08-C Pine Mill Rd & Loop Project Construction Contract
CITY OF PARIS, TEXAS
CITY COUNCIL AGENDA REQUEST
MEETING DATE: 15-14-07
~Action 0 Discussion Dlnformation DRefer to:
SUBMITTED BY:
I Engineertng Department
DESCRIPTION:
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PARIS, PARIS,
TEXAS, AUTHORIZING AND APPROVING THE EXECUTION OF A CONTRACT
FOR THE CONSTRUCTION OF WASTEWATER SYSTEM INPROVEMENTS
FOR THE TEXAS DEPARTMENT OF TRANSPORTATION PINE MILL ORAD
AND LOOP 286 NE GRADE SEPARATION PROJECT, PHASE II; MAKING
OTHER FINDINGS AND PROVISIONS RELATED TO THE SUBJECT; AND
DECLARING AN EFFECTIVE DA TE,
BACKGROUND INFORMATION:
This will be the second and last phase of the project. This will allow TXDOT to
complete the laying of storm sewer pipe that currently conflicts with our existing
18-inch clay tile sewer line. B. Bray Construction was the low bidder, with a bid of
$170,374.00, the Engineers estimate was 199,935.00 (see attached bid tab). I
recommend awarding the bid to B. Bray Construction.
FISCAL AUTHORITY:
BUDGETED: Account #:
GRANT: Account #:
BOND I C 0 Account #:
Other: City Council approved funding in March 2007 with Resolution 2007-040.
LEGAL REVIEW:
MANAGER'S RECOMMENDATION:
MEMORANDUM
TO:
Honorable Mayor and City Council
Ernie Clark, ~t^rim City Manager
Shawn N apie~f .~. City Engineer / Director of Public Works
May 9, 2007
FROM:
DATE:
SUBJECT: Award of Bid - Wastewater Improvements (Pine Mill Road & NE Loop
286) Phase II
Competitive bids were received for the referenced project on April 19th, 2007, at 3:00
P.M.
Attached is a tabulation of bids received for your reVIew. It also contains the
advertisements dates in The Paris News.
I recommend that the bid be awarded to B. Bray Construction Co., Inc., Paris, TX, in
the amount of$170,374.00. The Engineer's estimate for this project was $199,935.00.
-
Engineer's Estimate Barney Bray Construction
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL
1 Mobilization LS 1 $10,000.00 $10,000.00 $4,800.00 $4,800.00
2 6" SDR 35 PVC Gravity Sewer LF 32 $10.00 $320.00 $4.50 $144.00
3 8" SDR 35 PVC Gravity Sewer LF 98 $15.00 $1,470.00 $6.00 $588.00
4 18" Ultra-Rib PVC Gravity Sewer LF 2025 $20.00 $40,500.00 $14.00 $28,350.00
5 0'-5' Trench LF 145 $10.00 $1,450.00 $8.00 $1,160.00
6 5'-8' Trench LF 520 $12.00 $6,240.00 $11.00 $5,720.00
7 8'-10' Trench LF 1490 $14.00 $20,860.00 $13.00 $19,370.00
8 Trench Safety LF 2010 $2.00 $4,020.00 $1.00 $2,010.00
9 Standard Concrete Manhole 6' Deep EA 1 $2,500.00 $2,500.00 $3,300.00 $3,300.00
10 Standard FiberQlass Manhole 6' Deep EA 10 $3,500.00 $35,000.00 $4,500.00 $45,000.00
11 Additional Depth of fiberQlass Manhole VF 22 $180.00 $3,960.00 $150.00 $3,300.00
12 Remove Manhole EA 5 $1,000.00 $5,000.00 $850.00 $4,250.00
13 Man hole drop structure EA 1 $1,000.00 $1,000.00 $1,250.00 $1,250.00
14 6" Main line Cleanout EA 1 $500.00 $500.00 $350.00 $350.00
15 Manhole Marker EA 10 $50.00 $500.00 $40.00 $400.00
16 4" Sewer Service, near side EA 3 $1,200.00 $3,600.00 $375.00 $1,125.00
17 4" SDR 35 PVC Service line LF 100 $12.00 $1,200.00 $9.00 $900.00
18 Concrete Encasement LF 40 $10.00 $400.00 $30.00 $1,200.00
19 Rip Rap Repair LF 36 $5.00 $180.00 $60.00 $2,160.00
20 Gravel Drive Repair EA 40 $8.00 $320.00 $20.00 $800.00
21 Asphalt Repair LF 115 $25.00 $2,875.00 $25.00 $2,875.00
22 Concrete Repair LF 15 $50.00 $750.00 $60.00 $900.00
23 Concrete Channel Replacement LF 30 $300.00 $9,000.00 $60.00 $1,800.00
24 8" Connection to existinQ main EA 2 $1,000.00 $2,000.00 $650.00 $1,300.00
25 18" Connection to existing main EA 2 $3,000.00 $6,000.00 $1,600.00 $3,200.00
26 Force Main Connection LS 1 $12,000.00 $12,000.00 $10,000.00 $10,000.00
27 6" C-900 PVC LF 236 $15.00 $3,540.00 $12.00 $2,832.00
28 6" Gate valv with box EA 1 $750.00 $750.00 $590.00 $590.00
29 Misc FittinQs & Tie Ins LS 1 $4,000.00 $4,000.00 $1,500.00 $1,500.00
30 ClearinQ & GrubbinQ all trees and brush LS 1 $5,000.00 $5,000.00 $4,200.00 $4,200.00
31 Allowance for Unknown Conditions LS 1 $15,000.00 $15,000.00 $15,000.00 $15,000.00
Total $199,935.00 Total $170,374.00
COST ESTIMATE (PINE MILL ROAD & NE LOOP 286 PHASE II)
PUBLISH PARIS NEWS
DATE: April 8, 2007
DATE: April 15, 2007
ADVERTISEMENT FOR BIDS
PROJECT:
W ASTEW ATER SYSTEM IMPROVEMENTS (PINE MILL ROAD & NE LOOP 286)
PHASE II
OWNER:
CITY OF PARIS, PARIS, TEXAS
Sealed bids for wastewater system improvements (Pine Mill Road & NE Loop 286) will be received by
the City of Paris, Paris, Texas, at the office of City Manager, City Hall, 135 1st Street S.E., P.O. Box
9037, Paris, Texas 75461-9037, until 3:00 p.m. on Thursday, April 19th, 2007, at which time all bids will
be publicly opened, read aloud, tabulated, and referred to the City Council for the purpose of letting such.
Contract Documents may be examined at the following place(s):
City Hall Annex
150 S.E. 151 Street
Paris, Texas 75460
(903) 784-9298
Contract Documents may be obtained at the City of Paris, Engineering Office by depositing a check in the
amount of$20.00 per set payable to the City of Paris which shall be non-refundable.
Bids must be submitted on the bid form included in the Contract Documents. Bid Security in the form
and amount as stated in Instruction to Bidders must be submitted with each bid.
All Bids shall remain open for 60 days after the Bid opening.
It is intended that the project be awarded as a single contract to include all construction as shown in the
contract documents.
The City of Paris, Paris, Texas, as OWNER, Reserves the right to waive any and all informalities and to
reject any and all bids.
Janice Ellis
City Clerk
DRAFT
RESOLUTION NO.
f:attorneylresworklcurrentl Pine Mill-Loop 286 Separation - Phase 2 Award Bid
May 8, 2007
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PARIS,
TEXAS, ACCEPTING THE BID OF B. BRAY CONSTRUCTION AND
A WARDING A CONTRACT IN THE AMOUNT OF $170,370.00 FOR THE
CONSTRUCTION OF WASTEWATER SYSTEM IMPROVEMENTS FOR
PHASE 2 OF THE TEXAS DEPARTMENT OF TRANSPORTATION PINE
MILL ROAD AND LOOP 286 NE GRADE SEPARATION PROJECT;
MAKING OTHER FINDINGS AND PROVISIONS RELATED TO THE
SUBJECT; AND DECLARING AN EFFECTIVE DATE.
WHEREAS, the City of Paris did advertise for bids on April 8, 2007 for furnishing,
labor, materials, and equipment and for performing all work required for the Wastewater
System Improvement Project - Phase 2 as a part of the Texas Department of Transportation's
Pine Mill Road & NE Loop 286 Grade Separation Project, which bids were received until 3:00
o'clock p.m., Thursday, the 19th day of April, 2007; and,
WHEREAS, the bid submitted by B. Bray Construction was determined to be the lowest
responsible bid providing best value to the City of Paris, Texas, and it should be awarded the
bid for the same; and,
WHEREAS, the form of the contract for such construction project, attached hereto as
Exhibit A, should in all things be approved, and the Mayor should be authorized to execute the
same;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PARIS, TEXAS:
Section 1. That the findings set out in the preamble of this resolution are hereby in all
things approved.
Section 2. That the bid of B. Bray Construction for the "Wastewater System
Improvement Project - Phase 2" as a part of the Texas Department of Transportation's Pine Mill
Road & NE Loop 286 Grade Separation Project" in the amount of $170,374.00, be, and the
same is hereby, accepted and let conditioned upon said contractor meeting all of the terms and
specifications included in the bid documents.
Section 3. That the form of the contract with B. Bray Construction, attached hereto as
Exhibit A, be, and the same is hereby, approved.
Section 4. That the Mayor be, and he is hereby, authorized and directed to execute, on
behalf of the City of Paris, the contract with B. Bray Construction, upon the terms and
conditions substantially in accordance with the form shown in Exhibit A, attached hereto.
Section 5. That this resolution shall be effective from and after the date of passage.
PASSED AND APPROVED this 14th day of May, 2007.
Richard Manning, Mayor
ATTEST:
Janice Ellis, City Clerk
APPROVED AS TO FORM:
w. Kent McIlyar, City Attorney
AGREEMENT
THIS AGREEMENT is dated as of the 14th day of May in the year 2007 by and between the
City of Paris (hereinafter called OWNER) and B. Bray Construction Co., Inc. (hereinafter called
CONTRACTOR).
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth,
agree as follow:
Article 1. WORK
CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents.
The Work project is generally described as follows: Construction of approximate Iv 2025 LF 18" gravity
sewer. 10 fiberglass manholes. I concrete manhole. 3 single sewer services. and all misc. asphalt repairs and misc.
items on bid documents not listed.
Article 2. ENGINEER
The Project has been designed by The City of Paris Engineering Department, Paris, Texas, who
is hereinafter called ENGINEER and who is to act as OWNER'S representative, assume all
duties and responsibilities and have the rights and authority assigned to ENGINEER in the
Contract Documents in connection with completion of the Work in accordance with the Contract
Documents.
Article 3. CONTRACT TIME
3.1 The Work will be substantially completed and ready for final payment within 120 calendar
days from the date when the Contract Time commences to run, as provided in the General
Conditions.
3.2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence of
this Agreement and that OWNER will suffer financial loss if the Work is not completed within
the times specified above, plus any extensions thereof allowed in accordance with the General
Conditions. They also recognize the delays, expense and difficulties involved in proving in a
legal or arbitration proceeding the actual loss suffered by OWNER ifthe Work is not completed
on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree
that as liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay OWNER
$500 for each calendar day that expires after the time specified.
Article 4. CONTRACT PRICE
OWNER shall pay CONTRACTOR for completion of the work in accordance with the Contract
Documents in current funds as follows:
At the unit prices shown on the Unit Price Bid Schedule included in the Contract Documents.
EXHIBIT A.
Article 5. PAYMENT PROCEDURES
CONTRACTOR shall submit Applications for Payment in accordance with the General
Conditions. Applications for Payment will be processed by ENGINEER, as provided in the
General Conditions.
The OWNER shall retain 10% of the amount of each payment until final completion and
acceptance of all work covered by the contract documents. When the work is substantially
complete, the retained amount may be reduced to 5%, at the OWNER'S discretion.
Article 6. INTEREST
If the contract amount of this contract is less than $400,000, no interest will be paid to the
CONTRACTOR on retained money. When the contract amount exceeds $400,000, no interest
will be paid unless required by law.
Article 7. CONTRACTOR'S REPRESENT A nONS
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following
representations:
CONTRACTOR has familiarized himself with the nature and extent of the Contract Documents,
Work, site, locality, and all local conditions and Laws and Regulations that, in any manner, may
affect cost, progress, performance or furnishing of the Work.
CONTRACTOR has obtained and carefully studied (or assumes responsibility for obtaining and
carefully studying) all such examinations, investigations, explorations, tests, reports and studies
in addition to, or supplement, those referred to above, which pertain to the subsurface or physical
conditions at or contiguous to the site or otherwise may affect the cost, progress, performance or
furnishing of the Work as CONTRACTOR considers necessary for the performance or
furnishing of the Work at the Contract Price, within the contract Time and in accordance with the
other terms and conditions of the Contract Documents, and no additional examinations,
investigations, explorations, tests, reports, studies or similar information or data are, or will be,
required by CONTRACTOR for such purposes.
CONTRACTOR has reviewed and checked all information and data shown or indicated on the
Contract Documents with respect to existing Underground Facilities at or contiguous to the site
and assumes responsibility for the accurate location of all Underground Facilities, whether
indicated in the Contract Documents, or not. No additional examinations investigations,
explorations, tests, reports, studies or similar information or data in respect of said Underground
Facilities are, or will be, required by CONTRACTOR in order to perform and furnish the Work
at the Contract Price, within the Contract Time and in accordance with the other terms and
conditions of the Contract Documents.
CONTRACTOR has correlated the results of all such observations, examinations, investigations,
explorations, tests, reports an studies with the terms and conditions of the Contract Documents.
CONTRACTOR has given ENGINEER written notice of all conflicts, errors or discrepancies
that he has discovered in the Contract Documents and the written resolution thereof by
ENGINEER is acceptable to CONTRACTOR.
CONTRACTOR has reviewed and fully agrees to the limitation ofliability provisions included
in the Supplementary Conditions.
CONTRACTOR certifies that they are eligible to be awarded government contracts.
CONTRACTOR also certifies that any agreement entered into with a subcontractor will
contain a clause stating that the subcontractor is eligible to be awarded government contracts.
Article 8. CONTRACT DOCUMENTS
The Contract Documents, which comprise the entire agreement between OWNER and
CONTRACTOR concerning the Work consist of the following:
This Agreement
Bid and Bid Form, Advertisement, and Information or Instruction to Bidders
Performance, Payment Bonds, and Receipt for Payment and Release of Liens
Notice of Award, Notice to Proceed, and Statement of Bidders's Qualifications
General Conditions and modifications thereto, if any, such are included
Specifications prepared or issued by City of Paris Engineering Department, dated July 2006.
Drawings, consisting of sheets numbered 1 through 5, inclusive with each sheet bearing the
following general title: Wastewater Improvements (Pine Mill Road & NE Loop 286)
Addenda numbers N/ A
to
, inclusive.
Documentation submitted by CONTRACTOR prior to Notice of Award, identified as Statement
of Bidders Qualifications.
The following, which may be delivered or issued after the Effective Date of the Agreement and
are not attached hereto:
All Written Amendments, change orders, and other documents amending, modifying, or
supplementing the Contract Documents pursuant to the General Conditions.
There are no Contract Documents other than those listed above in this Article 8. The Contract
Documents may only be amended, modified, or supplemented, as provided in the General
Conditions.
Article 9. MISCELLANEOUS
Terms used in this Agreement that are defined in Article 1 of the General Conditions will have
the meanings indicated in the General Conditions.
No assignment by a party hereto of any rights under or interests in the Contract Documents will
be binding on another party hereto without the written consent ofthe party sought to be bound;
and specifically, but without limitation, monies that may become due and monies that are due,
may not be assigned without such consent (except to the extent that the effect of this restriction
may be limited by law), and unless specifically stated to the contrary in any written consent to an
assignment, no assignment will release or discharge the assignor from any duty or responsibility
under the Contract Documents.
OWNER and CONTRACTOR each binds himself, its partners, successors, assigns, and legal
representatives to the other party hereto, its partners, successors, assigns and legal
representatives in respect of all covenants, agreements and obligations contained in the Contract
Documents.
Article 10. OTHER PROVISIONS
None.
IN WITNESS WHEREOF, OWNER and CONTRACTOR have signed this Agreement in
multiple copies. One counterpart each has been delivered to OWNER, CONTRACTOR and
ENGINEER. All portions of the Contract Documents have been signed or identified by
OWNER and CONTRACTOR or by ENGINEER on their behalf.
This Agreement will be effective on May 14th, 2007.
OWNER: City of Paris
CONTRACTOR: B. Bray Construction Co.,
Inc.
By:
By:
(Corporate Seal)
(Corporate Seal)
Attest:
Attest:
Address for giving notices:
Address for giving notices: