09/15/2022 MinutesMINUTES OF REGULAR MEETING
AIRPORT ADVISORY BOARD
107 EAST KAUFMAN STREET
PARIS, TEXAS
THURSDAY SEPTEMBER 15,2022,5:30 P.M.
The Airport Advisory Board was called to order at 5:30 p.m. by Airport Manager Paul Strahan.
Members present: Scott Jackson, Jeffrey Nichols, and LeAndra Maughon.
City Representatives: Council Member Gary Savage; Assistant City Manager Robert Vine; Airport
Manager Paul Strahan
2. Receive Report from the Airport Manager.
• Introductions
Each Airport Advisory Board Member and each City Representative introduced themselves.
• Advertisement for the Airport
Mr. Strahan explained the different websites used to advertise the fuel prices for the airport, as
follows: FaceBook, AirNav, ForeFlight, Skyvector, and the city website for the airport.
• Previous Fly -In
Mr. Strahan talked about the previous airport fly—in, which was held on July 9, 2022. He said
there was a good turnout, with 87 planes and approximately 300 people in attendance. He also
said the airport had three food trucks on site. Mr. Strahan reported three companies offered items
to raffle, the airport offered two items to raffle, as well has donated 330 bottles of water.
• Different Types of Airport Funding
Mr. Strahan explained the different types of funding the airport has opportunities to make
application, from the FAA and TXDOT. He explained that Infrastructure Bill (IIJA Funds) passed
late last year but the airports had received no direction as how to spend the funds. He said the
infrastructure money will be for five straight years of funding for the airport with no date as to
when the funds are required to be spent. Mr. Strahan also explained Non — Priority Entitlements
(NPE) Funds were allotted in the amount of $150K per year and could be banked up to four years.
He emphasized if the funds were not spent prior to the four years, they were required to be returned
to FAA or TXDOT. Mr. Strahan said the airport has banked four years of NPE funds, which will
help cover the cost of the runway project. He explained that the Routine Airfield Maintenance
Program (RAMP) Grant is money from TXDOT and was up to $ l OOK each year, with one-half
being reimbursable. He also said money from the grant could only be used in certain areas.
• Runway Project
Mr. Strahan stated the airport planner and TXDOT engineer came to the airport to talk about the
upcoming runway project. He explained that the date for the runway project comes from TXDOT
and not from the airport. Mr. Strahan said the airport still did not have a date for the runway project;
TXDOT was awaiting a Project Manager to be assigned to the project. He said the cost of the
runway project was $2.75M, and that the original work planned had changed due to pushing the
project back year after year, and addition of the ever changing inflation situation.
• Taxi -Lane Extension
Mr. Strahan stated he was hoping the infrastructure money would help extend the taxi -lane which
would open up plots of land to build private hangars. He said the taxi -lane extension would be
540'
• Land to Develop
Mr. Strahan explained going forward, the Northwest land on the airport would be the future land
to develop for the airport and used for new taxi -lanes and private hangars.
• Items on 2023 Airport Budget
Mr. Strahan reviewed the big items on the 2023 airport budget. He explained the airport took over
all the mowing for the airport so a new zero turn mower was placed in the budget. Leasing an
avgas truck was discussed more specifically, the airport was working with the fuel provider,
AvFuel, to lease a truck.
3. Citizen's Input
No one spoke during the citizen's forum.
4. Next Airport Advisory Meeting
Mr. Strahan announced the next Airport Advisory Meeting would be November 17, 2022.
5. Adjournment
Meeting was adjourned at 6:14PM
_U
Approved this 7 ' day of November 2022.
Paul Strahan, Airport Manager.... __.........— .........r._