16 B - Award bid Phase I of the Wastewater Treatment Plant to Thalle ConstructionNo. 16
October 11, 2022
Grayson Path
City of Paris
135 SE 1 s' Street
Paris, TX 75460
3010 Gaylord Parkway
Suite 190
Frisco, TX 75034
TEL 972.377.7480
FAX 972.377.8380
www.Ga rverUSA.com
Re: Paris Contract No. 1 Phase 1 WWTP Improvements
Recommendation of Award
Mr. Path:
Bids were received for the Contract 1 Phase 1 Wastewater Treatment Plant Improvements Project at
City Hall at 2:00 PM on September 801. A total of two (2) bids were received on the project. A tabulation
of the bids received is enclosed with this letter. The bids have been checked for accuracy and
compliance with the contract documents, and all bidders have provided the required documents. The
two base bids and associated bid alternates received are summarized as follows:
Thalle
Gracon
Item Type
Description
i Construction
Construction,
Co., Inc.
Inc.
Bid Item 1
wwwwwwwwwwwww_
All work except as indicated in other bid
$64,460,000
$69,950,000
items
Bid Item 2
Trench Safety System
$5,000
$2000
Bid Item 3
Cash Allowance 1: Double Disc Pump
$223,950
$223,950
Equipment
Bid Item 4
Contingency Allowance 1 forwork
$1,000,000
$1,000,000
change directives
Contingency Allowance 2 for primary
Bid Item 5
electrical service installation and
L $120,000
$120,000
rerouting
Bid Item 6
Contingency Allowance 3 for Special
$60,000
$60,000
Inspections and independent testing
Bid Item 7
Contingency Allowance 4 for additional
$45,000
$45,000
GPS -based survey
Bid Item 8
Contin Allowance 5 for Additional
gencField
$20,000
�
$20,000
Trailer Equipment
Bid Item 9
Additional area of 10" compacted gravel
- 0
$50,000
$65,000
surface
Bid Item 10
Solids, sludge, and grit removal and
$160,000
$340,000
disposal
Total Base Bid _ _
$66,142,950
71,843,950
Item Type
Description
Thalle
Gra -on
Deduct Generator, Concrete Pad, and
Alternate 1
associated electric, instrumentation, and
- $1,025,000
-$760,000
controls
Alternate 2
Deduct for abandoning in-place the
- $1,080,000
- $400,000
Orbital Aeration Basins
Alternate 3
Deduct for deleting Final Clarifier 4
- $1,425,000
- $1,280,000
Alternate 4
Deduct for deleting rehabilitation for Final
- $1,480,000
- $1,600,000
Clarifiers 1, 2, and 3
Alternate 5
Deduct for deleting Primary Clarifier 2
-$420,000
- $1,170,000
Additional Unit
Price Item 1
100 LF of concrete crack repair
$150/LF
$60/LF
Additional Unit
Price Item 2
Existing clarifiers toping grout
$1,000/CY
$1,200/CY
Additional Unit
Price Item 3
Existing concrete resurfacing
$500/SF
$400/SF
Both contractors were approved through pre -qualification, and we consider Thalle Construction Co.,
Inc., the low bidder, to be a responsive, responsible bidder. We believe that the bid submitted by Thalle
Construction Co., Inc. represents a good value for the City of Paris. We recommend that the
construction contract for the Contract 1 Phase 1 Wastewater Treatment Plant Improvements project be
awarded to Thalle Construction Co., Inc. in the amount of $65,118,950.00 by accepting the base bid
with Deductive Alternate 1.
Please call if there are any questions.
Sincerely,
GARVER, LLC
deA A. C _,
Lance Klement, P.E.
Senior Project Manager