Loading...
09-CHANGE ORDER #1 WITH RICHARD DRAKE CONSTRUCTIONItem No. 9 memo�andum TO: City Council John Godwin, City Manager FROM: Shawn Napier, P.E., Director of Engineering, Planning & Development SUBJECT: CHANGE ORDER #1 WITH RICHARD DRAKE CONSTRUCTION CO. DATE: 3-4-2013 BACKGROITND: The City of Paris has been replacing sidewalks in downtown Paris over the past few years with grant money from the State. The City of Paris proposed to replace sidewalks on both sides of Bonham St. between 1 st St. and 2nd St. as well as a small area in front of the YWCA on Lamar Ave. At the September 24, 2012 City Council meeting, a grant application was authorized to be submitted to the Texas Capital Fund Main Street program to replace sidewalks. The City was not awarded the grant, but the new Capital Improvement Program has given the City the opportunity to fund this sidewalk replacement project. The City Council approved a contract with Richard Drake Construction in the amount of $130,705.85 at the February 25`�' City Council Meeting. STATUS OF ISSUE: This change order proposes to add two areas to the sidewalk replacement project and delete other areas from the approved contract. The small area in front of the YWCA on Lamar Ave. has been replaced by the Texas Department of Transportation (TxDOT) contractor and will therefore be deleted from the City contract with Richard Drake Construction Company. The ADA curb ramps at the northeast and southeast corners of Bonham and 1 S` St. have also been replaced by TxDOT. These two curb ramp areas will also be deleted from the existing contract. The proposed sections of sidewalk and driveways to be added to the contract include Grand Ave. in front of the Salvation Army and a section on SW 7th St. between Bonham St. and Grand Ave. BUDGET: The original bid amount from Richard Drake Construction Company was $130,705.85. The proposed change order #1 would be an increase of $21,669.20 (see attached Change Order #1 for details). If approved the new contract amount will be $152,375.05. This project will be funded from the Capital Improvement Program. RECOMMENDATION: Approve change order #1 to the contract with Richard Drake Construction Company. 32 Change Order Date of Issuance: February 26, 2012 Project: Downtown Sidewalk Replacement — Bonham Street +Project No.: HEI # 180060 Owner: City of Paris Contractor: Richard Drake Construction Co., LP of Contract: February 26, 2012 No. 1 The Contract Documents are mod�ed as follows upon execution of this Change Order: Description: Add sidewalk repair on 7�' SW from Bonham to Grand, and on Grand Ave between 2°d and 3`d, and adjust plan quantities to delete work recently performed by TacDOT. Justification: Additional areas of sidewalk need CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: $130,705.85 Original Contract Times: Substantial completion days: 105 Substantial completion date: _ [Increase] [Decrease] from previously approved [Increase] [Decrease] from previously approved Change Orders Change Orders No. to No. • No. to No. • $ Contract Price prior to this Change Order: $130,705.85 Increase of this Change Order: $21,66920 Substantial completion days: Substantial completion date: Contract Times prior to this Change Order: Substantial completion days: 105 Substantial completion date: (Increase� �Decrease� of this Change Order: Substantial completion days: Substantial completion date: Contract Price incorporating this Change Order: Contract "l�imes with all approved Change Orders: Substantial completion days: 105 $152,375.05 Substantial completion date: RECOMMENDED: ACCEPTED: ACCEPTED: : Engineer (Authorized Signature) Date: I� Owner (Authorized Signature) Date: 33 S Contractor (Authorized Signature) Date: Change Order #1 City of Paris Downtown Sidewalk Replacement - Bonham Street HEf #180060-280B February 26, 2012 Bid Item Description Quantity Unit Price Total Price Number 3 New sidewalk, includin inte ral curbs 122 SF 8.15 994.30 Curb ramp A w/warning pavers and 4 additional concrete 1 EA 5,481.00 5,481.00 14 #8 XHHW wire in conduit 720 LF 0.85 612.00 Removal & disposal of existing walk 20a (Area 1- YV1/CA) 228 SF 5.50 1,254.00 20b New sidewalk Area 1- YWCA 228 SF 10.30 2,348.40 Demo & reinstall integral curb, walk, and 21 retainin wall NE corner of 2nd and 1 LS 2,314.00 2,314.00 7th Street SW between Bonham and 22 Grand: 0.00 22a Remove concrete drive approach 588 SF 3.00 1,764.00 22b Remove concrete sidewalk 140 SF 3.00 420.00 22c Remove concrete curb and gutter 35 LF 15.00 525.00 22d Install new concrete drive approach 588 SF 7.50 4,410.00 22e Install new concrete sidewalk 140 SF 5.75 805.00 22f Install new concrete curb and gutter 35 LF 25.50 892.50 23 Grand Avenue Salvation Arm ): 0.00 23a Mobilization 1 LS 3,406.00 3,406.00 Removal and disposal of existing curbs 23b and sidewalk 1,216 SF 5.50 6,688.00 23c Install new sidewalk and int ral curb 1,216 SF 8.15 9,910.40 TOTAL CHANGE ORDER #1 $21,669.20 34