<br /> -
<br /> Engineer's Estimate Barney Bray Construction
<br />ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL UNIT PRICE TOTAL
<br />1 Mobilization LS 1 $10,000.00 $10,000.00 $4,800.00 $4,800.00
<br />2 6" SDR 35 PVC Gravity Sewer LF 32 $10.00 $320.00 $4.50 $144.00
<br />3 8" SDR 35 PVC Gravity Sewer LF 98 $15.00 $1,470.00 $6.00 $588.00
<br />4 18" Ultra-Rib PVC Gravity Sewer LF 2025 $20.00 $40,500.00 $14.00 $28,350.00
<br />5 0'-5' Trench LF 145 $10.00 $1,450.00 $8.00 $1,160.00
<br />6 5'-8' Trench LF 520 $12.00 $6,240.00 $11.00 $5,720.00
<br />7 8'-10' Trench LF 1490 $14.00 $20,860.00 $13.00 $19,370.00
<br />8 Trench Safety LF 2010 $2.00 $4,020.00 $1.00 $2,010.00
<br />9 Standard Concrete Manhole 6' Deep EA 1 $2,500.00 $2,500.00 $3,300.00 $3,300.00
<br />10 Standard FiberQlass Manhole 6' Deep EA 10 $3,500.00 $35,000.00 $4,500.00 $45,000.00
<br />11 Additional Depth of fiberQlass Manhole VF 22 $180.00 $3,960.00 $150.00 $3,300.00
<br />12 Remove Manhole EA 5 $1,000.00 $5,000.00 $850.00 $4,250.00
<br />13 Man hole drop structure EA 1 $1,000.00 $1,000.00 $1,250.00 $1,250.00
<br />14 6" Main line Cleanout EA 1 $500.00 $500.00 $350.00 $350.00
<br />15 Manhole Marker EA 10 $50.00 $500.00 $40.00 $400.00
<br />16 4" Sewer Service, near side EA 3 $1,200.00 $3,600.00 $375.00 $1,125.00
<br />17 4" SDR 35 PVC Service line LF 100 $12.00 $1,200.00 $9.00 $900.00
<br />18 Concrete Encasement LF 40 $10.00 $400.00 $30.00 $1,200.00
<br />19 Rip Rap Repair LF 36 $5.00 $180.00 $60.00 $2,160.00
<br />20 Gravel Drive Repair EA 40 $8.00 $320.00 $20.00 $800.00
<br />21 Asphalt Repair LF 115 $25.00 $2,875.00 $25.00 $2,875.00
<br />22 Concrete Repair LF 15 $50.00 $750.00 $60.00 $900.00
<br />23 Concrete Channel Replacement LF 30 $300.00 $9,000.00 $60.00 $1,800.00
<br />24 8" Connection to existinQ main EA 2 $1,000.00 $2,000.00 $650.00 $1,300.00
<br />25 18" Connection to existing main EA 2 $3,000.00 $6,000.00 $1,600.00 $3,200.00
<br />26 Force Main Connection LS 1 $12,000.00 $12,000.00 $10,000.00 $10,000.00
<br />27 6" C-900 PVC LF 236 $15.00 $3,540.00 $12.00 $2,832.00
<br />28 6" Gate valv with box EA 1 $750.00 $750.00 $590.00 $590.00
<br />29 Misc FittinQs & Tie Ins LS 1 $4,000.00 $4,000.00 $1,500.00 $1,500.00
<br />30 ClearinQ & GrubbinQ all trees and brush LS 1 $5,000.00 $5,000.00 $4,200.00 $4,200.00
<br />31 Allowance for Unknown Conditions LS 1 $15,000.00 $15,000.00 $15,000.00 $15,000.00
<br /> Total $199,935.00 Total $170,374.00
<br />
<br />COST ESTIMATE (PINE MILL ROAD & NE LOOP 286 PHASE II)
<br />
|