contract Price
while maintaining the utility and longevity of the facility. The chan0es involve
in summary:
1.
2.
3.
4.
5.
5.
7.
Requested by
Recommended by
Ordered by
Reduction of the instrumentation and control cost.
Changes in the sluice gate requirements.
Pipe and pipe fitting changes.
Changes in the building construction.
Deletion of the north meter vault and meter.
Allo\'ling reuse of the temporary bypass piping.
Clarification in the earthwork specifications.
Owner
date
U.:Jtc
Ron Pedersen, Staff Engineer
dJtc
Accepted by
George Fisher, Mayor
Johansson Construction Company, Inc.
date
Form 15.3
ATTACHMENT "A"
CHANGE ORDER NO. 1
Contract Title: Wastewater Pumping Station
Contract Number: 15-85-20-0341
1. Instrumentation and Controls:
No changes in the requirements of the
Contract Documents
Oeduction $ 5,600.00
2. Sluice Gates:
Section 11202, 1.5 Sluice Gates, E.
Change the schedule for SV-l, SV-2 and SV-3 to
Read: "Seating head: 30 feet
Unseating head: 20 feet
Max. Operating head: 20 feet"
Deduction $ 4,214.00
3. Pipe and Fittings
Section 11205
2.1 Delete the last sentence; cast iron fittings will
be acceptable with ductile iron pipe.
2.3 In the fi rst paragraph, change".... cl ass number 52."
to read "....class number 50."
3.3 B.l.c. delete the second sentence; restrainer glands
will be permitted.
Deduction $ 2,689.00
4. Building:
The building shall be constructed of 8-inch concrete
masonry units with a nominal 6-inch reinforced concrete
roof. The general arrangement shall be as shown in the
contract documents. Building details shall be as shown
on the Contractor's drawing dated October 9, 1985, and
as approved by the Engineer.
Deduction $ 7,000.00
5. Delete Meter Vault and Meter:
Delete the meter vault and meter located north of the
pump station structure on the 18-inch pump discharge
force main, including: excavation, concrete, miscellaneous
metals, reducers, coupling, spool pieces, meter, conduit,
wiring, and recorder. Piping in this area shall be IS-inch
as specified for this service.
Deduction $22,711.00
6. Reuse of Bypass Piping:
27-inch RCP pipe may be used for the temporary bypass
shown on the plans. Upon completion of the diversion
structure this piping may be re-installed as part of the
permanent work where such material is called for in the
Contract Documents. Re-used RCP pipe shall be subject
to inspection and all other provisions of the Contract
Documents.
Deduction $ 1,445.00
Total Deduction for Items 1 through 6
$43,659.00
7. Earthwork:
Section 02200
3.3, E. Change the last sentence of the last paragraph
to read:
"....a seal slab of concrete, or other method or
methods as approved by the Engineer, to prevent
significant desiccation of the clay."
3.7, B. Delete the entire second paragraph.
- 2 -