Loading...
15 - CHANGE ORDER #1 FOR CONTRACT B1 OF THE 2013 CIPItem No. 15 memorandum TO: City Council John Godwin, City Manager FROM: Shawn Napier, P.E., Director of Engineering, Planning & Development SUBJECT: CHANGE ORDER #1 FOR CONTRACT B1 OF THE 2013 CIP DATE: July 21, 2015 BACKGROUND: Contract B1 of the 2013 Water and Sewer Capital Improvement Program was awarded to B. Bray Construction in the amount of $2,425,002 at the October 13, 2014 City Council meeting. STATUS OF ISSUE: This request involves the request of 93 additional days to be added to the contract time. The majority (60) of the days are due to weather the other days (33) are because of additional work. Some of the additional work involved the contractor installing sewer alongside a fiber optic cable on 19th SW and additional sewer work along NW Loop 286. The change order amount of $18,030 is because it was discovered that a sewer line must be installed by open cut across 19th SW (FM 137) rather than by bore. This will be a longer process because of the TxDOT requirements and will involve closing the road for a few days. BUDGET: This will be funded from the 35- Million Dollar Bond. RECOMMENDATION: Authorize Change Order #I to Contract B 1 of the 2013 CIP. Change Order No.1 Date of Issuance: July 21,2015 Project: 2013 Bond Fund Water and Sewer Replacement Project Project No.: B1 B1 Owner: City of Paris Date of Contract: 12 -15 -14 Contractor: B. Bray Construction, Inc. The Contract Documents are modified as follows upon execution of this Change Order: Description: See Attachment 1 Justification: 60 of the additional 93 days are because of weather and the other 33 days are due to additional work. CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: Original Contract Times: Substantial completion days: 270 $2,425,002.00 Substantial completion date: September 11, 2015 Increase or Decrease from previously approved Increase from previously approved Change Orders Change Orders No. None: No. None: Substantial completion days: $0.00 Substantial completion date: Contract Price prior to this Change Order: Contract Times prior to this Change Order: No Changes Substantial completion days: 270 $2,425,002.00 Substantial completion date: September 11, 2015 Increase of this Change Order: $18,030.00 Contract Price incorporating this Change Order: $2,443,032.00 Increase of this Change Order: Substantial completion days: 93 Substantial completion date: December 13, 2015 Contract Times with all approved Change Orders: Substantial completion days: 363 Substantial completion date: December 13, 2015 RECOMMENDED: ACCEPTED: ACCEPTED: L-In Engineer (Authorized Signature) Date: Owner (Authorized Signature) Date: 0 Contractor (Authorized Signature) Date: B. Bray Construction Company, Inc. PO Box 6365 Paris TX 75461 Phone: (903) 784 - 4300 Fax: (903) 784 - 0725 To: Aaron Benson Contract B1 Job: Change Order for 19th Street Sewer Crossing Date 1 7/8/15 Description AMOUNT Lyon Barricade $10,210.00 52' of steel pipe $12,480.00 Dig and lay pipe $2,205.00 Type D & B mix $3,500.00 Select fill dirt $1,800.00 Remove one manhole $1,200.00 Mark up $1,005.00 Total $32,400.00 Credit of 52'@ $80.00 per foot - $4,160.00 Amount Due: $28,240.00 Street closure & Barricades by City of Paris .............Deduct ($10,210.00) Total $18,030