Laserfiche WebLink
05/17 — Construction Start (Anticipated 9 month duration) <br />Current Tasks: ❑ Easement coordination <br />❑ Design Kickoff <br />Upcoming Tasks: ❑ Project Budget <br />SE Lift Station <br />Project Manager: <br />Carla Easton Design Engineer: AECOM <br />Inspector: <br />TED Contractor: TED <br />Estimated Cost: <br />$2,387,000 (Prelim Estimate) Billed to Date: $0 <br />Funding Source: <br />2013 Bond Fund <br />Description: <br />Replace /Upgrade the SE lift station. <br />Current Status: <br />Beginning design phase. <br />Key Dates: <br />03/09/16 — Design NTP issued <br />05/16 — Begin design by Hayter (6 months) <br />08/16 — Preliminary Plan Submittal <br />11/16 — Final Plan Submittal <br />01/17 — Bid Advertisement and Award (Depends on easement acquisition) <br />03/17 — Construction Start (Anticipated 12 month duration) <br />Current Tasks: ❑ Easement coordination <br />❑ Design Kickoff <br />Upcoming Tasks: ❑ Project Budget <br />❑ Easement acquisition <br />Page 4 of 4 <br />April 6, 2016 <br />