Laserfiche WebLink
8. Schedule <br />This schedule is not only contingent on Owner review and authorization to proceed for each Task, but <br />also regulatory and funding agencies review and response time. <br />Project Task <br />Start Date and Duration by Phase <br />Task 1 <br />A .. ®... 1 <br />415 days from Notice to Proceed, concurrent with following <br />Funding Assistance <br />Tasks <br />Task 2 <br />Su <br />120 days from Notice to Proceed <br />r _ .......... <br />Task 3 <br />Environmental <br />180 days from Notice <br />Y Notice to Proceed <br />Task 4 <br />eliminar Design Services <br />240 days from Notice to Proceed <br />Task 5 <br />270 days from Owner's acceptance of Task 3 services and <br />Final Design Services <br />Owners Notice to Proceed <br />Task 6 <br />120 days from Owner's Advertisement for Pre -Qualification of <br />Bidding ServicesContractors <br />AppendixScope <br />ImprovementsCity of Paris WWTP <br />