Laserfiche WebLink
mobilization charge. The total cost is $56,377.00 Staff proposes to add the resurfacing of <br />Hubbard Street to this contract in order to complete the work as soon as possible. <br />The addition of these three items along with minor adjustments for paving and crosswalk <br />changes, will increase the construction contract $136,294.65, bringing the total contract amount <br />to $3,058,412.30. <br />BUDGET: Funding is available in the 2017 Street Bond Fund. <br />RECOMMENDATION: Authorize a change order to the Church Street Reconstruction contract <br />with Richard Drake Construction in the amount of $136,294.65, and extending the contract time <br />by 57 calendar days. <br />