1956 RES CITY COUNCIL IN RES NO 1675 PASSED ON 24TH DAY OF MARCH 1975 ADOPTED PROJECT SCHEDULE FOR INFILTRATION/INFLOW PROJECTRESOLUTION N0. 1956 ,
WHEREAS, the City Council oE the City of Paris did in
Resolution No. 1675, passed on the 24th day of March, 1975, adopt a
project schedule for the infiltration/inflow project which is in pro-
gress, with the aid of a federal grant pursuant to the Federal Water
Pollution Control Act Amendments of 1972, Public Law 92-500; and,
WHEREAS, said grant was processed by application to the
Texas Department of Water Resources and the Environmental
Protection Agency; and,
WHEREAS, it has become necessary that the project schedule
heretofore adopted in the above describe~ resolution must be
amended; NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PARIS, That the City of Paris does hereby adopt the project schedule
depicted on Exhibit A attached hereto; and,
BE IT FURTHER RESOLVED, That the City of Paris, as appli -
cant, understands that the project schedule, as amended, must be
approved by the Texas Department of Water Resources and the
Environmental Protection Agency and that once said project schedule
has been approved, no changes will be authorized without first re-
ceiving approval of the change from the Texas Department of Water
Resources and the Environmental Protection Agency.
Passed and adopted this 30th day of July, 1979.
t ~
,
Michael E. Malone, Mayor
ATTEST;
H. C. Greene, City Clerk ~
APPROVED TO FORM:
T. K. Haynes, ity Attorney
Proiect Schedule
Item
STEP 1 ,
A. Infiltration/Inflow Analysis
(with Evaluation Survey Plan of Study if
required) completed & subnu_tted to State
after Step 1 grant award.
Cal.endar Days
NA-- days
P. Infiltration/Inflow Evaluation Survey (if
required) completed & submitted to State Complete aays
after grant amendment for Survey.
C. Application for taaste Control
Permit (if required) made no later than 120 days
after Public Hearing notice for Facility_
Plan is issued.
D. Final Environmental Assessment and
Facility Plan (including time for draft
reports, advertisement & hearing)
completed and submitted to the State 395 days
after Step 1 grant amendment award.
STEP 2 '
A. User Charge System and Industrial
Cost Recovery System (if required)
developed and submitted to the State 365 days
after Step 2 grant award.
B. Preliminary Plan of Operation (if required)
completed and submitted to the State 365 days
after Step 2 grant award.
C. Final Plans and Specifications,
completed and submitted to State 5~8 days
after Step 2 grant award.
STEP 3
A. Advertise for Construction Bids within 30 days
after authorization to advertise for
bids has been issued.
B. Submit Bid Opening Documents within 105 days
after authorization to advertise for
bids has been i.ssued.
C. Award of Construction Contract within 3(,) days
after authorization to award the contract
has been issued.
D. Initiation of- Construction within 60 days
after the award of the contract.
F. Complete Constructior_ within 730 days
after inztiation of construction.