Laserfiche WebLink
8. Schedule <br />This schedule is not only contingent on Owner review and authorization to proceed for each Task, but <br />also regulatory and funding agencies review and response time. <br />Project Task <br />Start Date and Duration by Phase <br />Task 1 <br />415 days from Notice to Proceed, concurrent with following <br />Funding Assistance <br />Tasks <br />Task 2 <br />Surveys <br />120 days from Noticeto Proceed�����W <br />Task 3 <br />180 days from Notice to Proceed <br />Environmental <br />Task 4 <br />210 days from Notice to Proceed <br />PreliminaryDesign Services <br />....................................240mmdamm <br />Task 5 <br />_ <br />sm from Owner's acceptance <br />y p ance of Task 3 services and <br />Final Design Services <br />Owners Notice to Proceed <br />Task 6 <br />120 days from Owner's Adverbs........._____........... <br />ement for Pre -Qualification of <br />Phase 1 Biddin, Services <br />— .......�....... ..a ....... .................... .r...._._,,,,, ._ .. <br />Contractors <br />...................................,r ........... ..... ...................................................... <br />Appendix A - Scope of Services 9 of 9 <br />City of Paris WWTP Improvements <br />