10 - Wastewater Treatment Plant Project and presentation of bidsNo. 10
TO: Mayor, Mayor Pro Tem & City Council
FROM: Grayson Path, City Manager
Rob Vine, Assistant City Manager
Doug Harris, Utilities Director
SUBJECT: Waste Water Treatment Plant Project — Status Update
DATE: October 10, 2022
BACKGROUND:
On July 25, 2022, the City Council heard a status update on the Waste Water Treatment Plant
(WWTP) Project. At that time, the City Council was informed that pricing over the summer was
going up and we were expecting to see some significant increases in our bids. We have since then
received, opened, and reviewed bids for the WWTP Project and have a presentation for you tonight
on the results with recommendations for next steps.
STATUS OF ISSUE:
To provide some historical context, when we started this project two years ago, we were estimating
a total project cost of $60-$70 million. Because of arbitrage issues with the IRS, and to help ease
our rate increases for the residents, we took out a $45 million bond as a "phase I" to get us started.
To support this, we worked with our financial advisor and rate consultant to craft a strategic
approach for rate increases using a stair step method to allow residents to acclimate to increases.
The key is balancing our ability to "cash flow" which is our ability to raise enough revenue each
year to meet the debt payments when they come due. This is a true balancing act because we need
money to fund the project, but the bond requires repayment of debt to the lenders which cannot be
pushed off too far, all the while we want to ease in to rate increases for our residents. A plan was
crafted and the City Council implemented it. With this, we incorporated rate increases to then
allow us to take out the "phase II" of bonding when the time came, which was the balance of the
estimated $60-$70 million project. That would be scheduled to occur in 2024 or 2025. As of today,
I am told that our rate program has been very successful, fully capable to meet the growing needs
of debt payment for our initial bond and foreseen to meet the needs of the second bond that was
planned to come, all under the original cost estimates.
We opened bids on Thursday, September 8, 2022. The bid totals will be shared in Garver
Engineering's presentation tonight. In short, we only received two bids and they were much higher
than expected. Garver Engineering will provide a presentation tonight that explains the bidding
process, the review process, the analysis of the bids, working with city staff and the lowest bidder
to negotiate final pricing, the reasons for why the bids are higher than expected, and the timeline
going forward.
Garver Engineering and City Staff have worked hard these past several weeks to dissect the bid
and see if there is anything that we can cut in order to shave the costs down. Unfortunately, the
economy is driving prices up and the condition of our WWTP is such that we must move forward
with taking out another $26 million bond to support the approximate $60 million bid. This will
have a rate increase associated with it in order to cash flow our increased debt service. In addition,
we will still have Phase II to implement in a year or so that must be prepared for and done. I must
stress that "phase I" is incomplete without "phase II". We only divided this project up in to two
phases because of arbitrage issues and a goal of easing residents in to rate increases over a period
of years given debt payment can only be delayed so long. It could become easy to incorrectly think
that "phase I" will give us a product that will suffice. When asked point blank, our staff and Garver
have stressed that "phase I" will not suffice. What we have done is taken the full project, pulled
out elements that can hold out long enough to allow us to build "phase I" elements. But once
"phase I" is complete, the remaining aged elements scheduled for "phase II" must start. Basically,
"phase II" elements can hang in there longer than "phase I" elements.
It is strongly recommended that, despite the unexpected increase in bid, we do not delay in
proceeding. This project has been in the works for nearly 10 years; had it proceeded earlier in that
timeline, it would have cost much less. Our research shows that our economy is only going to
increase pricing over the next year, so we have concluded that rebidding is not in our best interest.
And given there are projects all over Texas exceeding cost estimates, not only will we see a higher
price but we are not likely to see more bidders. This is a very challenging issue we are facing, but
unless any other options can be brought forward, we believe our only way is forward.
Our next steps are to award a bid on Monday, October 24, 2022, amend our rate increase program
to account for the needed increases in rates to cash flow our debt, and issue new debt in the
approximate amount of $26 million to cover the added cost for the project.
BUDGET:
The total bid for the lowest contractor is now approximately $60 million. This will require an
additional $26 million in bonding to cover the added cost. To support this, we must unfortunately
expedite our rate step increase program and increase the planned amounts. We are currently in the
middle of implementing rate increases every six months through April 2026. We must now change
our plan as follows (this is still approximate — we will have a final recommendation at the 10/24/22
City Council meeting):
Waste Water Rate
e Increase
Our current rate program was proving to be very successful in meeting expense needs for our initial
bond, so we are confident that the figures provided by our consultant for the adjusted rates will
likewise cover our needs for the additional $26 million needed. There is however still uncertainty
when it comes to Phase II as we cannot guarantee pricing at this point given what we have seen in
Phase I.
RECOMMENDATION:
1. This agenda item is primarily information only unless the City Council feels certain actions
should be taken. It is our recommendation that we proceed with awarding a bid, increasing
the waste water rates, and issuing additional debt service on October 24, 2022. The bid is
only good for 90 days from September 8, 2022, so a decision will need to occur by
December 8, 2022.
ADDITIONAL THOUGHTS:
This is a bleak and daunting challenge for our citizens to take on. While it could be easy to once
again kick this can down the road, we would face a much greater chance of making this worse than
better (proof is what is happening to us today). But, while we are facing this great expense today,
there is indeed hope in the very near future for some potential relief.
Rate Increases
Increase 5k Gallon Bill
Date
Current
New
Current
New
Apr -21
8.50% _
No Change
Oct -21
8.50/
No Change
Apr -22
8.50%
No Change
Oct -22
3.75%
No Change
Jan -23
0.00%
...__ .......�. _
9.00%
$ 61.41
$ 66.92
Apr -23
3.75%
9.00%
.--- ........
$ 63.70
$ 72.95
Oct -23
3.75%
I 7.50%
$ 66.10
vvv
$ 78.44
Apr -24
3.75%
7.50%
$ 68.59
$ 84.33
Oct -24
4.25%0,00%
...
$ 71.48
$ 84.33
Apr -25
4.25%
0.00%
$ 74.50
$ 84.33
Oct -25
�_ 4.25%
6.75%
._w... _
$ 77.66
$ 90.03
Apr -26
4.25%..
6.75%
....
$ 80.96
-1
$ 96.12
Our current rate program was proving to be very successful in meeting expense needs for our initial
bond, so we are confident that the figures provided by our consultant for the adjusted rates will
likewise cover our needs for the additional $26 million needed. There is however still uncertainty
when it comes to Phase II as we cannot guarantee pricing at this point given what we have seen in
Phase I.
RECOMMENDATION:
1. This agenda item is primarily information only unless the City Council feels certain actions
should be taken. It is our recommendation that we proceed with awarding a bid, increasing
the waste water rates, and issuing additional debt service on October 24, 2022. The bid is
only good for 90 days from September 8, 2022, so a decision will need to occur by
December 8, 2022.
ADDITIONAL THOUGHTS:
This is a bleak and daunting challenge for our citizens to take on. While it could be easy to once
again kick this can down the road, we would face a much greater chance of making this worse than
better (proof is what is happening to us today). But, while we are facing this great expense today,
there is indeed hope in the very near future for some potential relief.
As you will recall, and this is all public information found in previous city council meetings, we
have many housing, retail and economic development projects in the works that — if followed
through on — will serve to spread this burden out. Our planned WWTP project has built in growth
capacity (we are using about 4.5 MGD and the plant will be built to about 7.25 MGD). Therefore,
until we grow to the point that TCEQ requires us to expand our plant, we have some available
capacity to add more customers on. This bid is in essence a "fixed" amount (barring unexpected
issues). With any fixed amount, the more it can be spread out, the cheaper it becomes to any one
individual funding source (in this case, rate payers). To this point, we have the following projects
in one stage or another of development:
- Numerous 5 in 5 Housing Agreements (signed and in the works)
- Forest Brook Estates
- Apartment Complex (golf driving range)
- Westgate Apartments
- Pshigoda Foundation (South Collegiate)
- Senior Citizen Tax Credit Project (East Lamar, Texas Housing Commission)
- Cunningham Town Home Project
- HOME Program
- Chapter 380 Agreements — Town Center, Home 2 Suites, and TownPlace Suites and
Fairfield Inn
- Harbor Freight, HTeo, Farmers Bank, Taco Bueno, etc. (new retail not Ch. 380)
- Several industrial prospects through the PEDC.
- Water line extension and redundancy project (sets us up for some smaller industrial users)
I'm confident I have left some things off, and there are others I'm aware of that are not as far along
as the above, but from this I would like to point out that we have hundreds of new housing units
and several new retail and industrial entities in the works, all of which will be added to the family
to help spread out the costs of the WWTP. This does not mean today's residents will see rates
come back down to pre-WWTP prices (it would take substantially more growth to accomplish
that), but I do think this will provide some much needed HOPE that development is bringing more
chairs to the table to help us with our bills. Their addition will of course bring forth additional
operational costs (chemicals, electricity, etc.) to treat the added water, but there is economy of
scale that allows their additional funding to strengthen our utility financially while including a
bond component to their rate that will have a direct positive impact to our existing rate payers by
spreading our (fixed) debt payments out across more payers.
I hope this information provides you some comfort as you prepare yourself for the rough road
ahead. We have worked so hard these past three years to bring development to our community. I
believe the next three years will show us the fruits of our labor. Our community has a reputation
of resiliency following fires and tornadoes, and while the WWTP is not a naturally created issue,
it is still a matter that requires us to once again prove ourselves resilient and capable of coming
together to address it. Therefore, if there is anyone who has the ability to initiate development in
our community, we encourage them to act. The City stands ready to support this.
I hope this information has proven helpful to you. This has all been made possible because of your
good policy decisions. Good policy decisions prepares us for tough times. Thank you for your
service and for the work you continue to do. We as staff will keep working hard to facilitate more
success.