14-Deliberate and act on a Resolution accepting a bid and approving the proposal for reconstruction of S. Collegiate DriveCITY COUNCIL AGENDA ITEM BRIEFING SHEET Submittal Date: Originating Department: Presented By: Agenda Item No.: 06/09/2010 Engineering, Planning Shawn Napier, P.E. Director of Council Date: & Development Engineering, Planning & 14. 06/14/2010 Develo ment RECOMMENDED MOTION: Move to approve a resolution authorizing an agreement for the reconstruction of S. Collegiate Drive to R.K. Hall Construction Co., LTD in the amount of $1,465,740.40 and authorizing the City Manager to negotiate and execute all necessary documents. POLICY ISSUE(S): Contract; Capital Improvement BACKGROUND: The City of Paris received two bids for the reconstruction of S. Collegiate Drive and R.K. Hall Construction Co., LTD was the low bidder for the project. The project will widen the current S. Collegiate Drive and allow it to become a major thoroughfare. Jefferson Road traffic will stop at S. Collegiate Drive after the project is completed. Working in tandem with the City's project, the Texas Department of Transportation (TxDOT) will be reworking the Jefferson Road section (F.M. 1507) to widen it to a three lane section. The City's project is broken into two sections. The north section extends from the bridge over Big Sandy Creek south to the north intersection of Jefferson Road and S. Collegiate. This roadway section will be widened from its current width of approximately 24-feet to a width of 38-feet. The project includes turn lanes into the south parking lot area of Dragon Park and the Love Civic Center. The south section extends fi-om Loop 286 north to the south intersection of Jefferson Road and S. Collegiate. This proposed section will be widened from its current width of approximately 20-feet to a width of 63-feet. The new roadway will include storm sewer pipes to drain the roadway and property to the west of this S. Collegiate Drive section. This proposed storm sewer system is planned to be constructed on the West side of the roadway. A change order will be needed in the near future to help facilitate Right-of-Way (ROW) acquisition. Specifically, one of the property owners on the south section has his property leased to someone to have cows on the property, so a fence will be needed along the entire west side of the south section to replace the existing one in the proposed (ROW). Staff has estimated that we will have approximately $850,000 to $900,000 remaining after construction. The City has options with what to do with the additional funds. However, the bond covenant limits what the money can be used for to making improvements to the frontage access of South Collegiate Drive. Examples of acceptable projects would be to construct the back road into the Police and Court Building, do design work for replacing the bridge, or build a sidewalk from the current Trail de Paris end at the Sports Complex south along S. Collegiate Drive to the Loop. The money could also be placed in the interest & sinking fund and used to help make the related debt payments. To date we have paid TxDOT $300,000 for the advanced funding agreement, Hayter Engineering fees in the amount of 75,219.25, Chalaire Surveying fees in the amount of $11,860.00 plus issuance costs. Staff recommends awarding the bid to R.K. Hall Construction Co., LTD in the amount of $1,465,740.40. City of Paris Revised 2/04/08 BOARD/ COMMISSION RECOMMENDATION: EXHIBITS: Resolution; Bid Tabulation; Aeria] Map ACTION: BUDGET INFO: Bond Fund ❑ Financial Report ❑ Minute Order Expense $1,483,060.00+ ❑ Department Report Z Resolution ❑ P i Budgeted Amt. $2,960,837.00, Net Bond Proceeds resentat on ❑ Ordinance ❑ Public H i ❑ O h yTD Actual $493,859.25 ear ng t er Acct. Name S. Collegiate Drive Reconstruction Acct. Number 14-0350-46-00, 14-0351-46-00 r 15cAL 1V OTES: REVIEWED AND APPROVED BY: Z Administration Z City Clerk ❑ Community Development ❑ Municipal Court ❑ Legal ❑ Library ❑ Police ❑ EMS/IT ❑ Finance ❑ Fire 0 Eng./Public Works ❑ Utilities City of Paris Revised 2/04/08 1 IL - DRAFT attorney\reswork\current\S. Collegiate Ext Awd & Contract Res 2010 RESOLUTION NO. A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PARIS, TEXAS, APPROVING THE BID AND AWARDING THE CONTRACT FOR THE SOUTH COLLEGIATE DRIVE RECONSTRUCTION - SOUTH LOOP 286 TO BIG SANDY CREEK TO R. K. HALL COIVSTRUCTION COMPANY, LTD, THE LOWEST RESPONSIBLE BIDDER; MAKING OTHER FINDINGS AND PROVISIONS RELATED TO THE SUBJECT; AND DECLARING AN EFFECTIVE DATE. WHEREAS, the City Council of the City of Paris did heretofore, advertise for bids for furnishing plant, labor, materials, and equipment, and for performing all work required for the "South Collegiate Drive Reconstruction - South Loop 286 to Big Sandy Creek Project" which bids were received until 3:00 o'clock p.m. Wednesday, the 2nd day of June, 2010; and, WHEREAS, the lowest responsible bid for all phases of the project in the amount of $1,465,740.40 was made by R. K. Hall Construction Company, Ltd, 1540 NW Loop 286, Paris, Texas 75460, and the contract should be awarded to R. K. Hall Construction Company, Ltd in accordance with the unit prices bid and the other terms and conditions set out in the bid documents attached hereto as Exhibit A; and, NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PARIS, TEXAS: Section 1. That the findings set out in the preamble of this resolution are hereby in all things approved. Section 2. That the bid of $1,465,740.40 from R. K. Hall Construction Company, Ltd, 1540 NW Loop 286, Paris, Texas for the "South Collegiate Drive Reconstruction - South Loop 286 to Big Sandy Creek Project" is hereby accepted as the lowest responsible bid which provides the best value to the City and the contract for this project is hereby let conditioned upon said contractor meeting all of the terms and specifications included in the agreement and bid documents attached hereto as Exhibit A. Section 3. That the City. Manager be and he is hereby authorized and directed to execute on behalf of the City of Paris an Agreement for the reconstruction and alignment of South Collegiate Drive walks with R. K. Hall Construction Company, Ltd, in the form attached hereto and incorporated herein as Exhibit A. Section 4. That this resolution shall be effective from and after its date of passage. PASSED AND APPROVED this 28th day of June, 2010. ATTEST: Janice Ellis, City Clerk APPROVED AS TO FORM: Will Biard, Mayor 12 W. Kent McIlyar, City Attorney i ~ BID PROJECT IDENTIFICATION: CONTRA.CT IDENTIFTCATION AND NUMBER: THIS BID IS SUBMITTED TO: South Collegiate Drive Reconstruction HEI # 180042 City of Paris 1. The undersigned BIDDER proposes and agrees, if this Bid is accepted, to enter into an agreement with OWNER in the form included in the Contract Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Contract Price and within the Contract Time indicated in this Bid and in Accordance with the other ternis and conditions of the Contract Documents. 2. BIDDER accepts all of the terms and conditions of the Advertisement or Invitation to Bid and Instructions to Bidders, including, without limitation, those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for ninety (90) days after the day of Bid opening. BIDDER will sign and submit the Agreement with the Bonds and other documents required by the Bidding Requirements within fifteen (15) days after the date of OWiNER'S Notice af Award. 3. In submitting this Bid, BIDDER represents, as more fully set forth in the Agreement, that: (a) BIDDER has examined copies of all the Bidding Documents and of the following Addenda, receipt of all which is hereby acknowledged: Number J11-- Date -S-3~2 0/0 (b) BIDDER has familiarized itself with the nature and extent of the Contract Documents, Work, site, locality, and all local conditions and Laws and Regulations that in any manner may affect cost, progress, perform.ance or furnishing of the Wozk. (c) BIDDER has obtained and carefully studied (or assumes responsibility for obtaining and carefully studying) all such examinations, investigations, explorations, tests and studies which pertain to the subsurface or physical ~ 11 ExHlBfT.,8.. 129 conditions at the site or otherwise may affect the cost, progress,- performance or furnishing of the Work as BTDDER considers necessary for the performance ar furnishing the Work at the Contract Price, within the Contract Time and in accordance with the other terms and conditions of the Contract Documents, and no additional examinations, investigations, explorations, tests, reports or similar information or data are or will be required by BIDDER for such purposes. (d) BIDDER has reviewed and checked ali information and data shown or indicated on the Contract Documents with respect to existing Underground Facilities at or contiguous to the site and assumes responsi6ility for the accurate location of any and all Underground Facilities. No additional examinations, investigations, explorations, tests, reports or similar information or data in respect of said Underground Facilities are or will be required by BIDDER in order to perform and furnish the Work at the Contract Price, within the Contract Time and in accordance with the other terms and conditions of the Contract Documents, including specifically the provisions of Paragraph 4.04 of the General Conditions. (e) BTDDER has correlated the results of all such observations, examinations, investigations, explorations, tests, reports and studies with the terms and conditions of the Contract Documents. BIDDER has given ENGINEER written notice of all conflicts, errors or discrepancies that it has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to BIDDER. (g) This Bid is genuine and not made in the interest of or on behalf of any undisclosed person, firm or corporation and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; BIDDER has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; BIDDER has not solicited or induced any person, firm or corporation to refrain from bidding; and BIDDER has nat sought by collusion to obtain for itself any advantage over any other Bidder or over OWNER. , iop - I a~. -v.v-a i .cJ - - ~ba-cc. .'.b - 4_ N0. i. 2_ 3. 4. 5. 6. s. 9. 10. 11. 12_ 13. 14. 1s. 16. 17. zs. 19. 20. BIDDER wi11 complete the Work for the following price(s): UNIT PRICE SCHEDULE E5TIMATED DESCRIPTION QUANTITY Mobilization. I LS 60" HDPE storm sewex. 1,255 LF 48" HDPE storm sewer. 12 LF 36" HDPE stornl sewer. 12 LF 30" HDPE stomi sewer. 698 LF 24" HDkE storm sewer. 192 LF 18" HDPE storm setiver. 397 LF 66" RCP stozm sewer. 8 LF 4' x 2' RCl' boZ culvert, 139 LF 24" RCP stonm sewer. 30 LF 21" RCP storm sewer. 36 LF 10` Recessed ialet. , 11 EA SETP-PD Headwall (for 66"). 1 EA SETP-PD Headwall (for 24"). 2 EA SETP-PD Headwall (foc 21"). 2 EA Inlet dovvnstream of detention pond. 1 EA 36" CH-FW-O Headwall. 1 EA 48" CH-FW-O Headwall. I EA 4' x 4' Type H inlet with erate. 2 EA Headwall and concrete channel rernoval downstream of detention pond. 1 LS UNIT TOTAL PRJCE PRICE $ 03 000' $ /c)3, o00 $ $ ! 1S ? b~~ =o Z,lC~o: s )15~ S 13d'" r $ ~ 3 $ / 7 Y D a s VGb ou $ ~b/73Z s $ 7S~ $ 71~ 77S o0 V o g ~75 ao ~ Z zov $ / O~ $ /e,070~ $ y3 ~ $ ~290 'o $ 39 ~ /yzS~ 60 $ 0700 $ Zg, 7vv °o $ 77Sv $ -7, c)._.. $ o0 vo $ 6/ ov ~ 36-00 ~G $ 3S00 ~i Z700c-" $ Z-7~0 Soo°= s .~yoo~o 09ee) - $ $ $ $ s S W "a $ $ gODc~i $ ~o0d G~ 13 rIC~n C! lU UJ:U..~cf flC`J'l.t'7- CfIs li1CC1 111s l, lt. 21. Lime material. 542 TN 22. 8" Lime stabilized subbase (8%). 21,515 SY 23. S" Asphalt (Type B) base. 16;915 SY 24. 2" Asphalt (Type D) wearing surface. 15,664 SY 25. 10" Concrete paving. 4,178 SY 26. Curb and gutter. 3,510 LF 27. Pavement markings. 1 LS 28. Relocation existing fire hydrant. 1 EA 29. 10 x 6" Tapping sleeve and valve. 1 EA 30. 10 Y 8" Tapping sleeve and valve. 1 EA. 31. 8" x S" Tapping sleeve and valve. 1 EA 32. Ductile iron fittings. 0.14 TN 33. 8" C-900 DR 18 PVC water main. 293 LF 34. Standard 4' diameter rnlnhole (0'-6'). 2 EA 35. Additional ma.nhole depth (over 6'). 4.5 VF 36. SDR 35 PVC gravity sewer. 325 LF 37. 0'-5' Trenching, backf'ill, and cleanup. 212 LF 38. 5'4' Trenehing, backf ll, and cleanup. 53 LF 39. Trench protection. 2,317 LF 40. 12" Road bore. 60 LF 41. 12" Steel encasement - road bore. 110 LF 42. 14" Road bore. 60 LF 43. 14" Steel encasement - road bore. 110 LF r•- ~ ly9 s-' s L/ oZy U 777 ~ 0 ~ r s sZ U s zi 2s6 ~ s 13%- s S 630 s /4-5~00 $ 2 yy ~ ~vy ~ ~ZU~~ $ ao= $ ~ pa s Z~ba~ s zv $~pZ-- ~ -7 30 ~ Z3~2 $ ~7 3r $ 1 5q7 ~ $ J/ so $ 6D~ So O~ 2317=- $ lI`~' $ C~~yv $ 13~ ~ > $ ~~oo = ~ 14 . 3.32 2 1-1 d7-1 G( lU L1.7 ; UZ) d 1-1Gl7-1 IiCI GIIS 111CC1 liis 111- JU.~ t V~+...+v..~ I 44. 12" Steel encasement - open cut. 45. 14" Steel encasement - open cut. 46. Subgrade mitigation. 47. Erosion protection. 48. Stormwater pollution prevention plan. 49. Traff`ic control plan. 50. Unclassified elcavation. 51. Embankment material. TOTAL BID: TVV R- {f''xt?'40 ADDITIVE ALT'ERIVATE: A 1. 60" RCP storm sewer. A2. 48" RCP stozm sewer_ A3. 36" RCP storm sewer. A4. 30" RCP storm seiver. AS. 24" RCP storm sewer. A6. 18" RCP storm sewer. TOTA L ADDITII'E AL?'ERN/,fJ,TE.• /-u~ /~✓Nl1P'Ef~ ~tIJ~NT Y ~AK' O TG10~5l1roQ r- I 73 LF 73 LF ~ $ 10 CY ~ $ 4,040 LF $ y y yy ~G 1 LS $ 1 LS ~ $ o00 $ 000 - 5,660 CY $ ~ ~ ~ s_ 2:578 cY au2 ftDS) ,-f A1~Y C-fAY-75 IG S) 1,255 LF $ /So ~ /~K 2<Sd ~ 12LF $ / 7 0 12 z,F $ d = 698 LF $ 192 LF $ 9'S'- $ l~7yo 397 LF $17sr~ (FI^~ (USE TVORDS) v 4Mt1Z~" DEDUCTIVE ALTERM4 TE.• D 1. 60" HDPE storm sewer. D2. 48" FIDPE storm sewer. D3, 36" HDPE storm sewer. D4. 30" HDPE storm sewer. 1;255 LF 12 LP 12 LF 698 LF 15 1 J3 1'IdZJ C.! lU U0 : VOtl tla~l.cr~ CIlsiilcal ti1fo -<<+ D5. 24" HDPE storm sewez. D6. 18" HDPE storni sewez. 192 LF 397 LF ~ vr $ 7S~ r. - 17 ~j 7" -5' ---r-- TOTAL DEDUCTIVE .4LTER ~stTE: ~sA~.x~ (USE WORDS) (FIGURES) 5. BIDDER agrees tha# the Work will be substantially com.pleted and ready for fina] payment vvithin 240 calendar days after the date when the Contract Time cammences to run, as provided in the Creneral Conditions. BIDDER accepts the provisions of the Agreement as to S500 per calendar day liquidated darnages in the event of failure to complete the Work on time. b. The foilowing dacuments are attached to and made a condition of this BID: (a) Required Bid Security in the form of ( t(~ a Comnlunications concerning this Bid shall be addressed to the address of BIDDER indicated below. 8. The terms in this Bid, which are defined in the General Conditions of the Construction Contract, included as part of the Contract Documents have the meanings assigned to them in the General Conditions. r--~ SUBMITTED on oN~- ~i- ~ Za~.~__• % Of the above total - Base Bid, $ is for materials actually incoiporatec3 in the Work, and v is foz aIl other costs. ~ ya J, yb ,5/ -710 15a ~ i ~ IF BIDDER IS: An Individual: By doing business as . Business Address: Phone Number: **~***********~*~x********~*************~*********x~~x****~*~*******~*~*:~******~* A Partnership: By 2,14YR(U- oMSTBUGi e~ T (Seal) (Name of Firm) (GeneraI Partner's Printed Name nd Signature) Business Address: /SYo N.vS/. G0o ~ ZA 'W P- 's {27x ? SY6o Phone Iti'umber: No3~ 77g N' b'88a A Corporation: Name of Corporation: , State of Incorporation: By (Printed Name of Person Authorized to Sign and Signature) (Title) Attest: Business Address: Phone Number: *~*******~~****~~~***~x****~******~***~*~*~x**~***~********~*~***~*~:*~********~* A Joint Venture: By (Printed Name and Signature) Address: Phone: By (Printed Name and Signature) Address: Phone: (Each joint venturer must sign. The manner of signing for each individual, partnership and corporation that is a party to the joint venture should be in the manner indicated above.) girli LUU (Individual's Printed Name and Signature) eal) (Printed Name and Signature of Secretary) Corporate Seal) 16 i~t_J Bid Bond ' SURETY AEPARTMENT Conforms with the American Institute of Architects, A.I.A Documents No. A-310 KNOW ALL MEN BY THESE PRESENTS, That we, R. K. Halt Construction Ltd, as Principal hereinafter called the Principai, and Travelers Casualtv and Surety Comaanv of America a corporation created and existinb under the laws of the State of Connecticut whose principal office is in Hartford as Surety, hereinafter called the Surety> are held and firmly bound unto Citv of Paris as Obligee, hereinafter called the Obligee, in the sum of Five Percent of the Greatest Amount Bid Dollars ($5% GAB) for the payment of which sum, well and truly to be made, the said Principal and the said Surety, bind ourselves, our heirs, executors, admiristrators, successors and assigns, jointly and severally, firmly by these presents Whereas, tlie Principal has submitted a bid for Reconstruction of 3,229 If of S. Collegiate Drive NO W, TI-lEREFORE, if the Obligee shatl accept the bid of the Principal and the Principal shall enter into a concract with the Obligee in accordance with the terms of such bid, and give such bond or bonds as may be speciFied in the bidding or contracc documents with good and sufticient surety for the faithful performance of sueh contraet and for the prompt payment of labor and material furnished in the prosecution thereof, or in the event of the failure of the Principal to enter such contract and give such bond or bonds, if the Principal sha(1 pay to the Obligee the difference not to exceed ihe penalty hereof between the amount specified in said bid and such larger amount for which the Obligee may in good faith contract with another party to perform the work covered by said bid, then this obligation shall be nnll and void, otherwise to remain in full force and effect Sijned and sealed this 2nd day of June, 2010 R. K. Hail Constrvction, Ltd. (Principal BY W - (Sc:.Ai,) Travelers Casa It and Suret Com an of America Surety) t By (SEAL) chard . aiker Attomey-in-fact JLJ~ ~ - - - - „ WAflNING: THIS POb'VER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER . ~ 1"RbVELERS J Atrorney-In Fact No. 220749 POWER QF ATTORNEY Farmington Casualty Company Fidelity and Guaranty Insurance Company Fidelity and Guaranty Insurance Undenvriters, lnc. Seabosrd Surety Company St. Paul Fire and Nlarine Insurance Company St. Paul Guardian Insurance Company SL Paul Mercury Insurance Company Travelers Casuatty and 5umty Company Travelers Casualty and Surety Company ot America United States Fidelity and Guaranty Companv Certifcate No. 003046246 KNOW ALL N'IEN BY THESE PRESENTS: T'ha[ Seaboard Surzty Company is a corporation dui}' organized under Ihe laws of the State of \ew York, [hat St. Paul Fire and Ivlarine Insurance Company, St. Paul Guardian Insurance Compam and St. Paul Mercury Insurance Compa-iy are c(irporations duty or-anized under thz laws nf the S[ate of blinnesota, that Farmington Casualty Company, Travelers Casualty and Surety Compan}', and Travelers CasuaIty and Surery Company of .4merica are carporatiols duly organized under the laws of the State of Connecueut, that United Stutes Fidelity and Guaranty Company is a corpora[ion duly organized undi:r thr la+vs of the State of Maryland, that Fidelity and Guazanry Insurance Company is a corPoration duly organized undcr ttie laws of the Sta[e of lowa, and that Fidelitv and Guaranty Insurance Undenvriters, Ine. is a cocporation duty organized nnder [he laws oF the State of Wisconsin (hereir, collectively called the "Companies"). and chm the Companizs do hereby make, constimte and appoint Richard W. Daiker, Tony Fierro, Johnny Moss, and Jay Jordan of [he Ciry o: it Stnte oF Tgxas their Irue and lawful Atturr,cyf:)-in-Ft:c[. each in their stparate caplCll4' It I11QfC (h:lR Qf10 1S t18Rizd iI70V0, to siLn, erecute, senl und acknowledae any and all bonds, recugmzances, conditional undertakings and othor writing; ohligaton• in the nature thereof on behalf oF the Companies ir. their business o( guaranteeing the fidcliry of persons, euaranteeine the pertormancr of conirucis and executing ar ouaranteeing bonds and undertakings reyu:reJ or pecmitted in any aetions or procaedings altowed by law. ~ IN 1V1TNESS WHBREOF, the Companies have cawed this instrument w 6e signed and their corporate seals to be hercto affixed, this 3fd Lk,) Ot June 2009 Farmingcon Casualty Company St. Paul Guardian Insurancc Company Fideliry and Guaranty Iruorance Cump:my St. Puul Ntercury lnsurance Company Fidelity and Cuaranty Insurance Underµriters, lnc. Travelers Casualty and Surety Company Seaboard 5urety Company Travelers Casualty and Surety Companv of Americ:i SL Paul Fire and hlarine Insurancc Company United States Fidelity and Guaranty Company r ~r.su~ su~ry .,*c a O*N !k ~ J„s aN c fp J~, ' \ •~..;SU p~. .~!'Vq t J~~ O o ~yp Wµ)4~ F~}TY.{"V n ol C:c'~ br~ORtOY~rf~_r,~ a Z~~ a ~ 1977 g ~~rm i927 .t~.. ;m z: W wurwRO. 1896 ~ 1951 s SE AL io~l ~ ca+~n. g ww+. e N „ 1 D ~ ~q~6 ~ ~1STRL;~i w o M1. S. A~ s•._. t 1 ~a Ah ' S[ate of Connecticut Citv of Hanfnrd sti. By: Gcore ' T'hompson, enior ice Presidznt Ou thia the 3rd day OfJune , 2009 , before me personally appeared George W. Thompson, who acknuwlcdged himself to be the Senior Vice President oF Farmin;ton Casualry Coinpany, Fidelity and Guaranty Insurance Company, Fidelity and Guarinty Insurance Underwriters. [nc., Senboard Surety Cnmpany, St. Paul Fire and Marine Insurance Company. St. Paul Guardian Insuranee Company, St. Paul Mercury Insurance Company, Travelrn Casualt~ and Surety Canpanp, Travelers Casualty and Surery Company of America, and United States Fidelity and Guaranty Company, and that he. as such, bein., authonzed so to do, esecuted the fore~oing instrument far the purposes tlierein contained by signing on bchalf of the corporations by himself as a duly authorizeci officer. ~G,Ter, , Ln NN`itness Whereaf, 1 hereunto set my hanJ and official seal. ~I My Commissinn expires the 30th day of June, 2011. cl p~L~G * 58440-5-07 Printed in U.S.A. Muric C. Tetrcault, Yntary Pubiic a A WARNING: TH1S POWER Of ATTORNEY IS INVALID WiTHOUT THE RED BORDER ~ r n " ~L J f HAYTER ENGINEERING, INC. CONSULTANTS PLANNERS ENGINEERS June 17, 2010 Mr. Kevin Carruth, City Manager City of Paris 135 SE ls` Street Paris, TX 75460 4445 S.E. LOOP 286 PARIS, TEXAS 75460 (903) 785-0303 FAX (903) 785-0308 REFERENCE: South Collegiate Drive Reconstruction - South Loop 286 to Big Sandy Creek HEI # 180042-280 Dear Mr. Carruth: On June 2, 2010, the City of Paris received bids for the above referenced project. Two bids were received, with the lowest being that of R.K. Hall Construction Co., LTD in the base bid amount of $1,484,412.40, additive alternate of $272,829.00, and deductive alternate of $291,501.00. A bid tabulation is attached for your review. We have verified the mathematical accuracy and completeness of both bids, and have verified that the bonding company is licensed in Texas. The low bid appeazs to conform to the contract document requirements. Based upon the Statement of Bidder's Qualifications, we believe the low bidder to be responsive and responsible. We therefore recommend award of this project to R.K. Hall Construction Co., LTD in the base bid amount of $1,484,412.40,plus additive alternate of $272,829.00, and less deductive alternate of $291,501.00, for a total award of $1,465,740.40. If the City concurs with this recommendation, please sign the attached three original Notice of Award forms. Upon signing, please return all three originals to this office for further execution. Sincerely, o F r4~ HAYTER ENGINEERING, INC. Michael J. an, P.E. DONNAN 7%, Project Manager 65217 JEnclosures •.~`aNAt cc: Shawn Napier, P.E., City Engineer Service Since 1957 TBPE F-000315 1 J .J 8id ? abulation City of Paris South Collegiate Drive Reconstruction South Loop 286 to Big Sandy Creek HEI #180042 ~ N ~IAAfl YY116 3:00 p.m. R.K. Hall Richard Drake Construction, LTD Construction Co., LP EsUmated Unit Total Unit Total Item Descri tion Quanti Price Price Price Price 1 Mobilization 1 LS 103,000.00 103,000.00 152,856.00 152,856.00 2 6 0" HDPE storm sewer 1,255 LF 156.00 195,780.00 132.90 166,789.50 3 4 8" HDPE storm sewer 12 LF 180.00 2,160.00 116.00 1,392.00 4 36" HDPE storm sewer 12 LF 115.00 1,380.00 63.40 760.80 5 30" HDPE storm sewer 698 LF 63.00 43,974.00 39.80 27,780.40 6 24" HDPE storm sewer 192 LF 96.00 18,432.00 27.50 5,280.00 7 18" HDPE storm sewer " 397 LF 8 LF 75.00 00 275 29,775.00 200.00 2 14.58 349.00 5,788.26 2,792.00 8 9 RCP storm sewer 66 4' x 2' RCP box culvert 139 LF . 130.00 , 18,070.00 183.00 25,437.00 10 24" RCP storm sewer 30 LF 43.00 1,290.00 51.40 1,542.00 11 21" RCP storm sewer 36 LF 39.60 1,425.60 42.80 1,540.80 12 10' Recessed inlet 11 EA 2,700.00 29,700.00 3,580.00 39,380.00 13 SETP-PD Headwail (for 66" 1 EA 7,750.00 7,750.00 2,140.00 2,140.00 14 SETP-PDHeadwall for24") 2EA 900.00 1,800.00 680.00 1,360.00 15 SETP-PD Headwall for 21" 2 EA 800.00 1,600.00 690.00 1,380.00 16 Inlet downstream of detention nd 1 EA 31500.00 3,500.00 2,800.00 2,800.00 17 36" CH-FW-0 Headwall 1 EA 2,700.00 2,700.00 5,240.00 5,240.00 18 48" CH-FW-0 Headwall 1 EA 5,400.00 5,400.00 8,940.00 8,940.00 19 4' x 4' T e H inlet with rate 2 EA 2,900.00 5,800.00 5,580.00 11,160.00 Headwall and concrete channei removal 20 downstream of detention ond 1 LS 8,000.00 8,000.00 1,960.00 1,960.00 21 Lime material 542 TN 149.50 81,029.00 152.10 82,438.20 22 8" Lime stabilized subbase 8% 21,515 SY 1.80 38,727.00 2.35 50,560.25 23 8" As halt T e B base 16,915 SY 22.00 372,130.00 25.45 430,486.75 24 2" As halt T e D wearin surface 15,664 SY 6.20 97,116.80 6.75 105,732.00 25 10" Concrete avin 4,178 SY 52.00 217,256.00 56.90 237,728.20 26 Curb and utter 3,510 LF 13.00 45,630.00 18.48 64,864.80 27 Pavement markin s 1 LS 12,500.00 12,500.00 13,200.00 13,200.00 26 Relocation existin fire h drant 1 EA 1,144.00 1,144.00 1,185.00 1,185.00 29 10" x 6" Ta in s sleeve and valve 1 EA 2,444.00 2,444.00 2,155.00 2,155.00 30 10" x 8" Ta in sleeve and valve 1 EA 2,886.00 2,886.00 2,720.00 2,720.00 31 8" x 8" Ta in sleeve and valve 1 EA 2,808.00 2,808.00 2,645.00 2,645.00 32 Ductile iron fittin s 0.14 TN 3,120.00 436.80 5,900.00 826.00 33 8" C-900 DR 18 PVC water main 293 LF 19.00 5,567.00 26.45 7,749.85 34 Standard 4' diameter manhole 0-6' 2 EA 2,860.00 5,720.00 4,640.00 9,680.00 35 Additionai manhole de th over 6' 4.5 VF 156.00 702.00 336.00 1,512.00 36 8" SDR 35 PVC ravi sewer 325 LF 7.30 2,372.50 19.60 6,370.00 37 01-5' Trenchin 212 LF 7.30 1,547.60 11.00 2,332.00 38 5'-8' Trenchin 53 LF 11.50 609.50 15.00 795.00 39 Trench rotection 2,317 LF 1.00 2,317.00 2.80 6,487.60 40 12" Road bore 60 LF 114.00 6,840.00 115.00 6,900.00 41 12" Steel encasement - road bore 110 LF 62.00 6,820.00 40.40 4,444.00 42 14" Road bore 60 LF 130.00 7,800.00 67.20 4,032.00 43 14" Steel encasement - road bore 110 LF 64.50 7,095.00 41.80 4,598.00 44 12" Steel encasement - o en cut 73 LF 78.00 5,694.00 48.70 3,555.10 45 14" Steel encasement - o n cut 73 lF 80.00 5,840.00 51.80 3,781.40 46 Sub rade miti ation 10 CY 14.00 140.00 35.00 350.OC 47 Erosion rotection 4,040 LF 1.10 4,444.00 4.40 17 776.OC 48 Stormwater ollution prevention lan 1 LS 800.00 800.00 7,200.00 7,200.0( 49 Traffic control lan 1 LS 12,000.00 12,000.00 27,500.00 27,500.0( 50 Unclassified excavation 5,660 CY 7.65 43,299.00 5.00 28,300.0( 51 Embankment material 2,578 CY 2.70 6,960.60 9.65 25,393.3( TOTAL BID $1,484,412.40 $1,629,616.21 A1 Additive Attemate: 60" RCP storm sewer 1,255 LF 150.00 188,250.00 212.40 266,562.0( A2 48" RCP storm sewer 12 LF 145.00 1,740.00 134.00 1,608A( A3 36" RCP storm sewer 12 LF 110.00 1,320.00 83.40 1.000.8( A4 30" RCP storm sewer 698 LF 48.00 33,504.00 .n - nn 55.75 .n nn 38,913.51 O 4 R7 AI -i1J•~ zr + , Y.' Li~ 1 '1 'J SOUTH PHASE OF PROJECT hYa f ~ ~1, .L ° yj i~ 3 ' • n 5 7Y, > y~ly .a y~N'''~,.'4a ~ ~r.. y«t ~g~'t?.. ~~~y;.'~"`~'•:, asF~ * ay': 7'* „E 9 / Y(c ~~'nr.~~ yf ~ , } 4► y~ w F x~ ~ 'Ty-wY.~ .''~3 4 ts- ~a ,f ~e * ti ~S ~ • ~ ~ t r.•+~r 1 tg wf f ~ .4 ~ Jl I ~ '4Y ~ . t~wa~1'.~~ ► ~l y ~ ~ c .1'a. t ~ . ~y.g~ .;tn ► 1 ' ~ ~j1 .';'z a ly; ta i . f ~„';Y r : # : t : i ~..t +'~'Y.~ '7 r ,;.t~~ : .~+~tS-~`t p 41 V y', i h ,.~.e s ..,s .t_ i • *P f ~Y 'y, 4 ~ + ° a~ x ' ~ i ~ ~i . ~ 'M ~ . ~ ~ F ~ ~ j.s'~.t~` ' . v a' ~ : ~ ~ . S r'~~ C 3^ f.:~ ~2.4.~^.~k ~ ~ r" xa~ ~ t ~A : f 'a .,,i'lI ~ ~/st ~ ~ ~'`t. t `~i . '1t y. ~ . . ~ r { ~ r.'~Ry~ ~ D~. *r' 4 k ~ . . ~ .i Y „t,,~*`. , . . ~ . . ~ 1 y 1 ~'1" ~ ~ ' 'kro r • ,'xi ~ a. 'F ~ yt : a., ~ .s ~4 ,'~~y "''-%:2 ~ a'✓ ya ~ -~I i~ - i a a, ~T',."+e.. ~ ~;yf x+'l~ t #:k~•~,,~ s xy,,~~,a.a~,. _ to~ ~,r ~ ~ ~ 'Mt►'„y 4 il'~,~ ~ ~S yii ~,~~T '1`+~f',t y+ y . ~ s h.• ~s '~t~~ t '9~ ~f , 'l~~ j.v~~ •'~V g~ 'y ~ ~ ~"S~! ~ - ~ rf c~ ' ~''s^ . ~pk ~ wz 'va. a .s .~t ~ `Y~'M~>Y:.# ,~',r F~~: i{ b'i,.~ 'it - X r w~ 1. Z. yp~ .f.'7~ ' .-yr~" f„ ''#~'x" ;'+Y~•. t.,? ~t U;`~,''x . u • ~ ' • X';x0, ~ . -'c•`t- y6..1.. '7t . s,~ } r . 1 . , . ~ y. y ~ ~i'.. t.. ~ . ~ t 4 ~ i a ,`✓~,i ~ F.'~~ ~ ± ~ ~ x t ~ ~ :w~ u ~...31:~ ~.,y, h ~ *1.. ♦ ~ '~.M' , C'. ~1T~ ~ a4'i ~ ; a ,y , Cx S~ ~ ~ ~ ~i 1~ ? ' y~. ~l b y R f~ir . + as x~ Y i' r x N ~ 1 W, ~ ~ •te` e ?r°'< • ~ ..L. M `w,V.. . . . , ..2 Loop~ V ~ . .Y - 6 • 44~"'; ~ i 141