2012-027 RES APPROVE CHANGE ORDER NO ONE TO CONTRACT BETWEEN BOBBY SMALLWOOD CONSTRUCTION AND COP FOR CLARKSVILLE STREET DOWNTOWN SIDEWALK PROJECTRESOLUTION NO. 2012-027 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PARIS, TEXAS, APPROVING CHANGE ORDER NO. ONE TO THE CONTRACT BETWEEN BOBBY SMALLWOOD CONSTRUCTION CO., IIVC. A1VD THE CITY OF PARIS, FOR CLARKSVILLE STREET DOWIVTOWN SIDEWALK PROJECT; MAKING OTHER FINDINGS AND PROVISIONS RELATED TO THE SUBJECT; AND DECLARING AN EFFECTIVE DATE. WHEREAS, on March 12 2012, the City Council of the City of Paris passed Resolution No. 2012-024, awarding the contract for the Clarksville Street Downtown Sidewalk Project to Bobby Smallwood Construction Co., Inc. of Paris, Texas; and, WHEREAS, the City Engineer, Shawn Napier, acting as project engineer, recommends the amendment of the contract for said project based on the actual materials to be used, and providing for a net decrease amount of $17,479.25 in the contract price, for a revised contract price of $219,527.37, the contract time will not be increased. The date for completion of all work will be June 26, 2012; and, WHEREAS, Change Order No. One attached hereto as Exhibit "A", should in all things, be approved, and the Interim City Manager should be authorized to execute the necessary documents. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PARIS, TEXAS: Section 1. That the findings set out in the preamble of this resolution are hereby in all things approved. Section 2. That Change Order No. One to the Contract between Bobby Smallwood Construction Co., Inc. and the City of Paris for the Clarksville Street Downtown Sidewalk Project, attached hereto as Exhibit "A", providing for a net decrease of $17,479.25 in the contract price, for an amended total contract price of $219,527.37, and no increase in contract time be, and the same is hereby approved. Section 3. That the Interim City Manager be, and he is hereby, authorized and directed to execute, on behalf of the City of Paris, any necessary documents, upon the terms and conditions in Exhibit "A", attached hereto. Section 4. That this resolution shall be effective immediately upon passage. PASSED AND APPROVED this 26th day of March, 2012. ATTEST: J ce Ellis, City Clerk APPROVED AS TO FORM: ~ W. Kent McIlya , ' Attorney 1103 Texas Department of Rural Affairs Construction Contract Change Order Approval Request ~ R Owner (contractor Locaifty): Contract For (project descr;pt►on): Date: March 26, 2012 City of Paris RE-BID Downtown Sidewalk P.O. Box 9037 Replacement - Clarksville St. Project No.: TCF #710222 Paris, TX 75461 Phone #:903-785-7511 Contractor: Engineer: TxCDBG Contract No Bobby Smaliwood Construction Hayter Engineering, Inc. . TCF #710222 1795 NE 17'' 4445 SE Loop 286 Paris, TX 75460 Paris, TX 75460 Change Order No.: One (1) Agreement Date: 3/12/12 Phone 903-785-0303 Phone 903-727-2350 En ineer's Pro'ect No.: 180050 You are hereb re uested to com I with the followin chan es from the contrad lans and s ecifications: Item Description of Changes-Quantities, Units, Unit Prices, Decrease in Increase in No. Chan e in Com letion Scheduled, Etc. Contract Price Contract Price 4 Delete resurfacing existing sidewalk, (351) SF @ ($13,601.25) $38.75/SF = ($13,601.25) 8 Delete Single 8" trench drain, (9) EA @$2,792.00/EA = ($25,128.00) ($25,128.00) 8 Add single one-piece 8" trench drain fabricated by North $22,500.00 Texas Fabrication, 9 EA @ $2,500.00/EA = $22,500.00 9 Delete Double 8" trench drain, (1) EA @$6,250.00/EA = ($6,250.00) ($6,250.00) 9 Add double one-piece 8" trench drain fabricated by North $5,000.00 Texas Fabrication, 1 EA @ $5,000.00/EA= $5,000.00 TOTAL (a17,479.25) Chan e in Contract Price Chan e in Contract Time Ori inaf Contract Price: $237,006.62 Ori inal Contract Time: 105 da s Previous Change Order(s) Net Change From Previous No. to No. $0.00 Chan e Orders 0 da s Contract Price Prior to Contract Time Prior to this Chan e Order $237,006.62 this Chan e Order 105 da s Net Decrease of Net Increase/Decrease of this Chan e Order $17,47925 this Chan e Order 0 da s Contract Pnce With all Contract Time With all A roved Chan e Orders $219,527.37 A roved Chan e Orders 105 da s Cumulative % Chan e in Contract Price: 7.38% BG reimbursement of costs annroved bv this ch anae nrripr ic ciihipr-r +nn.,.,.....-l ►.,,.k., nsr. - . ~ . - APPROVED: I ACCEPTED: _ I BY: . ) I OWNER (Authorized Signature) Date: By: CONTRACTOR (Authorized Signature) Date: EXHIBIT ~~1 Grant Recipient: City of Paris JUSTIFICATION FOR CHANGE TxCDBG Contract No.: 710222 Change Order No. One (1) 1. Wili this Change Order increase or decrease the number of beneficiaries? ❑ Increase ❑ Decrease x No Change If there is a change, how many beneficiaries will be affected? Total UM 2. Effect of this change on scope of work: O Increase ❑ Decrease x No Change 3. Effect on operation and maintenance costs: ❑ Increase ❑ Decrease x No Change 4. Are all prices in the change order dependent upon unit prices found in the original bid? ❑ Yes x No If "No", explain: Trench drains will be manufactured as one piece instead of 2' sections for cost savings. 5. Will this change be completed within the contract period? x Yes ❑ No If °No", expected completion date: (completion date) 6. Has this change created new circumstances or environmental conditions which may affect the project's impact, such as concealed or unexpected conditions discovered during actual construction? ❑ Yes x No If "Yes", is an Environmental Re-assessment required? ❑ Yes ❑ No 7. Is the Texas Commission on Environmental Quality (TCEQ) clearance still valid? x Yes ❑ No 8. Is the TCEQ permit approval still valid? (sewer projects only) ❑ Yes ❑ No 9. Are the handicapped access requirements/approval still valid (if applicable)? x Yes ❑ No 10. Are other TxCDBG contractual special condition clearance still valid? x Yes ❑ No (If no, specify): Notice: ` Generally, a cumulative change in the contract price in excess of 25% cannot be approved. " Generally, items not included or identifying unit costs in the original bid documents cannot be approved as change order items.