08 - Wastewater Treatment Plant UpdateItem No. 8
I: I
TO: Mayor, Mayor Pro -Tem & City Council
Robert Vine, Interim City Manager
FROM: Danny Rowell, Interim Director of Utilities
SUBJECT: WASTEWATER TREATMENT PLANT IMPROVEMENTS PROJECT
PRESENTATION BY GARVER.
DATE: September 9, 2024
BACKGROUND: Garver is the Engineering firm overseeing project management for Phase I
and Phase II Wastewater Treatment Plant improvements project and will give a presentation and
update to City Council on progress and work completed.
RECOMMENDATION: This is a presentation only.