29 - Waste Water Treatment Plant Project Status UpdateILI
TO: Mayor, Mayor Pro Tem & City Council
FROM: Grayson Path, City Manager
Rob Vine, Assistant City Manager
Doug Harris, Utilities Director
SUBJECT: Waste Water Treatment Plant Project — Status Update
DATE: July 25, 2022
BACKGROUND:
On April 11, 2022, the City Council heard a status update and presentation on the Waste Water
Treatment Plant (WWTP) Project. At that time, the plans had reached 90% completion. We have
since then reached 100% design, TCEQ has approved our design, and we have issued a request for
bids. This was a two-step process designed to narrow our list to qualified contractors, then accept
bids from this shortlist of qualified contractors. Those bids are due at the end of August 2022. We
have authorized an extension by request of some of the contractors which we believe will work in
our favor of seeking better bids. In addition, we held a mandatory pre-bid meeting for contractors
on Tuesday, July 12th at the WWTP. The meeting went very well.
On Monday, June 20, 2022, several City Staff met with representatives from Garver Engineering,
SAMCO Capital Financial Advisors, and McCall, Parkhurst & Horton Legal Counsel in Frisco,
TX to discuss the status of the WWTP Project, specifically the economics at this time. As you are
all aware, our nation has seen rampant price increases and material shortages this past year. Our
project is expected to be impacted by this as well.
STATUS OF ISSUE:
When we started this project two years ago, we were estimating a total project cost of $60-$70
million. Because of arbitrage issues with the IRS, and to help ease our rate increases for the
residents, we took out a $45 million bond as a "phase I" to get us started. To support this, we
worked with our financial advisor and rate consultant to craft a strategic approach for rate increases
using a stair step method to allow residents to acclimate to increases. The key is balancing our
ability to "cash flow" which is our ability to raise enough revenue each year to meet the debt
payments when they come due. This is a true balancing act because we need money to fund the
project, but the bond requires repayment of debt to the lenders which cannot be pushed off too far,
all the while we want to ease in to rate increases for our residents. As I said, a plan was crafted
and the City Council implemented it. With this, we incorporated rate increases to then allow us to
take out the "phase II" of bonding when the time came, which was the balance of the estimated
$60-$70 million project. That would be scheduled to occur in 2024 or 2025. As of today, I am
told that our rate program has been very successful, fully capable to meet the growing needs of
debt payment for our initial bond and foreseen to meet the needs of the second bond that was
planned to come, all under the original cost estimates.
Now, two years later, under the 2022 economy and price hikes we are seeing, our project has
grown to an estimated $80-$90 million. Our staff and Garver Engineering have worked extremely
hard to eliminate any excess and provide as lean a project as possible. However, there is only so
much you can cut before you functionally eliminate the project completely. I must also stress,
"phase I" is incomplete without "phase II". Remember, we only divided this project up in to two
phases because of arbitrage issues and a goal of easing residents in to rate increases over a period
of years given debt payment can only be delayed so long. It could become easy to incorrectly
think that "phase I" will give us a product that will suffice. When asked point blank, our staff and
Garver have stressed that "phase I" will not suffice. What we have done is taken the full project,
pulled out elements that can hold out long enough to allow us to build "phase I" elements. But
once "phase I" is complete, the remaining aged elements scheduled for "phase II" must start.
Basically, "phase II" elements can hang in there longer than "phase I" elements.
Garver Engineering has estimated that, under today's pricing in the market, we are in need of an
additional estimated $7 million to complete those elements designed in "phase P. The price for
"phase II" has also gone up, making up the balance of the now estimated $80-$90 million total
price tag. Important — the request for bids we have issued will tell us the true amount needed for
"phase I", so I am still hopeful that having a slate of qualified and competitive contractors as well
as Garver Engineering examining and verifying their bid pricing, will bring about some better
pricing than expected. However, we should expect a need to issue a second bond to support "phase
I", this year. That unfortunately will require us to amend our rate increase plan. I still fully plan
to stair step our increases over time, but the rise of the steps will have to get a little steeper. We
are trying to avoid turning this in to a cliff climb though, so we will work hard to balance this out.
In a year or two, we will need to begin preparations for a "phase II" bond. Instead of this being
$15-$20 million as we originally planned, it is now estimated to be closer to $35-$40 million.
Again, bids will decide and if we continue to have a slate of good and qualified competition, we
will get the best price we possibly could get.
This is not the type of news I like to give you, but as City Manager, it is my job to give you the
news as I know it. I know that rate increases are painful, but we must stay the course to complete
this critical project.
BUDGET:
Please see the "Status of Issue" section above.
OPTIONS:
1. This agenda item is information only and is meant to prepare you for what we expect to be
higher than planned bids with a possible need to seek an additional bond for phase I, thus
additional rate increases to support this bond.
RECOMMENDATION:
1. This agenda item is information only and is meant to prepare you for what we expect to be
higher than planned bids with a possible need to seek an additional bond for phase I, thus
additional rate increases to support this bond.